RFI - C - Site Based Stormwater Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawnFigure 1 - Locality Plan
Source: Queensland Globe
The purpose of the management plan is to ensure the current infiltration system designed for the site is
adequate to contain flows generated by the proposed development.
Calculations using the Insite Water modelling program provides the critical storm duration as 10 minutes and
a time of concentration for the site to the outlet as 5 minutes. (Refer Appendix A).
Previous approvals with Noosa Council indicate that any development requiring infiltration systems need to
demonstrate that all but the most extreme rainfall events would be infiltrated and that any infiltration tanks
are to be sized to cater for all design events up to and including the 1% AEP (1 in 100-year ARI design event).
Based on the post-development impervious fraction the site was calculated to have a peak flow for a 1% AEP
design storm event as 0.05 m3/s.
Page 6 of 11
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.