23616DA
Appeal Rights
SUNSTAINABLE PLANNING ACT 2009 & SUSTAINABLE
PLANNING REGULATION 2009
(3) However, a submitter may not appeal if the
submitter—
The following is an extract from the Sustainable
Planning Act 2009 (Chapter 6). (a) withdraws the submission before the
application is decided; or
MATERIAL CHANGE OF USE, RECONFIGURING A (b) has given the assessment manager a
LOT & OPERATIONAL WORKS notice under section 339(1)(b)(ii).
Division 8 - Appeals to court relating to development (4) The appeal must be started within 20 business
applications days (the submitter’s appeal period) after the
461 Appeals by applicants decision notice or negotiated decision notice is
(1) An applicant for a development application may given to the submitter.
appeal to the court against any of the following- 463 Additional and extended appeal rights for
(a) the refusal, or the refusal in part, of a submitters for particular development
development application; applications
(b) any condition of a development approval, (1) This section applies to a development
another matter stated in a development application to which chapter 9, part 7
approval and the identification or inclusion applies.
of a code under section 242 (2) A submitter of a properly made submission for
(c) the decision to give a preliminary approval the application may appeal to the court about a
when a development permit was applied referral agency’s response made by a
for; prescribed concurrence agency for the
application.
(d) the length of a period mentioned in section
(3) However, the submitter may only appeal
341;;
against a referral agency’s response to the
(e) a deemed refusal of the development extent it relates to—
application.
(a) if the prescribed concurrence agency is the
(2) An appeal under subsection (1)(a), (b), (c) or chief executive (environment)—
(d) must be started within 20 business days development for an aquacultural ERA; or
(the applicant’s appeal period) after—
(b) if the prescribed concurrence agency is the
(a) if a decision notice or negotiated decision chief executive (fisheries)—development
notice is given—the day the decision notice that is—
or negotiated decision notice is given to the
applicant; or (i) a material change of use of premises
for aquaculture; or
(b) otherwise—the day a decision notice was (ii) operational work that is the removal,
required to be given to the applicant. damage or destruction of a marine
(3) An appeal under subsection (1)(e) may be plant
started at any time after the last day a decision (4) Despite section 462(1), the submitter may
on the matter should have been made. appeal against the following matters for the
462 Appeals by submitters - general application even if the matters relate to code
(1) A submitter for a development application may assessment—
appeal to the court only against- (a) a decision about a matter mentioned in
(a) the part of the approval relating to the section 462(2) if it is a decision of the chief
assessment manager’s decision about any executive (fisheries);
part of the application requiring impact (b) a referral agency’s response mentioned in
assessment under section 314; or subsection (2).
(b) the part of the approval relating to the 464 Appeals by advice agency submitters
assessment manager’s decision under (1) Subsection (2) applies if an advice agency, in
section 327.
its response for an application, told the
(2) To the extent an appeal may be made under assessment manager to treat the response as
subsection (1), the appeal may be against 1 or a properly made submission.
more of the following— (2) The advice agency may, within the limits of its
(a) the giving of a development approval; jurisdiction, appeal to the court about—
(b) any provision of the approval including— (a) any part of the approval relating to the
(i) a condition of, or lack of condition for, assessment manager’s decision about any
the approval; or part of the application requiring impact
assessment under section 314; or
(ii) the length of a period mentioned in
section 341 for the approval.
Page 25 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
23616DA - Change to Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 122 KB (small file)
- File type
No other editions are linked here.