Prelim Construction Management Plan[1]
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn • Activities are to only be conducted during suitable weather conditions.
• A water truck or spray apparatus is to be provided on site if required.
• Exposed areas such as cleared areas and stockpiles are to be watered and kept
damp in order to minimise erosion or the potential for dust creation.
• Vehicle speed is to be limited on site to minimise dust generation.
• Trucks entering or exiting the site shall have their loads covered
• All construction vehicles exiting site shall pass through a wheel wash down and/or
drive over a shake down grid which will be located at the site entry /exit.
• Haulage routes shall avoid residential areas and use sealed roads where possible.
• Machinery shall be fitted dust filters all equipment and vehicles are to meet relevant
emission standards.
• Maintenance of wind breaks and barriers where possible.
5.4 Stormwater and Sediment Control
Excavation – At the commencement of these works, screens and bunding at the perimeter of the
site where stormwater may run off will be installed. Bunding will also be implemented around
stormwater drains. Diligent housekeeping will be implemented to minimise risk of dust/debris being
washed into pits.
RG Strategic Preliminary Construction Management Plan 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.