20220237 73 Southern Cross Pde SWMP
Original PDF page 1, section 1. The text section number identifies this passage in the reader.
73 Southern Cross Parade 20220237 Izarox Qld Pty Ltd Stormwater Management Plan November 2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.
Full text of sections 2 to 16 (of 39)
Section 2
Document control record
Document prepared by:
RECOR Pty Ltd
ABN 89 647 469 707
75 Noosa Drive
Noosa Heads, QLD 4567
Australia
T +61 7 5211 1003
E [email protected]
W recorconsulting.com
A person using RECOR documents or data accepts the risk of:
a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard
copy version.
b) Using the documents or data for any purpose not agreed to in writing by RECOR.
Document control
Report title Stormwater Management Plan
Document code 20220214-SWMP01 Project number 20220237
File path C:\12dS\data\RecorSYN\20220214 12 Wyandra St, Noosa Heads_645\03 Engineering\02
Reports\20220214 12 Wyandra St SWMP.docx
Client Izarox Qld Pty Ltd
Client contact - Client reference -
Rev Date Revision details/status Author Reviewer Verifier Approver
(if required)
1 1/11/2022 Initial Version BP BP
Current revision 1
Approval
Author signature Approver signature
Name B. Parry Name B. Parry
RPEQ: 28084
Title Civil Engineer Title Civil Engineer
recorconsulting.com
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567
E [email protected]
Section 3
Contents
Introduction..........................................................................................................................................4
Site Details ...........................................................................................................................................5
2.1. Existing Site Description & Drainage .................................................................................................. 5
2.2. Existing Drainage Patterns .................................................................................................................. 5
2.3. Proposed Development Drainage Pattern ......................................................................................... 6
Stormwater Quantity ............................................................................................................................7
3.1. Pre-Post Comparison .......................................................................................................................... 7
Stormwater Quality ..............................................................................................................................9
4.1. Construction Phase .............................................................................................................................. 9
4.2. Operational Phase ............................................................................................................................ 10
Conclusion ........................................................................................................................................ 11
Appendices
Appendix A
Proposed Development Plans
Appendix B
DRAINS Modelling Parameters and Results
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
recorconsulting.com
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected]
Section 4
INTRODUCTION
RECOR has been engaged to prepare a Stormwater Management Report to accompany a development application
for a residential duplex development located at 73 Southern Cross Parade, Sunrise Beach.
This report investigates the stormwater management considerations for the existing and proposed development
site and assesses how the run-off from the site is to be managed in accordance with Noosa Shire Council
requirements for stormwater drainage.
Page 4 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 5
SITE DETAILS
2.1. Existing Site Description & Drainage
The existing site, known in real property terms as Lot 672 RP 225123, is located at 73 Southern Cross Parade. The
existing site contains a residential dwelling on a site area of 810m². The site is bounded to the east by Southern Cross
Parade with the remaining surroundings to the north, south and west being residential properties.
2.2. Existing Drainage Patterns
The subject site is located on a moderately sloping hill with the natural surface contours falling to the north at
between 15% to 20%.
The surface run-off from the existing developed site typically drains as overland sheet flows across the property
draining towards the adjacent lot to the north. The built form of the adjacent lots south of the site act as a barrier to
any significant upstream catchments, with only small areas of the upstream ground likely to be conveyed into the
property. Due to sandy soils typically present in the locality, the run-off is likely to infiltrate as it is conveyed
downstream.
Roof run-off is conveyed by downpipes below ground to the kerb in front of the site in southern Cross Parade, where
a piped outlet was observed as the discharge point for this run-off. A stormwater inlet pit approximately 20m north
of this outlet is the nearest stormwater infrastructure located within the street.
Figure 2.1 - Site Locality Plan (Noosa Council Intramaps, 2022)
Page 5 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 6
Nearest
SW Inlet
Typical
overland
flow Kerb outlet to
roof drainage
Figure 2.2 - Site Drainage Characteristics (Noosa Council Intramaps, 2022)
2.3. Proposed Development Drainage Pattern
2.3.1 Stormwater Concept
Roof run-off from the new building will be drained via downpipes into an internal stormwater drainage which will
carry surface and roof run-off from the proposed development to discharge via new kerb adaptor outlets to replace
the existing discharge point of the roof run-off. The kerb adaptor outlets are proposed as the Lawful Point of
Discharge for the development.
Overland flow paths along the western and southern boundary will provide fall for upstream run-off to be conveyed
around the site, while the pits within the site will provide collection points to allow for the small areas of upstream
run-off that may reach the subject site.
The remaining typically pervious areas of the site will drain as overland surface flows infiltrating into the site soils
consistent with the current drainage conditions.
The roof and allotment drainage system for the proposed site shall be designed to comply with:
1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards – Roads, drainage and
earthworks;
2. The Queensland Urban Drainage Manual (QUDM); and
3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.
Refer to Appendix A Proposed Development Plan for the proposed stormwater drainage layout plan illustrating
the concept described above.
