Waste Management Plan – Proposed Storage Shed Development

Queensland Environmental Technologies
Location: 19 Lowermill Road, Cooroy, QLD, 4563

Application number : OPW26/0011
Prepared for: Development Application – Additional Storage Shed
Date: 11th March 2026



1. Introduction

This Waste Management Plan has been prepared to support a development application
for the construction of a new storage shed at an existing site within the Noosa Shire
Council Local Government Area.

The proposed structure will be used solely for additional storage and will not introduce
new operational activities, staR, or processes that would significantly increase waste
generation on the site.

The purpose of this plan is to demonstrate that the existing waste management system
is adequate to service the development and that waste will continue to be managed in
accordance with local council requirements and good environmental practice.



2. Existing Waste Management Infrastructure

The site currently operates with an established waste management system that
adequately services existing activities.

Current waste infrastructure includes:

General Waste

   •   4 × 240 L general waste bins

Recycling

   •   2 × 240 L recycling bins

Bulk Waste

   •   1 × 2 m² skip bin

            o   Equivalent capacity: approximately 8 × 240 L general waste bins

            o   Current collection frequency: fortnightly
Log in to download the original file

Waste Management Plan QET.pdf · 61 KB (small file)

Full text of the other 3 pages

Page 2

Waste is stored in designated bin storage areas that are easily accessible for collection
vehicles and staR.



3. Proposed Development

The proposed development involves the construction of a new storage shed to provide
additional storage capacity for materials and equipment associated with the existing
site operations.

Key characteristics of the development:

   •   The shed will be used exclusively for storage

   •   No manufacturing, processing, or operational changes are proposed

   •   No increase in staRing levels is anticipated

   •   No new waste streams are expected to be generated

As a result, the development is not expected to significantly increase waste
volumes.



4. Expected Waste Generation

Given that the proposed shed is intended only for storage purposes, waste generation is
expected to remain consistent with current levels.

Typical waste streams associated with the site include:

   •   General oRice or operational waste

   •   Packaging materials

   •   Recyclable materials such as cardboard, paper, plastics, and containers

These waste streams are already accommodated within the existing bin infrastructure.

The current waste capacity (including the skip bin) is considered more than suRicient
to manage the minor waste associated with the additional storage facility.



5. Waste Storage and Handling

Waste will continue to be managed using the existing storage and handling
arrangements on site.

Key management practices include:

Page 3

   •   Waste stored in designated bins and skip containers

   •   Clear separation between general waste and recyclable materials

   •   Bins maintained in accessible and safe locations

   •   Waste storage areas kept clean and free from obstruction

   •   StaR encouraged to minimise waste and maximise recycling



6. Waste Collection

Waste collection will continue to occur through existing waste service providers.

Current collection arrangements:

Waste Type             Bin Size Quantity Collection Frequency

General Waste          240 L    4 bins    Regular collection

Recycling              240 L    2 bins    Regular collection

Bulk Waste (Skip Bin) 2 m²      1         Fortnightly

The 2 m² skip bin, which provides the equivalent capacity of approximately eight 240 L
general waste bins, provides significant additional waste capacity.

If waste volumes were to increase slightly in the future, the skip bin collection frequency
can be increased from fortnightly to weekly, ensuring suRicient waste management
capacity without requiring additional infrastructure.



7. Waste Minimisation Measures

The site will continue to implement waste minimisation practices including:

   •   Encouraging recycling of cardboard, paper, plastics, and containers

   •   Reducing unnecessary packaging where possible

   •   Reusing materials where practical

   •   Maintaining clearly labelled recycling bins

These measures aim to reduce landfill waste and improve overall waste management
outcomes.

Page 4

8. Conclusion

The proposed storage shed will not generate significant additional waste, as it will be
used solely for storage associated with existing site operations.

The site already maintains adequate waste management infrastructure, including:

   •   4 × 240 L general waste bins

   •   2 × 240 L recycling bins

   •   1 × 2 m² skip bin (equivalent to approximately 8 × 240 L bins)

   •   1 × 10 m² metal recycling bin

This existing capacity is considered suRicient to service the development.

Should waste volumes increase slightly in the future, the skip bin collection frequency
can be increased from fortnightly to weekly, ensuring ongoing compliance with
council waste management expectations.

Accordingly, the proposed development is not expected to place additional strain on
waste management services and is considered appropriate within the current waste
management framework

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.