Att13 - Hydraulic and Wet Fire Services Investigation
CYC Noosa Campsite
__________________________________________________________________________________________
1.4 PROPOSED USE
• Campsite accommodating 300 campers with commercial kitchen facilities, Dining Hall and Activity
Spaces dispersed around the campsite with allocation of agricultural land, food growing activities and
adventure spaces.
• Class 3 accommodation blocks
o Village of 140 occupants: 2350m2
o Village of 100 occupants: 2020m2
o Village of 60 occupants: 1600m2
• Class 9b Dining blocks
• Proposed rise in storey Single or two storeys (max)
1.5 AUTHORITY INFRASTRUCTURE
The site is not serviced by reticulated water supply or sewer. Upon review of the Unitywater mapping it
appears the nearest Authority Infrastructure is in Boreen Point (refer below image)
1.6 ASSUMPTIONS
The following assumptions have been relied upon in the preparation of this report:
• It would not be feasible to extend Authority Infrastructure (Sewer and Water) to the site.
• It’s assumed for the purpose of this report that the existing clubhouse building and associated on-site
sewage treatment and land application system will be demolished.
• MRP have not sighed a Flood Certificate for this site however it is anticipated the site is above any DFL
(TBC during detailed design Stage).
•
1.7 REVIEW PROCESS
The following actions have occurred in the preparation of this report
• Desktop review of Authority Infrastructure drawings 8th February 2022.
Ref; 22-0008
Master Planning Site Infrastructure Review Rev 01
5 March 2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original