Decision Notice - Approved by Delegation of Authority DBW20 0036 · DBW20/0036

of 1

Text shows just the words. Original shows the document exactly as it was published.

Officer: 	Michelle Tucker
Direct Telephone: 	(07) 5329 6489
Our Reference:	DBW20/0036
Your Reference:	2020-3321
23 November 2020
Tom Riley Constructions
C/- Project BA
PO Box 45
NOOSAVILLE  QLD  4566
[email protected]
Dear Sir/Madam
Decision Notice
Planning Act 2016
I refer to your application and advise that on 23 November 2020, Council decided to approve the application, subject to conditions.
Details of the decision are as follows:
application details
Application No:	DBW20/0036
Street address:	Road 224, Noosa North Shore Qld 4565
Real property description:	Lot 4 on RP75378
Planning Scheme:	Noosa Plan 2020 (31 July 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Building Works - Additions to Detached House (Biodiversity)
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.

Plan No.	Rev.	Plan/Document Name	Date
Sheet 7/13	RC2020E	Proposed Ground Floor	14/08/2020
Sheet 8/13	RC2020E	Proposed Upper Floor	14/08/2020
Sheet 9/13	RC2020E	Proposed Elevations	14/08/2020
Sheet 10/13	RC2020E	Proposed Elevations	14/08/2020
Certification must be submitted to Council from a Licensed Surveyor which certifies that the building does not exceed the maximum height requirement of this Decision Notice.
Currency Period
The Currency Period for this development approval lapses if the use has not happened by 20 November 2026, unless an application to extend the currency period is approved by Council.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Building Works. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Landscaping
A minimum of 20% of the site must be retained as soft landscaping.
Existing trees on the site must be retained, except where required to be removed to accommodate the approved dwelling. In this regard, the removal of vegetation must not extend beyond 10 metres of the building footprint.
Existing vegetation in the road reserve must be retained, unless written authorisation from Council is granted for the clearing.
Trees to be retained must be protected from clearing or construction activities by:
clearly marking vegetation to be retained with flagging tape
installing protective fencing around the drip line of the vegetation
restricting stockpiling, storage and vehicle parking to those areas which are already cleared
using low impact construction techniques around vegetation.
Flood Immunity, Drainage and Earthworks
The minimum floor levels of all habitable rooms must be the greater of the following:
the minimum specified floor level if in an area where minimum floor levels are available
500mm above the modelled flood level if in an area where flood modelling is available
500mm above the highest known flood level if in an area where flood modelling is not available.
All cut and fill must not exceed 2 metres in depth relative to natural ground level.
Fill material placed over services must not impose any additional surcharge loading on the service.
Excavation must not be carried out within 600mm of any utility infrastructure (to top, sides and base of services). A retaining wall must be provided to support the soil surrounding utility infrastructure where proximate to excavation activities.
Compaction with a vibrating roller must not be carried out within 600mm of any utility infrastructure.
referral agencies
Not applicable.
ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
COVID-19
This development approval has been issued during the COVID-19 applicable event declared under 275F of the Planning Act 2016.
The period for undertaking the approved development may be subject to a further extension of 6 months under section 275R of the Planning Act.
Infrastructure Charges
All developments and/or changes to existing developments may require payment of “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution” made pursuant to the planning legislation and regulations current at the time of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-development/development-tools-guidelines/infrastructure-charges
Sustainability
In line with Noosa Council’s Corporate Plan, Council seeks to encourage sustainable building design for residential and commercial development. Council encourages the use of sustainable building materials, energy efficient fittings, solar hot water, photovoltaic systems (including the use of inverter/charges), water saving devices and rainwater harvesting. For further information go to http://www.noosa.qld.gov.au/sustainable-homes
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Type of Development Permit Required	Subject of the required Development Permit
Development Permit for Building Works	All building work
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.
Yours faithfully

Tara Norley
Development Planner

Enc:	Appeal Rights
Approved Plans/Documents

	Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017

Chapter 6 Dispute resolution
Part 1 Appeal rights
229 Appeals to tribunal or P&E Court
(1)	Schedule 1 of the Planning Act 2016 states –
(a)	Matters that may be appealed to –
(i)	either a tribunal or the P&E Court; or
(ii)	only a tribunal; or
(iii)	only the P&E Court; and
(b)	The person-
(i)	who may appeal a matter (the appellant); and
(ii)	who is a respondent in an appeal of the matter; and
(iii)	who is a co-respondent in an appeal of the matter; and
(iv)	who may elect to be a co-respondent in an appeal of the matter.
(2)	An appellant may start an appeal within the appeal period.
(3)	The appeal period is –
(a)	for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or
(b)	for an appeal against a deemed refusal – at any time after the deemed refusal happens; or
(c)	for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or
(d)	for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or
(e)	for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or
(f)	for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person.
Note –
See the P&E Court Act for the court’s power to extend the appeal period.
(4)	Each respondent and co-respondent for an appeal may be heard in the appeal.
(5)	If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal.
(6)	To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about-
(a)	the adopted charge itself; or
(b)	for a decision about an offset or refund-
(i)	the establishment cost of trunk infrastructure identified in a LGIP; or
(ii)	the cost of infrastructure decided using the method included in the local government’s charges resolution.
230 Notice of appeal
(1)	An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that-
(a)	is in the approved form; and
(b)	succinctly states the grounds of the appeal.
(2)	The notice of appeal must be accompanied by the required fee.
(3)	The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to –
(a)	the respondent for the appeal; and
(b)	each co-respondent for the appeal; and
(c)	for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and
(d)	for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and
(e)	each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and
(f)	for an appeal to the P&E Court – the chief executive; and
(g)	for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate.
(4)	The service period is –
(a)	if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or
(b)	otherwise – 10 business days after the appeal is started.
(5)	A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6).
(6)	A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person.
231 Other appeals
(1)	Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable.
(2)	The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error.
(3)	A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter.
(4)	In this section –
decision includes-
(a)	conduct engaged in for the purpose of making a decision; and
(b)	other conduct that relates to the making of a decision; and
(c)	the making of a decision or failure to make a decision; and
(d)	a purported decision; and
(e)	a deemed refusal.
non-appealable, for a decision or matter, means the decision or matter-
(a)	is final and conclusive; and
(b)	may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and
(c)	is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground.
232 Rules of the P&E Court
(1)	A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal.
(2)	However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court

[word/footer1.xml]
Page 5 of 5

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 5

[Attachment: image3.png (image text)]
ee) NOOSA COUNCIL

Used in these records

About this file

File size
368 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Approved by Delegation of Authority DBW20 0036.docx · 368 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.