Performance outcomes                   Acceptable outcomes                     Response     Comment
                                       plan has the capacity to hold and
                                       retain the material within its
                                       boundaries during construction and
                                       operation of the development.
                                       Editor’s note: The use of dredged
                                       material for a beneficial purpose
                                       could include development of port or
                                       other marine facilities, use for
                                       construction or industrial purposes,
                                       or use to create or modify land or
                                       waters for an approved
                                       environmental outcome (such as
                                       creation of a bird roosting site).
                                       Further information about beneficial
                                       uses is contained in the National
                                       assessment guidelines for dredging,
                                       Australian Government Department
                                       of Environment, Water, Heritage and
                                       the Arts, 2009

Within a strategic environmental area: riparian and wildlife corridor functions
PO5 Natural regeneration of any        AO5.1 There is no impediments to        N/A          The proposed deck is not located in a
cleared or work area is facilitated    the natural regeneration of native                   strategic environmental area.
wherever possible.                     plant species in the area of clearing
                                       and works following completion of
                                       works.

Within a strategic environmental area: hydrological processes
PO6 Development avoids or              No acceptable outcome is                N/A          The proposed deck is not located in a
minimises impacts on natural           prescribed.                                          strategic environmental area.
drainage lines or flow paths, during
both construction and operation.
Within a strategic environmental area: water quality
PO7 Development avoids or              AO7.1 Development demonstrates          N/A          The proposed deck is not located in a
minimises any adverse impacts on       best practice environmental                          strategic environmental area.
environmental values and water         management to meet relevant
quality objectives for receiving       environmental values and water
waters (surface and groundwater)       quality objectives of the
from pollutants on site or leaving a   Environmental Protection (Water)
site located in a strategic            Policy 2009.
environmental area.
                                       OR

                                       AO7.2 All stormwater, wastewater,       N/A          The proposed deck is not located in a
                                       discharges and overflows leaving the                 strategic environmental area.
                                       site are:

                                       (1) treated to the quality of the
                                            receiving waters prior to
                                            discharge, OR;

                                       (2) reclaimed or re-used such that
                                            there is no export of pollutants
                                            to receiving waters.




State development assessment provisions                                              Module 10 — Coastal protection     10.1
Tidal works, or development in the coastal management district state code
23 November 2015 V1.7

                                                                                                     Page 13 of 13

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Development Assessment Report.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.