Page 6 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 7
STORMWATER QUANTITY
3.1. Pre-Post Comparison
As the development proposes to increase the impervious area of the site, there is likely to be an increase in peak
flows discharged from the site. The site has therefore been modelled using the DRAINS software to assess the impact
on peak flows, comparing the existing site conditions to the proposed development.
In accordance with ARR2019, an Initial Loss-Continuing Loss (IL-CL) model has been used to assess the site against
the ensemble of storm temporal patterns for the East Coast North region. The loss parameters and temporal patterns
have been imported from the ARR Datahub, and rainfall intensities have been imported from the Bureau of
Meteorology IFD rainfall data allowing for a 20% increase to rainfall depths to account for future climate change
patterns.
The parameters obtained from the Australian Rainfall and Runoff (ARR) Data Hub for the location and the rainfall
IFD data obtained from the Bureau of Meteorology have been imported into DRAINS to generate the storm events.
The models have been run using the ensemble of storm events for 1EY, 50%, 0.2EY, 10%, 5%, 2% and 1% Annual
Exceedance Probability (AEP) for durations from 1 minutes to 12 hours to determine the critical storm duration and
the mean peak flowrate from the storms. Refer to Appendix B DRAINS Modelling Parameters and Results for details
of the parameters used and summary of the results from the modelling.
Due to the small site area, the pre and post development conditions have been modelled each as a single catchment
made up of the impervious areas as measured from survey and the proposed architectural design. A minimum time
of concentration of 5 minutes has been nominated for all surfaces within the catchment. The configuration of the
catchment areas for pre-development, post-development and split post development for roofwater to an attenuation
tank are shown in Figure 3.1 – DRAINS Pre-development catchment and Figure 3.2 – DRAINS Post-development
catchments respectively.
Figure 3.1 – DRAINS Pre-development catchment
Page 7 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 8
Figure 3.2 – DRAINS Post-development catchments
The results of the modelling against the range of design storms for the development under the existing and
proposed development conditions are shown in Table 3.1 Existing and proposed unmitigated site peak discharge
rates.
Table 3.1 Existing and proposed unmitigated site peak discharge rates
Wyandra Street
Qchange
A.E.P Qexisting Qproposed Qchange (%)
(m³/s) (m³/s) (m³/s)
63.2% AEP 0.022 0.024 0.002 9%
0.5 EY 0.029 0.031 0.002 7%
0.2 EY 0.038 0.041 0.003 8%
10% AEP 0.049 0.049 0.000 0%
5% AEP 0.055 0.056 0.001 2%
2% AEP 0.064 0.064 0.000 0%
1% AEP 0.072 0.072 0.000 0%
The results show that the site has increased the total peak flows from the site for a number of storm events however
these changes are typically restricted to the more frequent less severe storm events, where pervious areas have
greater impact through infiltration losses.
The overall magnitude of the increase resulting from the development is small, with a maximum increase of 3L/s
predicted by the modelling for any storm event. This level of change is not considered likely to result in any significant
impacts or damage to the downstream receiving environment and therefore no attenuation is considered necessary
for the proposed development.
Page 8 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 9
STORMWATER QUALITY
The following sections discuss the stormwater quality considerations for the construction and operational phase of
the development.
4.1. Construction Phase
4.1.1 Erosion and Sediment Control Measures
During construction, it is necessary to manage stormwater run-off to avoid potential contamination of downstream
waterways from sediments and other pollutants from the site. A range of best practice sediment and erosion controls
should be implemented on the development to ensure negative impacts to the downstream receiving environment
are mitigated.
As the area being developed is below 2,500m², the development’s construction will be managed using best practice
erosion and sediment control principles in line with the desired outcomes of Appendix 2 of the SPP (DERM, July
2017), which are shown below in Figure 4.1.
Figure 4.1 SPP 2017 Construction Phase Stormwater Management Design Objectives
A site-specific erosion and sediment control plan shall be prepared as part of a future submission for Operational
Works approval. Suitable erosion and sediment controls for the site may include:
1. Sediment fencing along downstream of the work areas within the site to prevent sediment from leaving the
construction area.
Page 9 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 10
2. A shakedown area is to be installed at the construction entry/exit to the proposed development area to
minimise sediment being transported to and from the site.
3. Diversion of upstream run-off around any exposed areas using diversion drains around the site.
4.2. Operational Phase
The development consists of a small lot duplex consistent in character with the existing residential dwelling. The
proposed development is not considered to significantly alter the pollutant generation potential of the site, and
therefore no additional stormwater quality treatment is proposed for the development.
Page 10 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 11
CONCLUSION
This Stormwater Management Report has outlined how the stormwater run-off from the site is to be managed to
comply with the relevant requirements and minimise any adverse impacts to the downstream catchments.
• Run-off from the development will be managed through an internal drainage network of pits and pipes to
capture and convey run-off to the lawful point of discharge from the development, being kerb adaptor
outlets in the Southern Cross Parade Street frontage. Run-off from impervious areas and the roof drainage
will be conveyed and discharged at this location in the north-eastern corner of the site.
• Overland flow paths along the western and southern boundary will provide conveyance for upstream run-
off. The internal pits will capture any excess run-off arriving in the site from upstream.
