WATER QUALITY & DRAINAGE CODE
Performance Criteria and Acceptable Solution
Noosa Civic Stage 2 Retail Development
29 September 2023
PERFORMANCE OUTCOMES ACCEPTABLE OUTCOMES RESPONSE
Stormwater drainage design
PO1 AO1 RO1
The development and its stormwater management system is A stormwater management plan is prepared consistent
planned and designed having regard to: with PSP6 Engineering Design Standards - Roads, drainage A stormwater management plan has been prepared for the
1. the natural features of the site; and earthworks proposed development to ensure compliance with the
2. the need to avoid impacts and potential risks requirements of the Noosa Plan.
to ecologically important areas;
3. the likely effectiveness of erosion and sediment
control and stormwater drainage measures during
rainfall events during and post construction; and
4. the need to protect environmental values and water
quality of receiving waters both during and post
construction.
PO2 AO2.1 A stormwater management plan has been prepared for the
Stormwater drainage infrastructure is planned, designed and
constructed to: Stormwater drainage planning, design and construction is in proposed development to ensure compliance with the
accordance with PSP6 Engineering Design Standards - requirements of the Noosa Plan. Stormwater drainage
1. incorporate allowance for increased flood risk and Roads, drainage and earthworks and the latest version of systems including stormwater treatment have been included
tidal inundation through pipework as a result of the Queensland Urban Drainage Design Manual. as part of the proposed development and connect into the
cilmate change and sea level rise;
existing Noosa Civic Stormwater system.
2. ensure the development is adequately drained; and
AO2.2
3. ensure stormwater is managed and lawfully
discharged without altering stormwater drainage The stormwater drainage system connects to a lawful point
characteristics external to the site. of discharge in accordance with PSP6 Engineering
Design Standards - Roads, drainage and earthworks.
AO2.3
Stormwater flows discharging from the development are
demonstrated to be consistent with pre-development
characteristics.
https://mpncnetau.sharepoint.com/sites/administration/shared documents/9000-9999/9900-9999/9954/codes/29-09-23 water quality & drainage code.docx
Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix C- Civil Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.