5.2 Construction Phase
Sediment generated during the construction phase shall be controlled in accordance with a site specific
Erosion and Sediment Control (ESC) Plan and kept on site throughout construction.
5.2.1 Silt and Sediment Erosion
A potential for sediment mobilisation/transportation exists during and beyond the construction of the
proposed development. This can elevate turbidity levels of stormwater runoff.
A RUSLE assessment of the site confirms proposed development is a Low Risk for soil loss (< 150
Tonnes).
Potential Causes
• Stormwater scour and erosion of excavated or stripped surfaces and stockpiled soils.
• Wind borne transportation of sediments.
• Disturbance/breakup of soil profile via vehicular traffic followed by stormwater scour
and erosion.
• Transportation of sediments from site via excavation vehicles.
Mitigating Measures
• Construction of silt fences around the development site located to cut off all runoff.
• Construction of a sediment basin throughout construction at a low point of the
development site.
• Provide 80-100mm crushed rock (no fines) hardstand under all vehicle paths expected
during construction. Generally, this would be provided from the existing crossover and
extended to a distance within the site that would accommodate the maximum delivery
vehicle length expected.
SCG Consulting Engineers Page 9 SCG Ref: 31131(SWMP)
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (RFI - SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.