Original source · versioned page text
2017-07-11 Planning & Environment Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 11 JULY 2017
Representations to Conditions
Condition 2 – List of approved Plans
2. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA-02 P5 Site Plan, prepared by Red Dog Architects 19/10/2016
DA-05 P5 North Elevation, prepared by Red Dog Architects 19/10/2016
DA-06 P5 South Elevation, prepared by Red Dog Architects 19/10/2016
DA-07 P5 East & West Elevations, prepared by Red Dog Architects 19/10/2016
Applicant’s Request
Condition 2 references the approved plans for the development. The submitted Signage Plan
(DA-08 Rev P5, prepared by Red Dog Architects, dated 19.10.16 – enclosed here) is not
included in the list of approved plans in Condition 2. Subsequent discussions with Council’s
Development Planner, Glen Conforti, have confirmed that the Signage Plan was intended to be
included as an approved plan.
It is requested that Condition 2 is amended to reference the submitted Signage Plan.
Assessment
Signage plan (DA-08 Rev P5) prepared by Red Dog Architects dated 19 October 2016 was
originally provided by the applicant for which was intended to be included in the list of approved
plans. It is agreed to amend Condition 2 to include this plan. The signage shown on the plan is
reflective of the originally approved signage.
Condition 27(e & k) - Stormwater
27 The site must be provided with a stormwater drainage system connecting to a lawful point
of discharge. The works must be undertaken in accordance with an Operational Works
approval and the Queensland Urban Drainage Manual, and must include in particular:
e) A stormwater quality treatment system. The stormwater treatment must generally be
in accordance with the Stormwater Management Plan for Highway Service Centre
Cooroy, project number 161968 by Covey Associates, dated October 2016 except
where alteration to impervious area and water quality treatment dimensions are
necessary to achieve the following objectives as predicted in MUSIC modelling in
accordance with the Water by Design MUSIC modelling guidelines.
State Planning Policy Environmental Approved Plan of
Protection Water Development Water
Policy Water Quality Quality Criteria
Objectives
Total 80% reduction compared <6mg/L 90th%ile 15mg/L
Suspended to an unmitigated
Solids development
Total 60% reduction compared Maximum 50ug/L Maximum 0.03mg/L
Phosphorous to an unmitigated
development
Total Nitrogen 45% reduction compared Maximum 500 ug/L Maximum 0.3mg/L
to an unmitigated
development
Page 23 of 78
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.