f. details on the location of external fill sites/sources, the haulage route, type of vehicle
to be utilised during filling operations and frequency of usage. NB any damage to the
existing road system as a result of haulage operations shall be fully repaired at the
applicant’s expense
g. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Private Infrastructure
5. All private infrastructure for the development must be designed to meet the planning
scheme requirements unless otherwise agreed by the relevant authority.
Qualified Person
6. For the purpose of preparing a Landscape Plan, a qualified person is considered to be a
landscape architect, landscape designer and/or horticulturist with a minimum of 3 years
current experience in the field of landscape design.
7. For the purpose of preparing an Arborist Report, a qualified person is considered to be a
person with either:
a. ISA certification; or
b. a Diploma of Arboriculture in addition to a minimum of 3 years current experience
in the field of arboriculture.
8. For the purpose of preparing a Fauna Management Plan, a qualified person is considered
to be an ecologist with a minimum of 3 years current experience in the field of fauna
assessment and management.
9. For the purpose of preparing a Bushfire Management Plan, and for certifying compliance
with the bushfire requirements of this Decision Notice, a qualified person is considered to
be an ecologist with a minimum of 3 years current experience in the field of bushfire
assessment and management.
5. PROPERTY NOTES
RAL18/0023 – Stormwater
The following notation applies to approved lots 4, 5 and 6:
These lots are part of a larger development covered by permit RAL18/0023. As part of the
stormwater management documented for this application, it was determined that all lots are
required to treat stormwater originating within the lot on-site, with the infrastructure to be
documented as part of any future MCU over each lot. Conditions are provided on permit
RAL18/0023 to enforce this commitment, even though the area of this lot would usually exempt
it from providing on-site stormwater treatment
RAL18/0023 – Stormwater
The following notation applies to approved lots 12-15:
Proposed Lots 12-15: Bioretention devices provided within this lot as part of RAL18/0023 are
provided solely to treat runoff associated with the bushfire access and car parking and is not
to be used for treatment of the developed site runoff. Additional stormwater quality
infrastructure is to be provided as part of any future MCU application over the lot. The
bioretention devices lots must be maintained in accordance with the Water by Design (2009)
Maintaining Vegetated Stormwater Assets (Version 1)
RAL18/0023 - Access
Page 108
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.