SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 11 JUNE 2019
Previous Council Consideration
Ordinary Meeting, 15 November 2018, Item 2, Page 11
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 6 November 2018 and
A. Support the urgent completion of a Shoreline Erosion Management Plan for Noosa Spit
and Noosa Main Beach subject to funding being provided in Budget Review 2; and
B. Provide a status update to Council on a quarterly basis.
Council Ordinary Meeting, 21 March 2019, Item 8, Page 9
That Council note the report by the Project Coordinator – Flooding, Coastal and Foreshore to the
Services & Organisation Committee Meeting dated 12 March 2019 providing an update on the
development of a Shoreline Erosion Management Plan (SEMP) and also note the formation of a
staff Noosa Spit SEMP Project Working Group to oversee that project.
Finance
The awarded contract for the Noosa SEMP work is well within the proposed budgets detailed in
the report to the Services and Organisation Meeting dated 6 November 2019 (Ordinary Meeting
15 November 2019).
Risks & Opportunities
An update to the risk matrix, presented to Service and Organisation Committee on 12 March
2019 is presented below.
Risk Description Likelihood Consequence
SEMP and proposed actions are not complete before intervention Implementation of
is required. Unlikely unplanned /
Note: Recent reduction in the rate of shoreline recession has emergency works
provided additional time to complete this project successfully. required.
Remediation costs will continue to grow until a solution can be Certain Increased costs to
implemented. replace lost sand
and habitat.
A failure to remediate may expose Council to a risk of litigation Legal costs and /
from properties that are currently protected by the Noosa Spit Possible or costs awarded
peninsula. as damages if it is
found Council
Note: A legal opinion on this matter is currently being sought. failed in their duty
of care.
Reputational damage, due to a perception of poor management. Possible Reputational.
Consultation
External Consultation - Community & Stakeholder
To be undertaken within the project.
Internal Consultation
Internal consultation is being conducted through the Noosa Spit SEMP Project Working Group.
Page 72 of 109
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.