WATER QUALITY & DRAINAGE CODE
Performance Criteria and Acceptable Solution
Noosa Civic Stage 2 Retail Development
29 September 2023
PERFORMANCE OUTCOMES ACCEPTABLE OUTCOMES RESPONSE
excess of 0.8m for any water quality treatment device.
Hydrology and waterway stability
PO10 AO10 No increase in peak runoff from site will occur as part of the
The development is designed to:
Development prevents increased bed and bank erosion and 1. limit the peak 1 year ARI event discharge within the proposed development. Refer Stormwater Management Plan
sedimentation in receiving waterways by avoiding changes receiving waterway to the pre-development peak 1 for further information.
in low rate, peak flow run-off and flow duration. year discharge;
2. maximise pervious areas by using pervious
alternatives for otherwise impervious areas wherever
possible;
3. provide for capture and reuse of stormwater for non-
potable purposes for gardening, toilet flushing,
laundry and hot water supply uses;
4. incorporate appropriate detention features; and
5. incorporate natural channel design principles
Editor’s note: The Sustainable Building Design
Code includes requirements for stormwater capture and
reuse.
PO11 AO11.1 No new stormwater conveyance channels are proposed as
Water sensitive urban design principles are applied to The design and construction of a natural channel or natural part of the development.
achieve multifunctional design of waterways, wetlands and channel rehabilitation works are in accordance with the
drainage lines that provide for: Natural Channel Design Guidelines (Brisbane City
Council) having regard to local topography, geology and
1. stormwater conveyance that uses natural channel geomorphology. Bioretention basins will be utilised for the treatment of
design;
AO11.2 stormwater runoff. Refer Stormwater Management Plan for
2. protection of landscape features and ecological
important areas including terrestrial and aquatic further information.
habitat; Landscape features, plant species and habitat types used in
3. aesthetic and passive recreation values; stormwater conveyance channels are complementary to the
4. flood management and conveyance of external local context and natural waterways.
catchment stormwater through the development;
5. landscaping that incorporates local native species; AO11.3
and
Bank and bed stability and planting densities result in a
https://mpncnetau.sharepoint.com/sites/administration/shared documents/9000-9999/9900-9999/9954/codes/29-09-23 water quality & drainage code.docx
Page 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix C- Civil Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.