SPECIAL MEETING AGENDA 27 JANUARY 2021
Pathways
7. Concrete pedestrian pathways, detailed on the plans, must be provided in accordance
with Council’s standard drawing RS-065 and any associated addendum. The works
must include:
a. Any reinstatement of verge area must smoothly match the new pathway,
b. The provision of topsoil, turf and any necessary stormwater drainage measures
to prevent ponding and excessive runoff over the pathways.
Stormwater Drainage Management
8. In conjunction with the development application for operational works, provide an
updated Stormwater Quality Management Plan and engineering drawings which are
based on a revised model which addresses the following:
a. Only include those sub-catchments which form part of the proposed works or
which contribute flow to the devices proposed to treat the proposed works;
b. Only include treatment devices which actually exits or which are proposed to be
built or refurbished as part of the proposed works;
c. Existing GPTs are not to be modelled as receiving and treating roofwater unless
this physically occurs on site; and
d. Additional treatment devices are to be provided as necessary within the car
parking area in order to meet the pollutant load reduction design objectives
specified by the Water Sensitive Design Code.
9. Proposed and refurbished bioretention devices are to be designed generally in
accordance with the Bioretention Technical Design Guidelines (Water by Design, 2012)
and IPWEAQ standard drawings
10. Permanent educational signage must be erected to educate the public about the
function of the bioretention device(s). The dimensions, standard, presentation and
location of the educational signage must be in accordance with an Operational Works
approval.
Public Services
11. All necessary approvals from external service providers and external parties on which
the development works are proposed or impacted on must have been obtained and a
copy of approval/s supplied to Council prior to the commencement of the works.
Easements
12. Where required, any public or third party infrastructure located on the subject site must
be placed within an easement registered against the title of the property and in
accordance with the requirement of the public service provider.
13. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard
easement terms. Draft easement documentation must be submitted to Council for
endorsement.
Landscaping Works
14. The development site must be landscaped. The works must be undertaken in
accordance with the Noosa Plan 2020 Planning Scheme Policy 2 – Landscaping for
that specific area and must include in particular:
a. Carpark shade trees in a minimum pot size of 45L for every four carparks
Page 5 of 41
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.