Decision Notice - 010.2007.00000738.001 [As Published] · 132007.738
Officer: Denis Wallace
Direct Telephone: (07) 5449 5179
Response Address: PO Box 141, Tewantin QLD 4565
Email: [email protected]
Our Reference: 2007/738
Your Reference: 070145T
2 July 2008
Mintgrove Pty Ltd
CARE Ken Hicks & Associates
PO Box 6380
MAROOCHYDORE BC QLD 4558
Dear Sir/Madam
Decision Notice
Integrated Planning Act 1997
I refer to your application and advise that on 2 July 2008 Council decided to approve the application
in full subject to conditions.
Details of the decision are as follows:
1 APPLICATION DETAILS
Application No: 2007/738
Street address: 64 Gateway Drive, Noosaville
Real property description: Lot 13 SP 170295
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
The following type of approval has been issued:
Development Permit for Material Change of Use - Industrial Business Type 1 – Warehouse
and Industrial Business Type 2 – Production, Alteration, Repackaging & Repairing
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Land Use
1. Development undertaken in accordance with this approval must generally comply with the
approved plan of development. The approved plan is titled and numbered:
Page 1 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 19 pages
Page 2
2007/738
Plan / Rev. Plan / Document Name Date
Document No.
Sheet No. 1 “Industrial Development at Precinct N May 2008
Gateway Drive Noosaville” prepared by
Herwig Hartl trading as Smartarch
and as may be amended by these conditions.
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
the premises being occupied and maintained at all times thereafter. The landscaping shall
include:
3.1. A minimum of 2m width of landscaping adjacent to uncovered parking at the head of the
cul-de-sac;
3.2. A minimum of 1 shade tree per six vehicle parking spaces;
3.3. Dense native screening vegetation within the landscaped buffer adjacent the western
boundary (where not located within the easement area) consisting of species with a
range of mature canopy heights;
3.4. Revegetation of the landscaped buffer along the northern and eastern boundaries; &
3.5. Appropriate landscaping / treatment to bin collection or storage areas so that they do
not dominate the streetscape.
4. All buildings shall have a maximum building height of 10 metres above the natural and finished
ground levels and shall be a maximum of 2 storeys.
5. A minimum 1.8 metre high timber screening fence shall be constructed along the western
boundary of the site.
6. The walls to the rear facades of the buildings shall be finished in muted natural tones.
7. The windows proposed along the western façade and the southern façade of tenancies 1, 2 &
3 of the development shall be permanently fixed and fitted with double glazed glass or glass
that is equivalent in sound transmission loss to double glazed glass.
8. The retail sales component of any tenancy shall not exceed 20% of the gross floor area of that
tenancy and shall relate to an industry use conducted from that tenancy.
9. All goods are to be displayed on site within the property boundaries and/or on the premises
approved for the use. Goods shall not be stored or displayed within the common areas of the
site.
10. Secure bicycle racks shall be provided on site to accommodate a minimum of 41 bicycles.
The proposed bicycle racks shall be identified on the landscaping plans and shall be shall be
dispersed across the site to the reasonable satisfaction of Council.
11. End of trip facilities shall be provided within the buildings at a minimum rate of 1 locker per 2
bicycle parking spaces; 1 shower per 10 bicycle parking spaces or part thereof; and change
rooms.
2
12. The tenancies of 150m or greater indicated on the approved plan shall not be further
subdivided or partitioned to create additional tenancies.
13. Any advertising sign or device is to comply with Council's policies on advertising devices.
Page 2 of 20
Page 3
2007/738
14. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use. The landscape
plans required to be submitted are to denote areas of existing vegetation or existing trees
proposed or required to be retained.
15. A qualified fauna spotter shall be engaged during the removal of any vegetation.
16. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site:-
16.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
minimum of 10 metres between edges of heaps.
16.2. Disposal for firewood.
16.3. Disposal for landscaping purposes.
16.4. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
16.5. The disposal method for clearing works is to be submitted in conjunction with an
application for a Development Permit for Operational Work. The Applicant is advised
that other methods may be considered provided full details of the method are submitted.
The Applicant is advised that burning off is an unacceptable method of disposal.
17. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
18. The proposed development shall have all kitchen, laundry and bathroom fittings that comply
with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
Dishwashers and washing machines are excluded from this requirement.
19. Security in the form of a cash bond or trading bank guarantee to the sum of $40,000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for Operational Works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
20. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
21. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
22. The Development Permit for a material change of use of premises lapses if the use has not
happened by 2 July 2012, unless an application to extend the currency is approved by
Council.
Land Development
Flooding
23. Where applicable, any habitable rooms within buildings proposed on site (and areas utilised
for carparking purposes associated with the buildings) and any outdoor electrical transformers
and generators shall be constructed to comply with Council’s Minimum Floor Height
requirements as defined in Council’s Planning Scheme and on Council’s Scheme Maps at the
time of issue of the Building Permit.
