Hydraulic Assessment 29 August 2024
Attached to the e-mail Operational Works Application OPW25/0049 - Cover Letter, DA Form 1, Hydraulic Assessment 29 August 2024 - 38 Barina Ct_ Pomona - Email 1 of 2.
2. SITE INSPECTION
A site inspection was completed on 25 July 2024, with a general overview of the existing dam overflow and outlet channel provided below.
• Figure 2.1 highlights the current overflow point from the dam, which highlights a number of tree roots growing across overflow point
and has resulted in a build-up of debris, silt and plant growth at this location. The level at which the dam overflows appears to have
increased over time with the sediment build up.
• Figure 2.2 details the upstream section of the overflow channel which highlights a number of tree roots from the adjoining pine tree
growing across the overflow channel with channel batters noted as being quite steep.
• Figure 2.3 details the downstream section of the overflow channel which highlights the overflow is currently bare earth with channel
batters noted as being quite steep and signs of erosion occurring.
FIGURE 2.1: DAM OVERFLOW
38 BARINA COURT, POMONA I BBNE00000_0020-REP-001-0 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.