Title Reference [to issue]
(ix) time is to Queensland time.
(b) A singular word includes the plural, and vice versa.
(c) The word ‘month’ means a calendar month and the word ‘year’ means twelve months.
(d) A word which suggests one gender includes any other genders.
(e) If a word is defined, another part of speech has a corresponding meaning.
(f) If an example is given of anything (including a right, obligation or concept), such as by saying it includes
something else, the example does not limit the scope of that thing.
(g) Any agreement, representation, warranty or indemnity by two or more parties (including where two or
more persons are included in the same defined term) binds them jointly and severally.
(h) Any agreement, representation, warranty or indemnity in favour of two or more parties (including where
two or more persons are included in the same defined term) is for the benefit of them jointly and
severally.
(i) Words defined in the GST law have the same meaning in this document unless the content makes it clear
that a different meaning is intended.
3. GRANT OF EASEMENT
3.1 Access
The Grantor grants to the Grantee and the Authorised Users, the non-exclusive right for the Grantee and the
Authorised Users to pass and re-pass as pedestrians and/or by motor vehicles over, along and upon the
Burdened Land for access in common with the Grantor and its employees, agents, visitors and invitees.
4. RESTRICTION ON USE
Each of the Grantor and Grantee must:
(a) not do any act likely to jeopardise or prejudicially affect the safety or reliable working of the access way
and must at all times refrain from using the Burdened Land in a manner likely to obstruct or
unreasonably hinder access to it by any other party; and
(b) cause as little inconvenience as is practical and minimise any interference to each other’s use of the
Burdened Land.
5. NO CONSTRUCTION ON RIGHT OF CARRIAGEWAY
The Grantor must not construct nor allow to be constructed any building or structure on the Burdened Land
without the Grantee’s consent.
6. REPAIR OBLIGATION
(a) The Grantor must keep the Burdened Land in good and proper trafficable repair and in a condition
suitable for the purposes of the grant under this easement.
Page 41
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.