Delegated Report - Code - Planning - RAL26 0020 & OPW26 0090 (As Published) · RAL26/0020

of 14

Text shows just the words. Original shows the document exactly as it was published.

               10.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
               Engineering
               11.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               12.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               13.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
               14.    The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                      Technical Design Guidelines for South East Queensland” for all water quality devices to be
                      constructed on site.
               15.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
               Works within Road Reserve/Reinstatement
               16.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               17.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               18.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
               Site Access and Driveways
               19.    Driveway crossovers must be constructed in accordance with council’s Standard Drawings
                      RS-049 and RS-050.
               20.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               21.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete


                                                                                                     Page 9 of 14

Document Set ID: 25098866
Version: 8, Version Date: 03/09/2026

Used in these records

About this file

File size
1.3 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning - RAL26 0020 & OPW26 0090 (As Published).pdf · 1.3 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.