Minor Change Existing Approval - RAL19 0018.01 (As Published)
41. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
42. All landscape works must be maintained generally in accordance with the approved design
for the life of the development.
Fauna Management
43. Vegetation must only be removed or disturbed in accordance with a Fauna Management
Plan (or part thereof) prepared by a qualified person* and endorsed through an Operational
Works approval.
*(Refer to Advisory Note)
44. The development must be undertaken in accordance with section 7.2 of the Ecological
Assessment Report v2 report prepared by North Coast Environmental Services report dated
27/06/2019. These requirements are to be prepared by a qualified person* and endorsed
through an Operational Works approval
*(Refer to Advisory Note)
Bushfire Management
45. The development must be carried out in accordance with section 5 and 7 of the Bushfire
Hazard Management Plan v2 prepared by North Coast Environmental Services report dated
27/06/2019, subject to the following the following inclusion:
a. A table specifying asset protection zones for each lots
b. A landholder booklet specifically designed for each lot which specifies asset protection
zone treatments
c. Include updated building envelope layouts
d. Allow for the retention and rehabilitation of the vegetation on the land area identified
as VU1 in the Ecological Assessment Report v2 report prepared by North Coast
Environmental Services report dated 27/06/2019.
The report must be resubmitted to Council incorporating the above amendments prior to the
issue of any Development Permit for Operational Works.
46. A copy of the Bushfire Hazard Management Plan listed within this Decision Notice must be
provided to the nearest fire authority.
47. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the bushfire management conditions
of this Decision Notice.
*(Refer to Advisory Note)
48. A clause must be included in the contract of sale for affected lots which requires future
dwellings to be constructed in accordance with any building siting and construction
requirements specified in the Bushfire Management Plan for the development.
Page 9 of 15
Document Set ID: 24931816
Version: 3, Version Date: 13/07/2026