Original source · versioned page text
Appendix G - Geotechnical Report
Total Concept Homes 20332-001-Rev0
15 December 2020
Table 3: Retaining Wall Design Parameters
Lateral earth pressure coefficients
Unit Friction
Retained material weight angle
Ka Ko
(kN/m3) (Degrees) Kp
(Cantilever wall) (Non-yielding wall)
Stiff to Very Stiff
18 26 0.39 0.56 2.56
Natural Clays
Weathered Phyllite
21 35 0.27 0.43 3.69
Rock
These parameters do not include allowance for surcharge above the wall, or additional loads imposed by
sloping ground.
Subsurface drainage must be installed behind any retaining walls in order to prevent the development of
hydrostatic pressure (e.g. slotted ‘aggi’ pipe wrapped in filter ‘sock’ placed in gravel backfill).
4.5 Drainage
Adequate site drainage should be installed to ensure that stormwater runoff is directed away from the
building walls and footings (e.g. swales in landscaped areas or grated drains across pavements up slope of
structures including retaining walls for the driveway). Diversion drainage should be installed above the crest
of all cut/fill batters, and toe of all cut batters. Uncontrolled flow of stormwater over embankment batters (e.g.
from gutter overflow during high intensity storms, or if formal arrangements are not in place for the retaining
wall on the neighbouring property to the south-west) has the potential to saturate and weaken the
embankment materials, potentially leading to slumping failure. Future building and landscaping must be
carried out to maintain good drainage.
Subsurface drainage must be installed behind any retaining walls in order to prevent the development of
hydrostatic pressure (e.g. slotted ‘aggi’ pipe wrapped in filter ‘sock’ placed in gravel backfill).
All excess stormwater collected on site must be directed by pipes to the legal point of discharge, at least 5 m
down slope from the proposed or existing structures. Surface dissipation, such as a rock weir or similar,
must be installed at the stormwater outlet(s) to minimse the risk of soil erosion at the discharge point..
Subsurface disposal of stormwater must not be undertaken.
5.0 SUMMARY & CONCLUSIONS
Based on the findings of our assessment we consider that there would be a Low Risk of slope instability
impacting the proposed development. This advice is subject to implementation of the recommendations
given in this report.
13/14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.