• The existing and proposed development site have been modelled for the ensemble of storm events for the
site, which found there would be an insignificant increase to the peak discharge characteristics of the site
being a maximum of 3L/s. This level of increase is not likely to result in significant impacts to the downstream
environment, therefore no attenuation is proposed for the development.
• During construction, erosion and sediment control measures are to be implemented to minimise potential
contaminants impacting the downstream receiving environment in line with the objectives of Appendix 2 of
the SPP.
• As the development is a small residential site that does not significantly alter the pollutant generating
characteristics of the site, stormwater quality treatment is not proposed for the development.
• The proposed stormwater solution is considered to suitably address the stormwater quality and quantity
requirements of the Noosa Council Planning Scheme and minimise any adverse impacts to the downstream
environment arising from the stormwater run-off from the proposed development.
Page 11 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 12
Appendix A
Proposed Development Plans
Page 12 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
Section 13
PROPOSED RESIDENTIAL DUPLEX
73 SOUTHERN CROSS PARADE SUNRISE BEACH QLD 4567
LOT 672 ON RP225123
CIVIL WORKS
DR
XCEN
DRAWING SCHEDULE
N
BEN LE
DRAWING NUMBER DRAWING TITLE
ED
W
AR
DS
001 COVER SHEET AND LOCALITY PLAN
EENIE C
ST
002 GENERAL NOTES REEK R
D
003 EXISTING SERVICES AND DEMOLITION LAYOUT PLAN
010 DRIVEWAY LAYOUT PLAN
HE
020 BULK EARTHWORKS LAYOUT PLAN AT
HLA
ND
021 EARTHWORKS LONGITUDINAL SECTIONS DR
030 EROSION AND SEDIMENT CONTROL LAYOUT PLAN
DR
031 EROSION AND SEDIMENT CONTROL DETAILS
XCEN
040 STORMWATER LAYOUT PLAN
045 STORMWATER CATCHMENT LAYOUT PLAN
BEN LE
046 STORMWATER LONGITUDINAL SECTIONS
060 VEHICLE SWEPT PATHS PLAN SHEET 1 OF 4
061 VEHICLE SWEPT PATHS PLAN SHEET 2 OF 4
062 VEHICLE SWEPT PATHS PLAN SHEET 3 OF 4
ED
063 VEHICLE SWEPT PATHS PLAN SHEET 4 OF 4
W
AR
064 VEHICLE SWEPT PATHS VERTICAL PLAN
DS
SOUTHERN CROSS PARADE
ST
LOT 672
ON RP 225123
HE
CEN DR
AT
HL
AN
D
DR
BEN LEX
LOCALITY PLAN
SCALE 1:2000
CLIENT DETAILS: PROJECT ADDRESS: APPROVED BY: PROJECT NAME:
PROPOSED RESIDENTIAL DUPLEX
IZAROX QLD PTY LTD TITLE: STATUS:
73 SOUTHERN CROSS PARADE COVER SHEET & FOR APPROVAL - NOT FOR
© ABN 89 647 469 707
SUNRISE BEACH, QLD, 4567 BEN PARRY LOCALITY PLAN CONSTRUCTION
75 NOOSA DRIVE RPEQ: 28084
01 31/10/22 MCU / OPW ISSUE MVP BRP BRP SCALE:
NOOSA HEADS, QLD 4567 CPEng
+61 7 5211 1003 REV DATE DESCRIPTION DWN CHK APP 1:100 DATE: 31/10/2022
DRAWING NUMBER: PROJECT NUMBER: SHEET REV:
RECORCONSULTING.COM REVISIONS
DO NOT SCALE, IF IN DOUBT ASK
001 20220237
SIZE:
A1 01
Section 14
GENERAL NOTES ANDSTOCKPILE ON SITE OR REMOVE FROM SITE AS DIRECTED. STRUCTURAL FILL. REQUIREMENTS OF THE GEOTECHNICAL ENGINEER AS OUTLINED IN THE
19. DRAWINGS TO BE READ IN CONJUNCTION WITH ARCHITECT, SURVEYOR, 3. UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR GEOTECHNICAL INVESTIGATION REPORT BY TECTONIC. TEMPORARY
1. ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN. HYDRAULICS, ETC. CONSULTANT AND CONTRACTOR DRAWINGS. SOFT MATERIALS ENCOUNTERED SHOULD BE REMOVED DURING UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE FORMED
SUBGRADE PREPARATION FOR BULK EARTHWORKS. ALL UNSUITABLE AT 1V:2H, AND IN MEDIUM DENSE SAND AT 1V:1H FOR BATTERS UP TO
2. ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE 20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT MATERIAL TO BE REMOVED FROM SITE AT CONTRACTORS EXPENSE. 3M IN HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY THE
CONTRACTOR. CONTRACTOR TO ALLOW FOR ALL MEANS NECESSARY AUTHORITY: ROAD OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN GEOTECHNICAL ENGINEER.
