Request to Change Current Application · OPW11/0023

of 66

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (10.6 MB): the original may take a few minutes to open or download. The page text below is quick to read.

    BIORETENTION BASIN & GROSS POLLUTANT TRAP
    PURPOSES FUNCTION
    The bioretention basins installed at Bunnings Noosaville provides treatment of stormwater runoff as
    well as improve the landscape amenity. The gross pollutant trap provides for primary treatment of
    stormwater runoff prior to it discharging into the bioretention basin in order to capture sediment and
    other gross pollutants.




    The purpose of this bioretention basin maintenance plan is to detail the operational phase
    maintenance requirements of the bioretention basins installed at the proposed Bunnings Warehouse
    at the corner of Gateway Drive and Noosa-Eumundi Dve. Routine maintenance of the bioretention
    basins shall be undertaken by Bunnings to ensure to efficient operation of the stormwater quality
    treatment train.



I   BIORETENTENTION BASIN
    PLANT ESTABLISHMENT

    Establishment of vegetation within the bioretention basin is of critical importance as vegetation helps
    maintain porosity of the filter media in the basin and removal of excess nutrients (considered a
    pollutant at the high levels typical of urban stormwater runoff). The plant establishment period within
    the first two years is the most intensive maintenance period with watering, weeding, and possible
    replanting to be carried out. The following schedule for watering of plants should be followed:



I   •

    •
            Week 1-2

            Week 3-6
                                      3 visits/week

                                      2 visits/week

    •       Week 7-12                 1 visit/week

    •       After Week 12     As required during dry spells




    REGULAR MAINTENANCE

    The Water Sensative Urban Design Technical Design guidelines for South East Queensland describe

I   the following typical maintenance requirements:




        •    Routine inspection of the bioretention basin profile to identify any areas of obvious increased
            sediment deposition, scouring from storm flows, rill erosion of the batters from lateral inflows,

Used in these records

About this file

File size
10.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Request to Change Current Application.pdf · 10.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.