20230025_Gympie Tce Hotel SWMP

of 34

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 13, section 1. The text section number identifies this passage in the reader.

     2. Sediment fencing along downstream of the work areas within the site to prevent sediment from leaving the
        construction area.

     3. A shakedown area is to be installed at the construction entry/exit to the proposed development area to
        minimise sediment being transported to and from the site.

     4. Ensuring any stockpiles and construction materials are located clear of overland flow paths and contained
        using sediment fencing downstream of these areas with upstream diversion berms to protect the stockpile.

     5. Diversion of upstream catchments around any exposed areas through the use of turfed catch drains or
        similar.


 5.2.2 Erosion and Sediment Control Monitoring
The control measures described above must be maintained in an effective operational condition during the
construction works. Regular inspections should be carried out by the contractor and any defects in erosion and
sediment control devices specified for the site are to be remedied as soon as practicable. Any damage to either
temporary or permanent water quality control structures is to be immediately rectified at the contractor’s expense.
The inspection of the ESC devices is to be carried out as follows:

               1. Routine Inspection – is to be carried out daily while work is being carried out on site, or weekly
                  while works are not being carried out.
               2. Preventative inspection – to be carried out a maximum of 24 hours before rain is forecast.
               3. Reactive inspection – to be carried out within 18 hours of a rainfall event sufficient to mobilise
                  surface sediment on the site.

Documentation of these defects is to be carried out, recording the date the defect was identified, a description of
the defect, the cause of the defect and measures that can be implemented to reduce the likelihood of the defect
occurring in the future. Once the device has been repaired, the date of repair and the solution implemented
should also be recorded in the documentation. A record of all inspections and maintenance carried out on the
erosion and sediment control devices is to be maintained on site all times during construction.




Project number 20230025                                                                                 Page 13 of 22
File 20230025_Gympie Tce Hotel SWMP, 2023-05-31 Revision 0



P +61 7 5211 1003                 A 75 Noosa Drive, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com
Log in to download the original file

20230025_Gympie Tce Hotel SWMP.pdf · 10.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.