20220237 73 Southern Cross Pde SWMP
Original PDF page 10, section 1. The text section number identifies this passage in the reader.
2. A shakedown area is to be installed at the construction entry/exit to the proposed development area to
minimise sediment being transported to and from the site.
3. Diversion of upstream run-off around any exposed areas using diversion drains around the site.
4.2. Operational Phase
The development consists of a small lot duplex consistent in character with the existing residential dwelling. The
proposed development is not considered to significantly alter the pollutant generation potential of the site, and
therefore no additional stormwater quality treatment is proposed for the development.
Page 10 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003 A 75 Noosa Drive, Noosa Heads,Qld 4567 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.