Page 3 of 20
Page 4
2007/738
In this regard, and as an indication only, - a Minimum Floor Height of RL 2.80m (AHD) shall
apply. These levels, however, are subject to change and verification shall be made to
Council’s Land Development Section prior to obtaining a Development Permit for Building
Works.
Vehicle Access
24. Vehicular access to the site shall be constructed from the Gateway Drive frontage of the site
generally in accordance with Drawing Job No: M0906, Sheet No: 1 dated May 2008 by
Hartland consultants Pty Ltd - Smartarch and as may amended by these conditions.
25. All accesses to the site shall be of a maximum width of 6.0m at the property boundary.
26. The eastern and the western exit/accesses shall be clearly signed and marked to indicate No
Entry and Exit Only.
27. The central access shall be clearly signed and marked to indicate Entry Only.
28. The driveway shall be designed and constructed to Council’s design standards and to grades
that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
movements along the footpath without any step or level difference. Should any driveways be
constructed to grades that do not comply with AS/NZS 2890.1-2004 and AS 2890.2-1989,
Council will require that the driveway be removed and reconstructed to levels that do comply.
Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
to have the footpath continue at a constant grade to minimise the potential for pedestrians to
trip or fall.
29. To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath,
the driveway and any associated fencing or vegetation near the driveway shall comply with the
minimum sight line requirements as defined in AS 2890.1, section 3.2.4. The applicant shall
demonstrate compliance by illustrating these sight lines on the plans submitted for both
Operational Works approval and Building Works approval.
30. A public access easement for future cycleway and pathway shall be created over the existing
sewer easement, Easement U, along the south and west boundaries of site as shown on the
Land Title Plan SP 170295.
Car Parking and Loading Areas
31. Car parking, loading zones and skip bin storage shall be designed and constructed generally
in accordance with Drawing Job No: M0906, Sheet No: 1 dated May 2008 prepared by
Hartland consultants Pty Ltd - Smartarch.
32. A minimum of 104 uncovered carpark spaces shall be provided on site and shall include:-
32.1. 3 clearly defined and strategically placed disabled carpark spaces.
32.2. A minimum of the equivalent of 3 of the car parking spaces designated for motorcycle
and motor scooter parking, to accommodate a minimum of 12 spaces. Motorcycle and
motor scooter parking is to be evenly dispersed across the site.
33. The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004
for user Class 1 for staff and Class 3 for clients spaces with allowance for vehicles to enter
and leave the site in a forward gear and with a minimum head clearance (headroom) at any
point of 2.2m.
34. All carparking areas shall be kept, maintained and line-marked in a condition fit for use.
35. In order to ensure safety of pedestrians, the internal pathways on the site shall be a minimum
1.5m wide and be raised above the level of the internal driveway (the aisles) by providing
mountable kerb along the outer edge of the pathway and providing line marking and textures
surface pathway where necessary. The type and extent of line marking and texture surfaces
shall be clearly shown on all plans submitted for operational works.
Page 4 of 20
Page 5
2007/738
Frontage Works
36. A new full width concrete or paved path shall be constructed along the cul de sac frontage of
the site in accordance with Council’s design standards. Care shall be taken to protect any
existing vegetation and/or any underground services.
37. All external and internal paths, driveways and parking areas shall be designed and
constructed to ensure pedestrian safety using non-slip materials, to produce an evenly graded
surface finish, and to be in accordance with the Disability Discrimination Act 1992 and
Australian Standard 1428.1 Design for Access & Mobility.
38. Any redundant vehicular crossings to the site shall be removed and replaced by kerb &
channel, footpath paving and landscaping such as trees and grasses in accordance with
Council’s Standard specifications prior to commencement of the use permitted by this permit.
Roof Water, Stormwater Drainage and Sewerage
39. Roof runoff from any new /building shall be directed to a rainwater storage system or tank(s)
that is installed to ensure water from the tank(s) is used for external uses (such as watering
gardens, irrigation, ornamental ponds, water features, topping-up swimming pools, outdoor
cleaning, etc) and for use in flushing of toilets internal to the building. All rainwater tanks are
to be designed and installed in accordance with the Queensland Development Code (QDC)
current at the time of building approval, and shall be part of the plumbing application for
approval. The location and capacity of the tank/s shall be clearly shown on the plans
submitted for Building Works / Operational Works approval and any overflow shall be directed
to the stormwater detention drainage system proposed near the north eastern part of the site.
40. All stormwater drainage of the site shall be designed and certified by a Registered
Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit
for Operational Works. The stormwater drainage design shall give considerations to the
following:
40.1. The design shall be generally in accordance to Drawing No 06105 - 1 (A) dated 3
November 2007 by Callaghan & Toth.