TO ACCURATELY SETOUT THE WORKS. FOR ALL WORKS WITHIN COUNCIL ROAD RESERVES. CONTRACTOR TO 4. COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES
ALLOW FOR ALL COSTS ASSOCIATED WITH IMPLEMENTATION OF THE SUBSTANTIAL VOLUMES OF WATER COMBINED WITH VIBRATORY 21. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE
3. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT TMP. COMPACTION EQUIPMENT. CARE MUST BE TAKEN TO ENSURE THERE ACHIEVED, TEMPORARY SHORING WILL BE REQUIRED UNDER THE
SPECIFICATIONS AND WHERE FURTHER DETAILS ARE REQUIRED THE ARE NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE ADVICE OF A SPECIALIST SHORING CONTRACTOR.
CONTRACTOR SHALL REFER TO NOOSA SHIRE COUNCIL DEVELOPMENT 21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL COMPACTED IN ACCORDANCE WITH GEOTECHNICAL REPORT AND
GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES, ASSOCIATED AUTHORITY APPROVALS RECEIVED FOR THE PROJECT AND IN AS1289. 22. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE
STANDARD DRAWINGS AND SPECIFICATIONS U.N.O. ACCORDANCE WITH OPW APPROVALS BY COUNCIL. SPECIFIC DESIGN TO PREVENT UNDERMINING WHICH SHOULD BE
5. A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE CARRIED OUT BY A SUITABLY QUALIFIED AND EXPERIENCED RPEQ
4. SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED 22. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE REQUIRED ON SOIL SUBGRADES ALONG HAUL ROADS AND LAYDOWN STRUCTURAL ENGINEER.
OUTSIDE OF THE TOLERANCES SPECIFIED WITHIN THE PROJECT BOUNDARY WITHOUT FORMAL APPROVAL BY THE OWNER/CUSTODIAN AREAS TO IMPROVE TRAFFICABILITY. SPECIFIC PLATFORM DESIGN
SPECIFICATION AND LOCAL AUTHORITY REQUIREMENTS, THE OF THAT LAND INCLUDING BUT NOT LIMITED TO PRIVATE PROPERTY, WOULD BE REQUIRED PRIOR TO MOBILISATION AND TRAFFICKING OF 23. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT
CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS. ANY HEAVY MOBILE PLANT ON THE SITE. ANY CONSTRUCTED CUT/FILL BATTERS AND RETAINING STRUCTURES
ADDITIONAL COSTS INCURRED BY RECOR. ON THE SITE HAVE ACHIEVED ADEQUATE STABILITY WITH A LONG-TERM
23. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION 6. IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND FACTOR OF SAFETY AGAINST GEOTECHNICAL FAILURES TO THEIR
5. EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND DRAWINGS AND APPROVALS ON SITE AT ALL TIMES. COMPACTED WHERE UNSUITABLE NATURAL MATERIALS ARE LOCATED SATISFACTION.
AS SUCH THEIR ACCURACY CANNOT BE GUARANTEED. NO AND AS OTHERWISE NECESSARY TO OBTAIN SUBGRADE/PLATFORM
RESPONSIBILITY IS TAKEN BY RECOR OR THE PRINCIPAL FOR THE LEVEL. IMPORTED GENERAL FILL MATERIAL SHALL BE CLEAN GRADED 24. EARTHWORKS LEVELS SHOWN ARE FINISHED SURFACE LEVELS
24. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN
ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE MATERIAL FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM INCLUSIVE OF TOPSOIL LAYER. REFER TO STRUCTURAL ENGINEERING
ACCORDANCE WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN
RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH PARTICLE SIZE OF 100MM AND CAPABLE OF BEING COMPACTED INTO DRAWINGS FOR BUILDING SLAB THICKNESSES AND HYDRAULIC
AND CONSTRUCTION CODE (2013).
THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR THE COHERENT FILLING TO THE SPECIFIED STANDARD. THE MATERIAL DRAWINGS FOR SUB-FLOOR DRAINAGE FOR DETERMINATION OF
COMMENCEMENT OF ANY WORKS. ANY DISCREPANCIES SHALL BE SHALL HAVE A MAXIMUM PLASTICITY INDEX OF 15%, A SHRINK-SWELL REQUIRED BULK EARTHWORKS SURFACE.
REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO LOCATE AND STANDARD SIGNS AND LINE MARKING NOTES INDEX OF LESS THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS. 1. GENERAL 25. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE
a. ALL SIGNS AND PAVEMENT MARKING IS TO BE IN ACCORDANCE WITH 7. ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE GEOTECHNICAL ENGINEERS REQUIREMENTS. CONTRACTOR TO ALLOW
6. THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND THE QUEENSLAND TRANSPORT MANUAL OF UNIFORM TRAFFIC CONTENT FOR STANDARD COMPACTION. FOR THE IMPORT AND REMOVAL OF ALL NECESSARY MATERIAL TO
SURVEY ALL CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS CONTROL DEVICES (CURRENT EDITION). UNDERTAKE THE PRELOADING OPERATIONS.
