response to information request - Werin St
Engineering
10. Please amend the Driveway and Access plan to reduce the width of the
crossover at the kerb and front boundary to be in accordance with standard
drawing RS-049.
11. Please demonstrate on the engineering plans, prepared by an RPEQ, that a
design B99 vehicle can manoeuvre onsite from each of the three parking
spaces (the double garage and the single carport) and leave in a forward
gear. If this cannot be achieved, please consider altering the design of the
proposed second unit to allow sufficient manoeuvring space.
12. Please amend the Bulk Earthworks Plan to detail whether the fill area is being
retained or battered and provide detail around the proposed (i.e. slope of the
batter or type of retaining structure).
13. Please amend the stormwater management plan to include either of the
following options:
a. Consolidate the downpipes to a single crossing point in the footpath,
preferably adjacent the crossover so the footpath replacement
section can be poured with the crossover; or
b. Include notes on the plan to replace an entire panel from the footpath
at each crossing point or alternatively install the pits via boring under
the footpath.
Please see attached updated SCG plans with detailed driveway plan. The proposed dual
occupancy dwellings adjoin a local road and may reverse out in accordance with the
Driveways and Carparking code. Despite this compliance, the applicant has demonstrated
manoeuvring for one space with the double garage for a five-point turn.
Bulk earthworks plan demonstrates minimal cut/fill and no retaining walls and stomwater
plans have been updated to address Council’s request.
----------------------------------------------------------------------------------------------------------------------
Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the information requested in the information request. Please proceed with the
assessment of the application at your earliest convenience.
If you have any further queries in relation to the above, please do not hesitate to contact
myself.
Regards,
Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA MQELA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Page 3 of 3