40.2. The design shall take into consideration the findings and the recommendations of the
Stormwater Quality Management and Assessment Report dated March 2007 prepared
by Callaghan & Toth.
40.3. The design shall include treatment train of rainwater detention/reuse tanks, gross
pollutant traps/oil arrestors, Bio-Retention Basin/Unit and Raingardens to attenuate the
stormwater runoff quality and quantity to the Pre Development levels. Calculation and
data shall be provided to demonstrate that the EPA recommended water quality
objectives will be achieved.
40.4. All stormwater runoff from the paved areas on the site shall be disposed off via the
treatment train.
40.5. There shall be no concentration of stormwater flows that may cause environmental
damage, erosion or siltation onto the downstream bushland due to the completed
development or the construction phase of the site.
40.6. To ensure no adverse impact on the proposed buildings on the site (particularly units
facing the central access driveway), the design shall allow for secondary flowpath to
cater for 100 years flows from within the site and from Gateway Drive. Improvement/s
on the existing stormwater collection within Gateway Drive shall be included in the
design and construction where necessary.
41. To ensure that polluted run-off does not enter Council’s stormwater drainage system,
stormwater run-off from the carparking areas and the driveways shall have the first flush (the
first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor/gross pollutant trap
provided on site prior to being permitted to discharge into Council’s drainage system.
Page 5 of 20
Page 6
2007/738
All other clean stormwater, such as roof water, can be collected on site and discharged
through a single underground drain line directly into the existing drainage system, bypassing
the grease/oil arrestor/gross pollutant trap.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors/gross pollutant trap, which shall be submitted to the Council for approval prior to
obtaining a Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
42. All site stormwater drainage shall be by means of a gravity system.
43. The treatment train including the gross pollutant traps/oil arrestors, Bio-Retention Basin/Unit
and Raingardens shall have three (3) years maintenance period from the date of the accepting
the operational works on the site on maintenance.
During the three years maintenance period the applicant shall monitor the quality of the
stormwater runoff existing the site to ensure that water achieve the water quality objectives as
set out by Council and generally as described by the Stormwater Quality Management and
Assessment Report dated March 2007 prepared by Callaghan & Toth. Should the monitoring
indicate that the objectives have not been met or indicate that objectives may not be met the
applicant shall undertake the necessary works and/or upgrading works to ensure the
objectives are achieved on a regular basis.
44. The applicant shall provide a comprehensive ongoing stormwater quality monitoring,
management and maintenance program for the stormwater treatment train on the
development site including the water tanks and gross pollutants traps (GPTs). The
management plan shall be submitted to the Council for approval in conjunction with obtaining
a Development Permit for Operational Works.
The approved maintenance plan must be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
45. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
46. The design for the sewer layout on the site shall be generally in accordance to Drawing No
06105 - 2 dated 3 November 2007 by Callaghan & Toth titled Proposed Site Layout Levels &
Sewer Plan.
47. Any building or structure within proximity of an easement or any other public utility’s
underground must have its foundations designed so that no surcharge loads are imposed
upon such underground infrastructure. Foundations must be taken down a minimum of 1.0m
below a line of influence measured 1.0m in the direction of the foundation from the centreline
of the closest underground service and along the natural angle of repose of the foundation soil
type(s).
Plans, and supportive documents, detailing these proposed foundations shall be designed by
a registered practicing Geotechnical Engineer and submitted with the application for a
Development Permit for Operational Works.
48. There shall be no encroachments on Council easements by any buildings or structures (eg.
ponds, retaining walls exceeding 1m in height, raised terraces, aboveground or underground
water tanks, air conditioning units, ancillary buildings and the like).
Page 6 of 20
Page 7
2007/738
49. All proposed underground services on the site shall not interfere with the function or the
access to the existing Council’s services on the site. To this end the applicant shall provide
general plan showing all the existing and proposed services and easements on and adjacent
the site to be submitted to council in conjunction with the application for Operational Works.
Town Water Supply
50. The site shall be connected to Council’s existing town water supply and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
51. Each individual water connection to the water reticulation system shall extend to the property
boundary and be metered. All fees for the supply of water meters shall be paid to the Council.
52. All water meters must be located outside the property boundary and in an easily assessable
location to facilitate unhindered reading by Council and/or Council’s contracted water meter
readers, and not behind fences or locked gates. In this regard approval of the water meter
configuration and location must be obtained from Council’s Water & Sewerage Capital Works
Manager prior to lodgement and approval of hydraulic drawings.
53. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development
shall be served by:
53.1. A single Body Corporate water meter to measure the total water consumption (including
fire hose reels, but excluding fire hydrants and fire sprinkler systems), and
53.2. Individual water meters to each tenement capable of being separately rated, and
53.3. A fire service (fully testable single detector check with metered bypass), where
applicable, for flows to fire hydrants and fire sprinkler systems (excluding fire hose
reels).