SHOWN ON THE DRAWINGS INCLUDING ANY POTENTIAL EXISTING 8. ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE
2. SIGNS
SERVICES CLASHES PRIOR TO COMMENCEMENT OF CIVIL WORKS. PROPERTY BOUNDARY OF THE SUBJECT SITE, INCLUDING REAR OF
a. ALL SIGNS TO BE REFLECTORISED CLASS 1 TO AS1906.1:2007 UNLESS 26. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RETAINING WALL DRAINAGE INFRASTRUCTURE FOR RETAINING WALLS
RECOR AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL NOTED OTHERWISE.
IN CUT. RETAINING WALLS ARE TO BE PREPARED IN ACCORDANCE WITH
WORKS. b. SIGNS ARE TO BE INSTALLED WITH THE FOLLOWING CLEARANCES TO STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE
EDGE OF SIGN: LOCATION CLEARANCE NO KERB 600 BEHIND GUIDE WITH CONSTRUCTION REQUIREMENTS OF GEOTECHNICAL REPORT. INSPECTIONS:
7. ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS POSTS BARRIER KERB 300 FROM FACE MOUNTABLE KERB 500 FROM THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS
SHALL BE RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS, FACE OF KERB. 9. REFER ARCHITECT/LANDSCAPE ARCHITECT DRAWINGS FOR BEFORE ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR
FOOTPATHS, CONCRETE AREAS, GRAVEL AREAS, GRASSED AREAS AND CONFIRMATION OF RETAINING WALL COLOUR AND FINISH. IS TO PROVIDE A MINIMUM OF 72 HOURS NOTICE TO RECOR FOR REQUIRED
ROAD PAVEMENTS. c. PARKING CONTROL SIGNS TO BE MOUNTED TO FACE APPROACHING
INSPECTIONS. SHOULD THE CONTRACTOR FAIL TO REQUEST AN
TRAFFIC AT 45° TO KERB OR CARRIAGEWAY EDGE. ALL OTHER SIGNS TO INSPECTION, THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL COSTS TO
10. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 2'
8. CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO BE TURNED AWAY BY 5° FROM THE NORMAL TO APPROACHING ALLOW FOR THE WORKS TO BE INSPECTED TO THE SATISFACTION OF
SOIL ENGINEERING SUPERVISION IN ACCORDANCE WITH APPENDIX B OF
AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR HEADLIGHT. AS 3798. THE NOMINATED GEOTECHNICAL TESTING AUTHORITY SHALL RECOR. ANY INSPECTIONS THAT FAIL ARE TO BE RE-INSPECTED WITH ALL
REINSTATEMENT TO BE CARRIED OUT IMMEDIATELY TO THE 3. SIGN SUPPORTS PROVIDE CERTIFICATION THAT ALL GENERAL EARTHWORKS REINSPECTION COSTS TO BE PAID BY THE CONTRACTOR.
SATISFACTION OF INFRASTRUCTURE OWNER/MANAGER / a. SLEEVED SIGNS SUPPORTS ARE TO BE PROVIDED IN ALL AREAS OPERATIONS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE
AUTHORITY/COUNCIL. DRAWINGS AND SPECIFICATIONS AND THE CONTROLLED FILL IS a. PRESTART
WHERE THEY ARE IN A PAVED SURFACE.
4. LINEMARKING SUITABLE FOR PURPOSE TO THE REQUIRED BEARING CAPACITY UNDER
9. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL a. REDUNDANT LINEMARKING IS TO BE GROUND OFF. THE PLATFORM/STRUCTURES AS SPECIFIED BY THE GEOTECHNICAL b. EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF
WORKPLACE HEALTH AND SAFETY REQUIREMENTS. REPORT. SEDIMENT AND EROSION CONTROL MEASURES UNSUITABLE GROUND
b. THERMOPLASTIC LINEMARKING TO BE USED FOR ALL CONCRETE.
10. WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN 11. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED
c. SIDE AND CUT OFF DRAINS
CLOSE PROXIMITY TO NEIGHBOURING LOT BOUNDARIES OR JOINTING NOTES TO 98% STANDARD MAXIMUM DRY DENSITY OR A DRY DENSITY INDEX
INFRASTRUCTURE, CONTRACTOR TO ALLOW IN SCOPE OF WORKS TO OF AT LEAST 75% IN ACCORDANCE WITH THE GEOTECHNICAL REPORT
PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY OF 1. ALL JOINTING AND CONCRETE TO BE IN ACCORDANCE WITH THE IN LAYERS OF 250MM LOOSE THICKNESS (PRIOR TO COMPACTION). d. STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL
EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE REQUIREMENTS OF AS3727.1:2016.
