PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 JUNE 2019
Each report concludes as follows:
Geotechnical Peer Review:
“The responses generally address most of the issues raised.
The sand dune in its existing condition is potentially unstable. In this regard the site is
similar to other areas which have been developed within the Noosa Sand Dune Stability
Problem area.
The proposed development on the western side of the creek does not attempt to avoid
areas of potential instability and the proposed structures will be constructed on the
potentially unstable slopes. There are no proposals to stabilise the land.
It appears that the overall approach adopted by the geotechnical reports is to accept that a
landslide will occur but design the structures to be secure in the event of a landslide. That
is, the land may slide down the hill but the structures will be left suspended above the
landslide on piers founded at depth below the potential zone of instability.
Council needs to be aware that if the proposed development is approved it will be on this
basis.”
Ecological Peer Review:
“While responses have been provided to each of the information request items, most of
Council’s requests have not been met. Of greatest concern are that:
Koalas are known to inhabit the area and the site is likely to provide an important
avenue for movement for the species. This is not reflected within the ecology report.
Neither the riparian buffer of 10 m from top of creek bank or wildlife corridor of a
minimum of 50 m vegetated width are possible with the current design.
The proposal should therefore not be approved for development according to these plans.”
Stormwater Peer Review:
Quantity
“The legal point of discharge is the existing flow path within the site.
The Rational Method has been used to show that the development will have a minor
(+0.3%) impact to peak flows, resulting in a minor increase (1mm) in flow depth within the
existing flow path. This will not cause any actionable nuisance to downstream properties.
The site is located at the lower end of a larger forested catchment and development has
been limited to the up-slope areas of the site to leave the drainage line within the site
undeveloped. It is our opinion that providing detention measures on site would not provide
any benefit.”
Quality
“Proprietary stormwater treatment devices (SPEL StormFilter and Stormsack or approved
equivalent) and rainwater harvesting tanks are included in the model. It is noted that a
detailed Operational Phase Maintenance Plan is to be included in future Operational Works
applications as these assets will be privately owned and maintained.
Based on the information available, the water quality objectives will be met by the proposed
treatment train.”
Conditions of approval are recommended as part of this report.
Page 77 of 133
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.