54. Fire hydrants are to be provided throughout the development in accordance with Council
Engineering Design Standards and in accordance with Queensland Fire Service Standards.
The applicant is advised that this development may require the provision of fire hydrants and a
booster pump in accordance with the Building Code of Australia, and consultation may also be
needed with Queensland Fire Services to ensure suitable fire fighting infrastructure is
provided. To this end any necessary fire hydrants shall be clearly shown on the plans
submitted for both Operational Works and Building Works approval and if a booster pump is
deemed necessary, the plans shall indicate where the fire truck is to be accommodated in
order to provide boosting to the water supply.
Earthworks
55. Filling works required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any natural
watercourses. Detailed site surveys indicating natural surface levels and contours of the
adjoining properties must be provided with the application for a Development Permit for
Operational Works for Filling and Drainage.
This may require the design and construction of drainage pipes and/or an overland flow-path
within the development site that caters for drainage from the adjoining sites for a design storm
with an Average Recurrence Interval of 1 in 100 years. A private easement for the Drainage of
Water encompassing the drainage pipes or overland flow-path will also be required. In this
regard a Development Permit for Operational Works shall be obtained.
Should evidence be provided to Council indicating that no additional ponding of stormwater
will occur on the adjoining properties the requirement for the drainage pipes, overland flow-
path and easement shall not apply.
Page 7 of 20
Page 8
2007/738
56. Earthworks carried out on site shall not affect the structural integrity of any of the existing
fences or structures that border the development site. Fences that are affected shall be
replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
any fences to be replaced shall be clearly shown on the plans submitted for Operational
Works approval.
57. Any filling works shall be retained with constructed walls that are designed and located to
minimise impacts on the vegetated buffers areas indicated on the approved plan of
development.
Acid Sulfate Soils
58. As the site is located below the 5m AHD, any excavation works or earth disturbance consisting
3 3
of 100m or greater and/or any filling works consisting of 500m or greater and with an
average depth of 0.5m or greater will need to be carried out in accordance with State Planning
Policy 2/02 Planning and Managing Development Involving Acid Sulfate Soils. In this regard
appropriate testing and supporting documentation prepared by a suitably qualified specialist
shall be submitted to Council for approval prior to obtaining a Development Permit for
Operational Works.
59. Excavated soil shall be lime treated in accordance with the recommendations of the Acid
Sulfate Soil Investigation dated August 2003 by Golder Associates Pty Ltd.
Environmental
60. The applicant shall provide a professionally prepared Environmental Management Plan (EMP)
for the site to be submitted to Council for approval prior to obtaining a Development Permit for
Operational Works. The management plan shall be for the construction phase and the
operational phase of the development and shall address:-
60.1. Management of the naturally acidic soils identified on the site;
60.2. Protection of vegetation with the Environmental Buffer and Landscaped Buffer areas;
60.3. Run-off water quality management, sediment and erosion control;
60.4. Vegetation removal and disposal, including the use of fauna spotter;
60.5. Removal of environmental weeds; &
60.6. Rehabilitation of disturbed areas within the identified buffer areas.
61. All Class 1, Class 2 and Class 3 pest plants declared under the Land Protection (Pest and
Stock Route Management) Act 2002 are to be controlled on the site prior to Council
endorsement of the plan of survey. In this context “controlled” shall mean, for class 1 and 2
pests, completely eradicated. For class 3 pests it shall mean removal of the plants where they
threaten environmentally significant areas of the site such as riparian zones and areas of
natural vegetation.
Where class 3 plants are removed as a result of this condition and there is not sufficient
natural regeneration of native species, the areas shall be replanted with endemic native
species so that a sustainable natural ecosystem is restored.
Council’s Conservation Management Supervisor will not inspect the site until 30 days after the
weed treatment and replanting is complete.
62. A Vegetation Protection Area shall be provided in the northeast corner of the property as
indicated on drawing the approved plan and as recommended by the Ecological Survey
prepare by Pederson Biological and Environmental dated 15 April 2003. This area shall be of
a triangular shape, with corners being approximately 54 metres along the northern boundary
and 37 metres along the eastern boundary from the northeastern corner of the property.
Page 8 of 20
Page 9
2007/738
63. In order to protect the vegetation within the Vegetation Protection Area an Environmental
Covenant(s) (as defined by Part 6 division 4A of the Land Title Act 1994) shall be created at
no cost to Council. The covenant(s) shall be for the protection of the site’s environmental
values so that it retains and enhances the vegetation and allows for fauna movement.
