20220237 73 Southern Cross Pde SWMP

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 6, section 1. The text section number identifies this passage in the reader.

                                                                       Nearest
                                                                       SW Inlet




                         Typical
                         overland
                         flow                                                                      Kerb outlet to
                                                                                                   roof drainage




                            Figure 2.2 - Site Drainage Characteristics (Noosa Council Intramaps, 2022)



     2.3. Proposed Development Drainage Pattern

          2.3.1 Stormwater Concept
Roof run-off from the new building will be drained via downpipes into an internal stormwater drainage which will
carry surface and roof run-off from the proposed development to discharge via new kerb adaptor outlets to replace
the existing discharge point of the roof run-off. The kerb adaptor outlets are proposed as the Lawful Point of
Discharge for the development.

Overland flow paths along the western and southern boundary will provide fall for upstream run-off to be conveyed
around the site, while the pits within the site will provide collection points to allow for the small areas of upstream
run-off that may reach the subject site.

The remaining typically pervious areas of the site will drain as overland surface flows infiltrating into the site soils
consistent with the current drainage conditions.

The roof and allotment drainage system for the proposed site shall be designed to comply with:

     1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards – Roads, drainage and
        earthworks;

     2. The Queensland Urban Drainage Manual (QUDM); and

     3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.

Refer to Appendix A Proposed Development Plan for the proposed stormwater drainage layout plan illustrating
the concept described above.

                                                                                                                    Page 6 of 14
Project number 20220237
File 20220237 73 Southern Cross Pde SWMP.docx, 2022-10-31 Revision 1
P +61 7 5211 1003                 A 75 Noosa Drive, Noosa Heads,Qld 4567          E [email protected]         recorconsulting.com
Log in to download the original file

20220237 73 Southern Cross Pde SWMP.pdf · 8.4 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.