Noosa Spit SEMP Final Report 74
Shoreline Erosion Mitigation Options
Table 4-5 Summary of MCA Results Developed with the PCG
Effectiveness Whole of Life Environmental Social Benefits Risk
Costs Values Overall Score
(30% weighting) (20% weighting) (15% weighting) (10% weighting) (25% weighting)
Option 1a – Sand plug at either end of
100% 50% 50% 100% 100% 83%
Dog Beach and shoreline nourishment
Option 1b – Sand plug at the southern
end of Dog Beach and shoreline 75% 25% 25% 75% 75% 58%
nourishment
Option 2 – Extension of the existing
training wall/groyne at western end of 75% 75% 50% 50% 75% 69%
Dog Beach
Option 3 – Extension of submerged
25% 75% 50% 0% 0% 30%
breakwater and two new groynes
Option 4 – Three new short groynes at
50% 100% 50% 50% 75% 66%
Dog Beach
Option 5 – Shore parallel seawall 100% 25% 25% 25% 75% 60%
Option 6 – Do nothing 0% 100% 25% 0% 0% 24%
G:\Admin\B23636.g.mpb.NoosaSpit_SEMP\R.B23636.001.02.SEMP_final.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.