64. The existing vegetation within the 10m wide Landscape Buffer areas adjacent to the western,
northern and eastern boundaries shall be retained, with the exception of any bio-retention
basins, raingarden areas or rainwater tanks, and a 3metre strip adjacent to the buildings for
construction purposes. Plans shall be submitted to the Council for approval that clearly
indicates the vegetation retention areas prior to obtaining a Development Permit for
Operational Works. Temporary fencing shall be provided to protect these trees during the
construction phase.
65. Where retained trees are located in areas proposed to be filled on the site (or are located on
neighbouring allotments to the area to be filled), there will be a need to prevent fill material
from being placed on the tree’s root system. To this end, the design of any filling works will
need to incorporate terracing around the tree or a similar means of ensuring that the natural
ground level around the trees remains generally the same as existing. These measures shall
clearly be shown on the plans submitted for Operational Works approval and any drainage
required to drain these areas shall also be shown on the plans.
66. An environmental maintenance period of 12 months shall commence after the Landscaped
area has been re-vegetated and all declared & environmental weeds have been removed from
the entire property. Council’s appointed Environmental Officer shall sign the maintenance
period ‘on’ and ‘off’ after this work has been successfully completed. To this extent, the
Officer has the discretion to pause the maintenance period if work has not been carried out as
instructed or if lengthy time delays occur.
Erosion and Sediment Control
67. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
Contributions Towards Council Infrastructure
68. Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or
upgrading various infrastructure at the rates applicable at the time of payment. An estimate
only of the contribution amounts under the current Council policies and requirements is
outlined in the table below:
Contribution Required For: Amount:
PSP12 – Public Open Space Contributions (Park) $13,086
PSP16 – Sewerage Headworks Contributions $31,492
PSP17 – Water Supply Headworks Contributions $27,331
PSP20 – Pathway Trunk Network Contributions $13,911
TOTAL Contribution Amount = $ 85,820
Please note, that these amounts are all subject to variations in the Consumer Price
Index, All Groups Brisbane from March 2008 until the date of payment.
Page 9 of 20
Page 10
2007/738
All contributions must be paid prior to the issue of a Development Permit for Operational
Works
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
contributions not be paid at the due time, Council shall call upon the trading bank guarantee in
full.
Processing of bonds for security where specific Council approval has been given for the
bonding of contributions will incur an administration fee in accordance with Council’s Land
Development Commercial & Regulatory Fees at the time of lodgement.
In the event that the Development Permit for Material Change of Use of Premises lapses or is
cancelled, the paid contributions and/or the trading bank guarantee will be returned.
General
69. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works, which shall be submitted in conjunction with an
application for a Development Permit for Operational Works. In this regard a DXF/DWG file
on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction with
any application for Operational Works.
70. Digital detailed designs including drawings, calculations, specifications and a schedule of
works, shall be submitted with any application for a Development Permit for Operational
Works in respect of stormwater drainage works. The design shall be in accordance with
Council’s Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage
and Earthworks. To avoid conflict with underground pipes or services, all existing and
proposed services required by the development shall be shown on the plans.
71. A construction management plan/strategy to ensure no damage occurs to Council services
shall be prepared by a suitably qualified Registered Professional Engineer and submitted to
Council in conjunction with any application for Operational Works.
72. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
73. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
74. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
75. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
76. Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Page 10 of 20
Page 11
2007/738
Environmental Health
77. Refuse containers must be provided in accordance with the requirements of the Environmental
Protection (Interim Waste) Regulation 1996 and (Waste Management) Regulation 2000, for
the storage and collection of refuse.
78. The Operational Waste Management Plan (OWMP) dated 20 May 2008 submitted is not
approved and shall be amended and re-submitted to Council for approval prior to the issue of
a Development Permit for Operational Works. The revised OWMP shall address the following:
78.1. Additional skip bin storage areas for Bulk Recyclables for the eastern and western
areas of the development in addition to the refuse storage areas as indicated in the
Operational Waste Management Plan dated 20 May 2008 Job No. 7800/62.
78.2. Provision for waste generated from food, mechanical, boat repair and other industries,
in accordance with the range of approved uses.
78.3. A minimum separation distance of 500mm between bins to be collected by robotic arm.
78.4. Flat or minimal grades where industrial bins are to be manually shifted by refuse
collectors.
78.5. The role of the Body Corporate Manager is to be clarified. If no on-site manager is
proposed then the OWMP is to be revised to adequately address the day-to-day
management of waste issues on the site.
79. There shall be no awnings or building overhangs along the refuse truck travel path or
manoeuvring areas.
80. A Waste Management Plan (Construction) shall be submitted in accordance with Planning
Scheme Policy 11, Waste Management Plans. Waste storage areas are to provide for
adequate separation of all reusable, recyclable and waste materials. These shall be located so
that they are convenient and safe to use (refer to Noosa Council Waste Management Code).
The Plan shall contain the following information:
The site area for the storage and separation of waste is to be shown on the plan
drawings accompanying the application.
A waste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled – reused or disposed.
