74. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
ED 23114 OPW - 01 A Site Layout Plan by Element Design 5/04/2023
ED 23114 OPW - 02 A Planting Plan by Element Design 5/04/2023
ED 23114 OPW - 03 A Planting Plan by Element Design 5/04/2023
ED 23114 OPW - 04 A Planting Plan by Element Design 5/04/2023
ED 23114 OPW - 05 A Plant List & Specification Plan by 5/04/2023
Element Design
RECONFIGURATION OF LOT
When Conditions Must Be Complied With
75. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
- - Community Title Subdivision Plan, prepared 14/11/2022
by applicant
Currency Period
76. This development approval lapses if the use has not happened by 15 June 2027, unless an
application to extend the currency period is approved by Council.
Plan Sealing
77. Prior to Council sealing the plan of survey, all works described within this Decision Notice
must be completed and accepted by a Council representative.
Services
78. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with the approval for Operational Works and the standards and requirements of
the relevant service provider.
79. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
80. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
81. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the landscape conditions of this
Decision Notice.
*(Refer to Advisory Note)
Page 11 of 24
Document Set ID: 22467236
Version: 3, Version Date: 20/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - MCU22 0197 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 503 KB (small file)
- File type
No other editions are linked here.