Council archive · source document
Minor Change Existing Approval 132001.210127.4
Pathway Contributions
33. A pathway contribution of $5,343 towards external major pathways, in accordance with
Planning Scheme Policy PSP41 Pathway Trunk Network Contributions, shall be paid to the
Council prior to obtaining a Development Permit for Operational Works. This amount will be
subject to variations in the Consumer Price Index, All Groups Brisbane from September
2005 until the date of payment.
Stormwater Drainage
34. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site.
35. Deleted.
36. To ensure that polluted run-off does not enter Council’s stormwater drainage system or
nearby creeks, stormwater run-off from the carparking areas and the driveways shall have
the first flush (the first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor
provided on site prior to being permitted to discharge from the site.
All other clean stormwater, such as roof water, can bypass the grease/oil arrestor.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors, which shall be submitted to the Council for approval prior to obtaining a
Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Management Plan for the
development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit
for Operational Works has been issued in regard to the drainage scheme.
37. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
38. The existing sewer main that traverses the site and the ‘zone of influence’ (taken as the area
within a 45-degree angle measured from the invert of the sewer main to the finished surface
level) shall be accurately located and determined by a licensed Surveyor and shown on all
plans submitted for Operational Works approval.
To ensure Council’s sewer main is accessible for maintenance purposes and is protected
from risk of damage no structures requiring a building permit (eg. buildings, swimming pools,
retaining walls, raised terraces, etc) shall be constructed within this ‘zone of influence’ and
as such the applicant shall amend Operational Works plans including Building plans to
ensure compliance.
Town Water Supply
39. The new building and extensions shall be connected to Council’s existing town water supply
and be constructed in accordance with Council’s standards and requirements at no cost to
Council.
Earthworks
40. Any filling works required on site shall be carried out in accordance with Section 3.8 of
Council’s Engineering Design Standards Manual and so as not to cause the additional
ponding of water on any adjoining lands or the blockage of, or interference with, any natural
watercourses.
Erosion and Sediment Control
41. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
Page 5 of 13
Document Set ID: 23351231
Version: 3, Version Date: 14/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval 132001.210127.4Related documentApplication case desk ↗
About this file
- File size
- 194 KB (small file)
- File type
No other editions are linked here.