B Current Decision Notice · 132007.2398
Attached to the e-mail 132007.2398.02 Request to change existing approval (1 of 3) Cover letter and site, floor & elevation plans.
132007.2398.01
72. A Stormwater Monitoring and Maintenance Plan (SMMP) shall be prepared ensure
stormwater treatment infrastructure is performing its intended purpose. The SMMP shall
be approved by the Council’s CEO or delegated officer prior to issue of any Operational
Works Approval. The SMMP shall specify:
72.1 performance indicators including water quality objectives;
72.2 monitoring schedule to ensure specified performance indicators are achieved;
72.3 maintenance schedule for all elements of the stormwater treatment train;
72.4 reporting requirements;
72.5 corrective actions for non compliance with performance indicators; and
72.6 responsibility framework.
Sewer Mains
73. The site must be connected to Council's existing sewerage reticulation system by gravity,
and be constructed in accordance with Council's standards and requirements at no cost to
Council.
74. The sewer connection shall be generally in accordance with the Sewerage Layout Plan
Drawing No N07058-DA10 Issue E dated 22/01/09 and the Proposed Sewer Details
N07058-DA20 Issue (A) dated 22/01/2009 by Brown Consulting. A Development Permit
for Operational Works is required.
75. A new sewer connection must be provided within the property boundary of Lot 4 RP
215922.
76. The applicant must provide written approval from all property owners through which
external sewers will traverse, to enter, construct and provide a sewer easement. This must
be submitted prior to the associated development application for Operational Works.
Water Supply
77. The site must be connected to Council's existing town water supply and be constructed in
accordance with Council's standards and requirements at no cost to Council.
78. Works be carried out in accordance with the approved findings of the water supply
network analysis by Worley Parsons and dated 10 June 2008
79. The existing 100mm diameter watermain within Pearson Road must be upgraded
between the existing 150mm diameter main in Carruthers Court to the existing 150mm
diameter main to the North in Pearsons Road
80. The water connection to the water reticulation system shall extend to the property boundary
and be metered. All fees for the supply of water meters shall be paid to the Council
81. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the
development shall be served by:
81.1 Single Body Corporate water meter to measure the total water consumption
(including fire hose reels, but excluding fire hydrants and fire sprinkler systems)
81.2 Individual water meters to each tenement capable of being separately rated. These
meters must be supplied and installed in accordance with Councils requirements
81.3 All water meters must be located in an easily assessable location to facilitate
unhindered reading by Council and/or Council’s contracted water meter readers,
and not behind fences or locked gates
81.4 A fire service (fully testable single detector check with metered bypass), where
applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
reels)
Page 10 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
B CURRENT DECISION NOTICE.pdfRelated documentApplication case desk ↗
About this file
- File size
- 121 KB (small file)
- File type
No other editions are linked here.