Hydraulic Assessment 29 August 2024
Attached to the e-mail Operational Works Application OPW25/0049 - Cover Letter, DA Form 1, Hydraulic Assessment 29 August 2024 - 38 Barina Ct_ Pomona - Email 1 of 2.
3.1.1 Modelling Parameters
A hydrologic analysis of the Site and contributing catchments has been undertaken to determine the pre- and post-development peak
discharges. Key hydrologic model details are provided in Table 3.2.
TABLE 3.2: KEY MODELLING PARAMETERS – HYDROLOGY
Parameter Details Basis / Comments
Software WBNM -
Approach ARR 2019 Methodology -
Pervious Initial and Continuing
51mm and 3mm/hr ARR Data Hub
Losses
Lat: -26.383
Temporal Patterns East Coast North (ECNorth) Long: 152.839
Median pre-burst depths have been subtracted
Pre-Burst Median from the total storm initial loss.
BOM Rainfall IFD Data System
IFD - Lat: -26.383
Long: 152.839
3.1.2 Rational Method Validation
The peak flow estimates from the hydrologic model were validated using the Rational Method at the catchment outlet. The difference
between peak flows was 0.1m³/s (3%), indicating that the WBNM model is suitable for use and there are no gross errors. As such the model
is considered suitable for this assessment.
TABLE 3.3: PEAK DISCHARGE COMPARISON – EXISTING CASE RATIONAL METHOD & WBNM
1% AEP
WBNM (m3/s) 3.7
Rational (m3/s) 3.6
Difference (m3/s) 0.1
Difference (%) 3
38 BARINA COURT, POMONA I BBNE00000_0020-REP-001-0 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.