Page 11 of 20
Page 12
2007/738
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected Estimated On-site Off-site *specify
waste volume *specify *specify contractor
materials (m³) proposed re- contractor and landfill
use or on- and site or other
site recycling recycling disposal site
methods outlet
Excavation
material
Green waste
Bricks
Concrete
Timber-
please specify
Plasterboard
Metals -
please specify
Asbestos
Other - please
specify
The purpose of the Waste Management Plan is to facilitate the segregation of waste for
the effective reuse and recycling of such materials. Additionally Council rewards those
who segregate waste by significantly reducing disposal fees at the landfill some items
are free. Higher gate fees are charged for loads of mixed waste.
81. Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool
pumps, etc.) shall comply with the following requirements:
The equipment shall be installed and located in a manner that prevents excessive noise in
accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-
the-spot fines) may apply for offences.
A person must not use equipment on any day if it makes or causes noise to be made –
From 10pm to 7am: More than the lower of either –
40 dB(A)
3 dB(A) above the background noise level
No audible noise for pool pumps apply during these hours.
From 7am to 7pm: More than the lower of either –
50 dB(A)
5 dB(A) above the background noise level
From 7pm to 10pm: More than 3 dB(A) above the background noise level.
82. Written certification is required from a suitably qualified person confirming that the noise levels
from all mechanical equipment comply with the above condition when measured at either the
residential boundary or outside the most exposed part of an affected building, whichever is the
closest to the equipment.
Page 12 of 20
Page 13
2007/738
The assessment and certification is required immediately after installation of the equipment
and prior to any occupation of the building, and in a format approved by Council. This
assessment must take into account noise from any other fixed equipment on the property e.g.
swimming pool pump, heating/cooling equipment, etc that may increase the overall noise level
emitted.
Advice: It is highly recommended that the person you engage to certify the installation is
involved at the plan development stage so they can recommend where this equipment is best
located. They can also advise about noise enclosures and can make other suggestions to
avoid noise problems. It is a lot more costly to try and deal with noise problems after
everything is built.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Acid Sulfate Soils Advice Agency Department of PO Box 573
Natural Resources NAMBOUR QLD 4560
& Water
A copy of any referral agency conditions is attached.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Rev. Plan / Document Name Date
Sheet No. 1 “Industrial Development at Precinct N May 2008
Gateway Drive Noosaville” prepared by
Herwig Hartl trading as Smartarch
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is advised that development contributions and infrastructure charges applicable
to this development approval have been based on the following Uses Class/ Uses and
applicable quantities:-
Existing Development Approved Development
Existing Use Approved Use Class / Approved
Existing Quantity
Class / Use Use Quantity
Industrial Business –
Detached House Vacant Land 3,840 m2
Type 2
2. The applicant is informed that approval of this development application will trigger an
Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
Charges Plan for the estimated amount of $134,661 and is subject to variations in the
Consumer Price Index, All Groups Brisbane from March 2008 until the date of payment. An
Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
Planning Act 1997.
Page 13 of 20
Page 14
2007/738
3. The applicant is informed that payment via credit card transaction will not be an acceptable
method of payment for development contributions conditioned in this permit or for
infrastructure charge notices issued separately.
4. The plans for the proposed building work have not been assessed for compliance with the
requirements of the Building Code of Australia as they relate to people with disabilities. Your
attention is drawn to the matter that either or both the Disability Discrimination Act 1992
(commonwealth) and the Anti-Discrimination Act 1991(Queensland) may impact on the
proposed building work.
Noosa Council recommends that the following matters be considered to address equitable
access and facilities in the building:-
a. The building and environs should be designed to meet the requirements of the
Human Rights and Equal Opportunity Commission “Advisory Notes on Access to
Premises” and AS1428.2;
b. Applicants should be aware that a “Disability Standard on Access to Premises is
being developed and most likely will result in changes to the Building Code of
Australia;
c. Any services and facilities in the building complex must allow independent, dignified
and equitable use of the services and facilities for all people.
5. This proposal has not been assessed in relation to the spread of fire between properties /
buildings. It is the building certifiers responsibility to assess the requirements for fire services,
fire separation and appropriate methods of construction as part of the building works approval
process. Referral to the Queensland Fire and Rescue Service (QFRS) may be required as
part of the Building Approval process.
6. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
6.1. On a Sunday or public holiday, at any time; or
6.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
7. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
declaration outlining the cost of the operational works must be submitted to Council with the
lodgement of any application for operational works over the site.
8. The applicant is advised that a Compliance Permit for all plumbing and drainage works within
the boundaries of the development site shall be obtained from Council’s Plumbing Services
Section prior to obtaining a Development Permit for Building Works.
9. Where any food premises is included in a development, the following is required:
9.1. Plans and application is to be made to Council’s Environmental Health Section for
approval prior to any building approval, fitting out or use of the premises.
