Rfi - Swmp · MCU21/0156
5.2 Construction Phase
Sediment generated during the construction phase shall be controlled in accordance with a site specific
Erosion and Sediment Control (ESC) Plan and kept on site throughout construction.
5.2.1 Silt and Sediment Erosion
A potential for sediment mobilisation/transportation exists during and beyond the construction of the
proposed development. This can elevate turbidity levels of stormwater runoff.
A RUSLE assessment of the site confirms proposed development is a Low Risk for soil loss (< 150
Tonnes).
Potential Causes
• Stormwater scour and erosion of excavated or stripped surfaces and stockpiled soils.
• Wind borne transportation of sediments.
• Disturbance/breakup of soil profile via vehicular traffic followed by stormwater scour
and erosion.
• Transportation of sediments from site via excavation vehicles.
Mitigating Measures
• Construction of silt fences around the development site located to cut off all runoff.
• Construction of a sediment basin throughout construction at a low point of the
development site.
• Provide 80-100mm crushed rock (no fines) hardstand under all vehicle paths expected
during construction. Generally, this would be provided from the existing crossover and
extended to a distance within the site that would accommodate the maximum delivery
vehicle length expected.
SCG Consulting Engineers Page 9 SCG Ref: 31131(SWMP)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - SWMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.