2102-21163 SRA -Response with conditions
Attached to the e-mail MCU21/0012 - Referral agency response.
RA6-N SARA reference: 2102-21163 SRA Council reference: MCU21/0012 Applicant reference: 02821 2 March 2021 Chief Executive Officer Noosa Shire Council PO Box 141 Tewantin Qld 4565 [email protected] Attention: Patrick Murphy Dear Mr Murphy SARA response—32 Plover Street, Peregian Beach (Referral agency response given under section 56 of the Planning Act 2016) The development application described below was confirmed as properly referred by the State Assessment and Referral Agency (SARA) on 17 February 2021. Response Outcome: Referral agency response – with conditions. Date of response: 2 March 2021 Conditions: The conditions in Attachment 1 must be attached to any development approval. Advice: Advice to the applicant is in Attachment 2. Reasons: The reasons for the referral agency response are in Attachment 3. Development details Description: Development permit Material change of use for a dwelling house SARA role: Referral agency. SARA trigger: Schedule 10, part 4, division 3, table 1, item 1 (Planning Regulation 2017) – Contaminated land (Unexploded ordinance) South East Queensland (North) regional office Mike Ahern Building, Level 3, 12 First Avenue, Maroochydore Page 1 of 6 PO Box 1129, Maroochydore QLD 4558
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 5 pages
Page 2
2102-21163 SRA
SARA reference: 2102-21163 SRA
Assessment Manager: Noosa Shire Council
Street address: 32 Plover Street, Peregian Beach
Real property description: Lot 9 on P9313
Applicant name: Rosalind and Graham Broadhurst
Applicant contact details: PO Box 1684
Noosa Heads QLD 4567
[email protected]
Representations
An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment Rules)
Copies of the relevant provisions are in Attachment 4.
A copy of this response has been sent to the applicant for their information.
For further information please contact Paul Gleeson, Principal Planning Officer, on 5352 9717 or via
email [email protected] who will be pleased to assist.
Yours sincerely
Garth Nolan
Manager (Planning)
cc Rosalind and Graham Broadhurst , [email protected]
enc Attachment 1 - Referral agency conditions
Attachment 2 - Advice to the applicant
Attachment 3 - Reasons for referral agency response
Attachment 4 - Representations provisions
State Assessment and Referral Agency Page 2 of 6
Page 3
2102-21163 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application)
No Condition
Conditions
. timing
Material change of use
10.4.3.1.1—The chief executive administering the Planning Act 2016 nominates the Director-General of
the Department of Environment and Science to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter relating
to the following condition(s):
1. Provide written confirmation to the Department of State Development, Prior to the
Manufacturing, Infrastructure and Planning by an approved contractor on the commencement
Australian Government, Department of Defence, Unexploded Ordnance of works
(UXO) Panel that the subject site has been remediated and cleared of
unexploded ordnances.
The Unexploded Ordnance (UXO) Panel is found online at:
http://www.defence.gov.au/estatemanagement/support/dehp/WhoToEngage.
asp.
State Assessment and Referral Agency Page 3 of 6
Page 4
2102-21163 SRA
Attachment 2—Advice to the applicant
General advice
1. Terms and phrases used in this document are defined in the Planning Act 2016 its regulation or
the State Development Assessment Provisions (SDAP) v2.6. If a word remains undefined it has
its ordinary meaning.
State Assessment and Referral Agency Page 4 of 6
Page 5
2102-21163 SRA
Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)
The reasons for SARA’s decision are:
The proposed development involves a material change of use for a single detached dwelling on land
mapped as potentially subject to unexploded ordinance.
No evidence was provide with the application that a clearence certificate in accordance with .. has
been issued over the land.
The land is located in an established residential area and has been previously subdivided and is
therefore considered to have a low risk of unexploded ordinance.
The applicant is required to obtain written confirmation by an approved contractor on the Australian
Government, Department of Defence, Unexploded Ordnance (UXO) Panel that the subject site has
been remediated and cleared of unexploded ordnances.
Material used in the assessment of the application:
The development application material and submitted plans
Planning Act 2016
Planning Regulation 2017
The State Development Assessment Provisions (version 2.6), as published by the department
The Development Assessment Rules
SARA DA Mapping system
State Assessment and Referral Agency Page 5 of 6
Page 6
2102-21163 SRA Attachment 4—Change representation provisions (page left intentionally blank) State Assessment and Referral Agency Page 6 of 6