9.2. A statement indicating the purpose of the food premises, type of food sold, proposed
menu and maximum number of patrons at any time, is to accompany the application
for plan approval.
Page 14 of 20
Page 15
2007/738
9.3. Construction and use of the food premises should comply with Council’s Food
Premises Policy and the Food Safety Standards. (Both available from Council)
9.4. Toilets for customers and staff to be provided in accordance with Building Code of
Australia. Obtain advice from a building certifier on numbers and standards, including
disable access.
9.5. Plans and approval is required for any mechanical exhaust ventilation system, which
should comply with AS1668. A certificate from the installer certifying the system
complies with the Standard must be obtained and lodged with Council prior to
commencement of trade.
9.6. Any Licensable Food Business, as defined in Chapter 3 of the Food Act 2006, must
obtain a Food License from Council, prior to use of those premises.
10. Where any part of the premises is proposed to be used for an industrial purpose defined as an
environmentally relevant activity under the Environmental Protection Act 1994 (E.g. motor
vehicle workshop, engineering workshop, plastic manufacturer etc), a separate development
approval and registration is required prior to commencement of that use.
11. In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
where it could reasonably be expected to move into a roadside gutter, storm water drain or a
watercourse. On the spot fines apply for such offences.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
8 PROPERTY NOTES
Not applicable
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable
Page 15 of 20
Page 16
2007/738
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Building Works All Building Works
Development Permit for Operational Access, Carparking and Internal Pathways, Site Civil
Works Works, Stormwater Drainage including the Treatment
Train, Frontage Works, Earthworks and Acid
Sulphate Treatment, Erosion and Sediment Control
and Landscaping
11 SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Advertising Devices Code
12 SUBMISSIONS
Not applicable
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Despite the proposal’s conflict with the Biodiversity Code contained in The Noosa Plan, the existing
development commitments for the site provide sufficient planning grounds to support the application.
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.
During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).
15 OTHER DETAILS
Please note that an Infrastructure Charge in accordance with the Coastal Major Road Network
Infrastructure Charges Plan has been triggered by the approval of this development application. An
Infrastructure Charge Notice is attached in compliance with Chapter 5 of the Integrated Planning Act
1997.
Should you wish to obtain more information about Council’s decision electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,
Tracy Jones
SENIOR PLANNING OFFICER
Page 16 of 20
Page 17
2007/738
Referral Agency Conditions –
Department of Natural Resources &
Water
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
Page 17 of 20
Page 18
2007/738 Page 18 of 20 [OCR of page images] 2007/738 THIRD PARTY ADVICE MATTERS Aboriginal Cultural Heritage Act 2003 NRW also takes this opportunity to advise you of an applicant's responsibility under the Aboriginal Cultural Heritage Act 2003. Under section 23 of the Aboriginal Cultural Heritage Act 2003 a person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage (the “cultural heritage duty of care"). Maximum penalties for breaching the duty of care are $750,000 for a corporation and $75,000 for an individual. The applicant will ensure compliance with the cultural heritage duty of care if the applicant is acting in accordance with the gazetted cultural heritage duty of care guidelines. An assessment of the proposed activity against the duty of care guidelines will help determine whether or to what extent Aboriginal cultural heritage may be harmed by the proposed development. It will also help determine if the applicant needs to undertake a search of the cultural heritage database and register. If following an assessment of the duty of care guidelines the applicant believes cultural heritage may be harmed by the proposed activity, the applicant should contact the Cultural Heritage Coordination Unit for further advice on (07) 323 83838 or e-mail cultural. [email protected] information on cultural heritage, together with a copy of the duty of care guidelines and cultural heritage search forms, may also be obtained from www. nrw.qid.gov.au/cultural_heritage/index.html | look forward to receiving a copy of the decision notice for the application in due course. A copy of this Referral Agency Response has been issued to the applicant. Should you have any questions about this matter please contact Mr Nick Hill on (07) 5451 2287, quoting the reference number IAOS07NAMO004. Yours sincerely Vee Daniel Leo AlSenior Officer (Planning & Environment) South East Region (Nambour) cc. Ken Hicks & Associates Attention: Scott Sobey PO Box 6380 MAROOCHYDORE QLD 4558 Department of Natural Resources and Water Page 2 of 2 Page 18 of 20
Page 19
2007/738
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
(5) If an application is processed under section
The following is an extract from the Integrated 6.1.28(2), appeal rights for submitters for the
Planning Act (Chapter 4). application are available only for the aspects of the
development that would have required public
Division 8 - Appeals to court relating to
notification under the repealed Act.
development applications
Appeals by applicants (6) If an application involves assessment
4.1.27.(1) An applicant for a development against a concurrence agency code, appeal rights
application may appeal to the court against any of for submitters for the application are not available
the following- against the part of the approval that represents the
(a) the refusal, or the refusal in part, of a concurrence agency’s response for the code.
development application; Appeals by advice agency submitters
(b) a matter stated in a development approval, 4.1.29.(1) An advice agency may, within the limits
including any condition applying to the of its jurisdiction, appeal to the court about the
development, and the identification of a code giving of a development approval for a
1
under section 3.1.6; development application if-
(c) the decision to give a preliminary approval (a) the development application involves impact
when a development permit was applied for; assessment; and
(d) the length of a currency period; (b) the advice agency told the applicant and the
(e) a deemed refusal. assessment manager to treat its response to
the application as a submission for an appeal.
