Initiatives not on Target
OP Ref Initiative Service/Mgr Responsible Status Reason for Status
5.7.2 Finalise the development of the Boreen Point Strategy and Environment Major Consultant engagement and design work for Boreen Point
Disruption
Campground Master Plan. Director Campground master planning completed. Project scope is
currently on hold due to identified challenges in obtaining
development approval under the current scope and scale.
Further progression paused pending resolution of planning
constraints and review of alternative options in 25/26.
5.9.1 Deliver the budgeted Capital Works program Infrastructure Planning Minor Progress on the program is presented in a regular Quarterly
Disruption
across Shire to budget time and quality Design & Delivery Report to Council, most recently February 2025. As referenced
expectations. Manager in the quarterly report; resourcing, and rising project costs
pressures are proving challenging to deliver the program.
Notwithstanding delivery pressures good progress has been
made on delivery, and considerable work undertaken to
contain project costs
Page 90 of 100
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.