Slope Stability Report
Fills ‐ Minimise height.
Support filled batters with engineered retaining walls or profile to an appropriate slope. For
this site, exposed fill batters are to be profiled no greater than the following :‐
Safe Batter Profile Angles/ Heights
Material Temporary Permanent Maximum Unsupported
Batter Height
Uncontrolled Fill 1V : 2H 1V : 4H 1.0 m
Engineered Controlled Fill 1V : 1H 1V : 2H 2.0 m
Note: The safe batter profile angles given are for un‐surcharged batters only.
Strip vegetation, topsoil and key/ bench the natural slope prior to filling. Fill is not to be simply
placed onto sloping surfaces greater than ~ 7 degrees.
Use clean fill materials and compact to engineering standards. Fill should be placed in
maximum 200 mm deep layers and be compacted to a minimum of 95 % Standard Maximum
Dry Density for cohesive (clay) material or 70 ‐ 90 % Relative Density for non‐cohesive (sand)
materials.
Structural filled batters should be over constructed by filling beyond the required final batter
face and cut back/ trimmed enabling machines to adequately compact the entire fill batter.
The finished platform must not slope towards the filled embankment which will allow water
to flow/ cascade over the exposed face. Ponding water on the platform must also be
avoided.
Consideration must be given to ensure that no surcharge loading from proposed filling is
imposed onto any existing infrastructure (including retaining walls, sewer and storm water
infrastructure etc..) unless it can be shown that measures have been implemented to
protect the stability of these structures during and after construction. This should be
determined by the design engineer.
7.3 Foundations
Footings should be founded within the medium dense to dense sand profile. This is to be
determined by the designing engineer.
The design engineer should consider the location of the existing swimming pool and
retaining walls to ensure that no additional surcharge is imposed on these structures as a
result of the proposed development.
On site foundation inspections including footing, slab & retaining walls must be undertaken
by a suitably qualified and experienced Geotechnical Engineer.
7.4 Drainage
The control of surface and subsurface water is critical to the overall performance of this site. All
surface and subsurface water must be captured and directed off site via a suitable outflow. Water
MUST not be left to pond on site, nor is water to be left to cascade over any cut or fill batter. Some
basic guidelines include but are not limited to:‐
Surface
Provide drains at the top of all cut and fill slopes, including those retained.
Discharge under controlled conditions (i.e. pipe) to the street drainage.
Provide and maintain general falls within drains to prevent blockage by siltation.
Line spoon drains to minimise the infiltration of surface water and make drains flexible
where possible.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.