(2) An appeal under subsection (1)(a) to (d)
must be started within 20 business days (the (2) The appeal must be started within 20
“applicant’s appeal period”) after the day the business days after the day the decision notice or
decision notice or negotiated decision notice is negotiated decision notice is given to the advice
given to the applicant. agency as a submitter.
(3) An appeal under subsection (1)(e) may be Appeals for matters arising after approval given
started at any time after the last day a decision on (co-respondents)
the matter should have been made. 4.1.30.(1) For a development approval given for a
Appeals by submitters development application, a person to whom any of
the following notices have been given may appeal
4.1.28.(1) A submitter for a development
to the court against the decision in the notice-
application may appeal to the court about-
(a) a notice giving a decision on a request for
(a) the giving of a development approval, including
extension of the currency period for an
any conditions (or lack of conditions) or other
approval;
provisions of the approval; or
(b) a notice giving a decision on a request to make
(b) the length of a currency period for the approval.
a minor change to an approval.
(2) The appeal must be started within 20
(2) The appeal must be started within 20
business days (the “submitters appeal period”)
business days after the day the notice of the
after the day the decision notice or negotiated
decision is given to the person.
decision notice is given to the submitter.
(3) Subsection (1)(a) does not apply if the
(3) If a person withdraws a submission before
approval resulted from a development
the application is decided, the person may not
application (superseded planning scheme)
appeal the decision.
that was assessed as if it were an
(4) If an application involves both impact application under a superseded planning
assessment and code assessment, appeal rights scheme.
for submitters are available only for the part of the
(4) Also, a person who has made a request
application involving impact assessment.
mentioned in subsection (1) may appeal to
the court against a deemed refusal of the
request.
1
Section 3.1.6 (Preliminary approval may override
local planning instrument)
Page 19 of 20
Page 20
2007/738
(5) An appeal under subsection (4) may be For Building Works Only
started at any time after the last day the Rights of appeal conferred by Section 4.2.9 of the
decision on the matter should have been Integrated Planning Act 1997 as follows:
made.
Division 3 – Appeals to tribunals relating to
development applications
Division 9 - Appeals to court about other
matters Appeals by applicants
Appeals for matters arising after approval given
(no co-respondents)
4.2.9(1) An applicant for a development application
4.1.31.(1) A person to whom any of the following may appeal to the Building and Development
notices have been given may appeal to the court Tribunal against any of the following-
against the decision in the notice-
(a) the refusal, or the refusal in part, of a
(a) a notice giving a decision on a request to development application;
change or cancel a condition of a development
approval. (b) a matter stated in a development approval,
2 including any condition applying to the
(b) a notice under section 6.1.44 giving a decision development, and the identification of a code
to change or cancel a condition of a under section 3.1.6;
3
development approval.
(c) the decision to give a preliminary approval when a
(2) The appeal must be started within 20 development permit was applied for;
business days after the day the notice of the
(d) the length of a period mentioned in section 3.5.21
decision is given to the person.
currency period;
(3) Also, a person who has made a request
(e) a deemed refusal.
mentioned in subsection (1)(a) may appeal
to the court against a deemed refusal of the (2) An appeal under subsection (1)(a) to (d) must
request. be started within 20 business days (the “applicant’s
appeal period”) after the day the decision notice or
(4) An appeal under subsection (3) may be negotiated decision notice is given to the applicant.
started at any time after the last day the
(3) An appeal under subsection (1)(e) may be
decision on the matter should have been started at any time after the last day a decision on the
made. matter should have been made.
Appeals against decisions to change approval The Registrar for the Building and Development
conditions under the repealed Act Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a http://www.localgovernment.qld.gov.au/
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
(3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to
the court against the decision or the conditions
applied.
(2) The appeal must be started within 20
business days after the day notice of the decision
is given to the applicant.
2
Section 6.1.44 (Conditions may be changed or
3
cancelled by assessment manager or concurrence Section 3.1.6 (Preliminary approval may override
agency in certain circumstances) local planning instrument)
Page 20 of 20
Used in these records
Decision Notice - 010.2007.00000738.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 185 KB (small file)
- File type
No other editions are linked here.