4. Conclusion
On the basis of the above information, discussion and findings, I summarize my conclusions as
follows:
The requiremnts outlined in Noosa council RAL20/0021 states the construction of new stormwater
drainage line, bioretention and detention basin. This requirement will result in the removal of the
existing vegetation within the new stormwater drainage line to comply with councils requirements
with the current works to be performed within this area.
The stormwater drainage line, bioretention and detention basin are critical to managing the
stormwater flows and enhance stormwater treatment and quality.


I therefor conclude that these areas of vegetation affected by the required infrastructure cannot
be retained.


The offsite drainage vegetation is important to the drainage/creek line for fauna flora as well as
hydrology and water adjustment levels.
Any areas of vegetation to remain must have tree protection measures as outlined in the Tree
Management Plan following.




Arborist report – TSA: BAX-Pearsons Rd Cooroy
Treesafe Australia Pty Ltd. August 2021©                            P a g e 11 | 20
Log in to download the original file

20210817 Pearsons Rd, Arborist Report 2.pdf · 1.4 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.