USE OF LOW VIBRATION EQUIPMENT, TRENCH SHORING ETC AS 2. SAW CUT JOINTS MUST BE:
12. COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO e. STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT
REQUIRED. a. BETWEEN 1 AND 1 OF CONCRETE PAVEMENT DEPTHS. TESTS PER VERTICAL LIFT WHERE STRUCTURAL FILL HEIGHTS EXCEED
4 3 300MM IN ACCORDANCE WITH AS3798. CONTRACTOR TO UNDERTAKE
f. STORMWATER STRUCTURE BASE SLABS
11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON b. CLEARED OF ANY DEBRIS FROM THE CUTTING METHOD. ALL EARTHWORKS TESTING IN ACCORDANCE WITH GEOTECHNICAL
THESE DRAWINGS, THE CONTRACTOR IS TO NOTIFY RECOR AND ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.
c. PERFORMED WITHIN 6 TO 12 HOURS OF FINISHING CONCRETE POURS. g. PAVEMENT SUBGRADE
RECEIVE WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
3. DOWELL BARS MUST BE INSTALLED EXACTLY 90° TO THE FACE OF JOINT
13. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN
12. CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL TO ALLOW EXPANSION AND CONTRACTION MOVEMENTS.
ACCORDANCE WITH LANDSCAPE DRAWINGS. h. PAVEMENT REINFORCING
CONSTRUCTED WORKS IN ACCORDANCE WITH LOCAL GOVERNMENT 4. JOINTING LAYOUT TO BE CONFIRMED BY SUPERINTENDANT PRIOR TO
REQUIREMENTS. UNLESS OTHERWISE ADVISED BY RECOR CONSTRUCTION COMMENCING. LAYOUT SHOULD AVOID ACUTE ANGLES
IN THE CONCRETE SLAB AND AVOID MISMATCHED JOINTS. 14. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS. i. PAVEMENT PRIOR TO SEALING (PRESEAL)
CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.
5. JOINT SEALANTS WHERE USED MUST ADHERE TO SIDE OF JOINT FACES
ONLY AND SHALL NOT EXTEND ABOVE SIDES OF JOINTS ONTO THE SLAB 15. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED j. RETAINING WALL FOOTING REINFORCING
13. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH
SURFACE. MANAGEMENT PLANS.
RELEVANT APPROVALS.
6. DOWEL BARS ARE TO BE
a. FOR 100MM THICK SLAB, 12MM Ø OF LENGTH 300MM AND SPACED AT 16. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES k. RETAINING WALL BLOCKWORK PRIOR TO CORE FILL
14. CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL,
400MM CENTRES ARE INSTALLED INCLUDING BUT NOT LIMITED TO SHAKE DOWNS, SILT
LANDSCAPE AND OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL
b. FOR 125MM THICK SLAB, 16MM Ø OF LENGTH 350MM AND SPACED AT FENCE ETC IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL l. STEEL REINFORCEMENT OF CONCRETE STRUCTURES
CONSTRUCTION.
PLAN
300MM CENTRES
15. CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR c. FOR 150MM THICK SLAB, 20MM Ø OF LENGTH 400MM AND SPACED AT m. PRACTICAL COMPLETION
17. ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL
DEMOLITION WORKS COMMENCING ON SITE. 300MM CENTRES BATTERS OR RETAINING WALLS (TEMPORARY OR PERMANENT) AS PER
RELEVANT AUSTRALIAN STANDARDS AND LEGISLATION. n. ON MAINTENANCE
16. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES,
ROADS AND SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM EARTHWORKS NOTES 18. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON o. OFF MAINTENANCE
SITE U.N.O.
1. FOR DETAILED GEOTECHNICAL INFORMATION, REFER GEOTECHNICAL UNPAVED ROADS, ACCESS TRACKS AND STOCKPILES AT A SUFFICIENT
INVESTIGATION REPORT BY GEOTECHNICAL ENGINEER. IT IS LEVEL TO SUPPRESS DUST GENERATION. ADDITIONALLY CONTRACTORS p. ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER
17. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING ARE TO COVER OR ENCLOSE STOCKPILES WHERE REASONABLY
RECOMMENDED THAT THE GEOTECHNICAL CONSULTANT BE DEVELOPMENT APPROVAL)
PROPERTIES AND COUNCIL ROADS AND VERGES PRIOR TO PRACTICAL TO RESTRICT DUST MOVEMENT.
CONTACTED TO CONFIRM THE SOIL CONDITIONS PRIOR TO
COMMENCEMENT OF ANY WORKS ON SITE.
EARTHWORKS COMMENCING.
19. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON
18. CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE
2. GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF
IDENTIFIED IN THE APPROVED VEGETATION MANAGEMENT PLAN. WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
100MM OVER THE EXTENT OF THE WORKS UNLESS DIRECTED
CONTRACTOR TO ENSURE ALL TREE ROOTS AND STUMPS ARE
OTHERWISE AND STOCKPILED WHERE REQUIRED FOR FILL OF
COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.
LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT BE USED IN 20. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE
CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION
ENERGY SERVICE PROVIDERS TELECOMMUNICATIONS
SERVICE PROVIDERS elstra Manual of Uniform Traffic Control Devices
BEFORE YOU DIG SERVICE LOCATIONS AGL AUSTRALIA
ERGON. 60
ENERGY
energex ' yes' Telstra
WARNING: OPTIC FIBRE
IT IS THE RESPONSIBILITY OF THE PRINCIPAL visionstream km/h
CONTRACTOR TO CONTACT ALL RELEVANT origin OPTUS
SERVICE AUTHORITIES TO VERIFY THE NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM EXTREME CARE TO BE TAKEN WHILE EXCAVATING IN THE
NOTE: ALL SIGNS & LINE MARKING TO BE IN
LOCATION OF ALL EXISTING SERVICES PRIOR PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED VICINITY OF OPTIC FIBRE CABLES. LOCATIONS ARE TO ACCORDANCE WITH THE MANUAL OF
PRIOR TO START OF CONSTRUCTION. PHONE DBYD PRIOR TO START OF CONSTRUCTION. PHONE DBYD
TO THE START OF CONSTRUCTION SERVICE LOCATIONS ON 1100 FOR DETAILS. SERVICE LOCATIONS ON 1100 FOR DETAILS.
BE CONFIRMED PRIOR TO START OF CONSTRUCTION. UNIFORM TRAFFIC CONTROL DEVICES.
CLIENT DETAILS: PROJECT ADDRESS: APPROVED BY: PROJECT NAME:
PROPOSED RESIDENTIAL DUPLEX
IZAROX QLD PTY LTD TITLE: STATUS:
73 SOUTHERN CROSS PARADE GENERAL NOTES FOR APPROVAL - NOT FOR
© ABN 89 647 469 707
SUNRISE BEACH, QLD, 4567 BEN PARRY CONSTRUCTION
75 NOOSA DRIVE RPEQ: 28084
01 31/10/22 MCU / OPW ISSUE MVP BRP BRP SCALE:
NOOSA HEADS, QLD 4567 CPEng
+61 7 5211 1003 REV DATE DESCRIPTION DWN CHK APP 1:100 DATE: 31/10/2022
DRAWING NUMBER: PROJECT NUMBER: SHEET REV:
RECORCONSULTING.COM REVISIONS
DO NOT SCALE, IF IN DOUBT ASK
002 20220237
SIZE:
A1 01
Section 15
SW
N
SW
SW
S
SW
CP 671
SP111801 RP225123
NOTES:
1. FOR GENERAL NOTES REFER DWG 002, WHICH IS TO BE REQUESTED AND
S
VIEWED PRIOR TO COMMENCEMENT OF CONSTRUCTION IF NOT SUPPLIED.
SW
W
ALL EXISTING BUILDING, EXISTING SEWER SERVICE TO BE
STRUCTURES AND IMPERVIOUS DISCONNECTED AND CAPPED OFF 2. THE CONTRACTOR WILL MAKE HIMSELF FULLY AWARE OF THE EXISTING
SURFACES TO BE REMOVED U.N.O DURING CONSTRUCTION FEATURES OF THIS SITE AND ENSURE ANY ADDITIONAL WORKS NOT
SHOWN ON THIS PLAN ARE INCLUDED IN THE CONTRACT.
S
3
.09
.2
37
SW
37
W
3. LOCATION AND DEPTH OF EXISTING SERVICES BASED ON SURVEY, DBYD
8
.7
38
AND COUNCIL RECORDS. IT IS THE CONTRACTORS RESPONSIBILITY TO
2
2
.5
37.5
38
CONFIRM ACTUAL LOCATION AND DEPTH PRIOR TO CARRYING OUT ANY
2
41
37.6
37
.
EXCAVATION OR TRENCHING WORKS.
38
S
.5
2
BAN
.4
9
.6
K 38.40
38
0.25 37
SW
38.
38
0504 86 .96
38. .89 4. CONTRACTOR TO LOCATE AND PROTECT ALL EXISTING SERVICES ON SITE
W
49 38 0 38.23
3 8.9 PRIOR TO COMMENCEMENT OF WORKS.
38.60
4
.6
EXISTING WATER SERVICE TO BE
38
37.92 DISCONNECTED AND CAPPED
39.15 5. CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR TO ANY
37
4
OFF DURING CONSTRUCTION
.4
39
.9
DEMOLITION WORKS COMMENCING ON SITE.
38
.
SW
3
14 37.83
W
5
4
9
39.5
.3
.2
5
6. ALL VEGETATION WITHIN THE LIMIT OF WORKS TO BE CLEARED, MULCHED
38
38
.28
.9
39
38
PA
LM .82 AND REMOVED FROM SITE IN ACCORDANCE WITH APPROVED VEGETATION
.06
39.60
S
CL 39 38
39.81 UM 98
38. 39 TBM (Nail in Kerb) CLEARING PLAN (BY OTHERS) OR IF SCHEDULED STOCKPILE FOR USE BY
39 .20
P RL38.17 AHD LANDSCAPER.
82
.60 39.
SW
.
56
39
W
39.63 38 38
7 4 ( .5 7. CONTRACTOR TO LOCATE ALL EXISTING UTILITIES ON SITE AND MAKE
.92 38.
2
2
.66
.0
Stairs
5
40
RL41.03
39
Landing
.6
Co
( SUITABLE ARRANGEMENTS TO HAVE DISCONNECTED PRIOR TO
39
S
ncr DEMOLITION WORKS BEGINNING.
6
ete 73
.5
39
Stairs 38. 8
39
.5 .8 0 .6
8
9 38
4
.7
38
8
SW
.8
.7
39
EXISTING DRIVEWAY
39
39
8. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON
W
\ \ \ \ \ \ .45 .70 38.53
CROSSOVER TO BE REMOVED
8 \ 39 38
39.9 39 THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE
0
.65
\
. \
.7
80
39
40 WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
38
\
\
S
\
\ 8
BANK 0 01
\ \ \ \ \ 39.6
\
.20405 40. 9. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING
SW
\ \ \ \ \ \ \ \ \ \ \ \ \
\ .30
39 PROPERTIES AND COUNCIL ROADS AND VERGES PRIOR TO
W
\
.72
40
\ 39
rs
\ \ \ \ \ \ \ \ \ \ \ \ COMMENCEMENT OF ANY WORKS ON SITE.
.8
ai
\
40 \ \ \
7
St
TR .29
39
S
EE
01
0 21 10. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES,
5
.
.31 41.
40
.7
7
CP 010
1
39
.8
39.33
.8
ROADS AND SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM SITE
40
39
SW
3
SP111802
\ \ \ \ \ \ \ \ \ \
.7
5
.
30W
.6
U.N.O.
39
39.20
39
41.04
10
6
31
.
.1
6 (
40
0
41
39.
.5
39.7
97
41
Upper Floor 11. WHERE NECESSARY, CONTRACTOR SHALL OBTAIN ALL NECESSARY
.
39
S
42
(
.15
Level RL42.49 APPROVALS TO CARRY OUT SERVICES RELOCATION OR ALTERATIONS.
(
(
SW
(
W
41.42
(
SOUTHERN CROSS PARADE
(
42.06
78
Section 16
39.
(
\
(
39.9
81
3
40
.1
S
39.70
\
(
42
9
\
EXISTING TREES TO BE \
(
SW
\ \ \ \ \ \ \ \ \ \
CLEARED, GRUBBED AND \
(
W
REMOVED OFF SITE U.N.O \
MA
40
(
\
CA
0.2
\
506 Deck (
0
\
S
0
.5
3
.41
42
RL42.46 (
40
42.77
Pandanus Roots (
SW
\ \ \ \ \ \ \ (
Edge of Bitumen
(
W
LEGEND:
(
(
(
(
(
(
S
\ \ \
(
\ \ \ \ \ \ \ \ \ \ \ \
(
ADJACENT BOUNDARY
(
(
(
(
\ \ \ \ \ \ \ \ \ \ \ \ 96
(
41.
46
(
SW
(
22
.
(
42
42. 41.94
(
42.97 Stairs 41.89
(
W
PROPOSED BOUNDARY
\
(
42
(
(
(
(
(
(
\ \
(
(
.96
(
6
(
(
(
(
(
(
(
(
(
(
.3
(
(
40.8
(
(
(
(
(
(
(
(
(
42
6
(
(
(
(
(
(
(
(
EXISTING FENCE
(
(
(
1
(
(
(
(
(
TREE 0.30604
.3
(
40.
(
S
(
42.92
(
(
42.5
(
(
42.
(
(
(
(
(
42
(
(
(
(
(
(
27
(
42.40
(
(
(
(
(
(
(
(
88
42.95
(
(
.00
(
40.74
(
(
(
(
(
(
43 42.11 \ \ \ \ \ \ \ \ \ \ \ EXISTING BUILDING
43.59 .07
43.30
(
SW
43.03 43.02 42 TREE 0.250604
42.88 42.5
W
EXISTING KERB AND CHANNEL
TBM (Screw in Kerb) E E EXISTING ELECTRICITY
S
RL41.09 AHD SW SW EXISTING STORMWATER
SW
41.40
W
W W EXSTING WATER
S S EXISTING SEWER
S
.51
ELECTRICITY SERVICE
SW
1 2
41
SP194330
W
SP194330 41.53 EXISTING STORMWATER MANHOLE
.63
EXISTING WATER FIRE HYDRANT
41
S
EXISTING WATER METER
SW
W
EXISTING SEWER CHAMBER
S
EXISTING TREE
SW
W
EXISTING CONCRETE
SW
W
1 0 1 2 3 4 5
SCALE (metres)
1 : 100 (FULL SIZE)
SW
W
PROJECT ADDRESS: PROJECT NAME:
PROPOSED RESIDENTIAL DUPLEX
SW
IZAROX QLD PTY LTD TITLE:
W
73 SOUTHERN CROSS PARADE EXISTING SERVICES & FOR APPROVAL - NOT FOR
© ABN 89 647 469 707
SUNRISE BEACH, QLD, 4567 BEN PARRY DEMOLITION PLAN CONSTRUCTION
RPEQ: 28084
SW
75 NOOSA DRIVE
01 31/10/22 MCU / OPW ISSUE MVP BRP BRP SCALE:
NOOSA HEADS, QLD 4567 CPEng
W
+61 7 5211 1003 1:100 DATE: 31/10/2022
RECORCONSULTING.COM 003 20220237 A1 01
W