DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW25/0054)

Approved Plans

1.

Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.

Plan No. Rev. Plan/Document Name Date

4868 Sheet 2/14 A Site Plan Proposed prepared by Reitsma 19 May 2025
(Annotated by Council)

Currency Period

2.

The Currency Period for this development approval lapses if the development has not
substantially started by 3 July 2027, unless an application to extend the currency period is
approved by Council.

Site Specific Conditions

The driveway in the Landrail Street frontage must be setback a minimum of 6 metres from
the end of the existing kerb at the intersection of Landrail Street with Oriole Avenue.

The works must include kerb and channel in Landrail Street extending between the proposed
driveway and the existing kerb and channel at the intersection with Oriole Avenue.

A site control and/or compliance bond of $2000 is to be submitted to Council prior to the pre-
start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.

The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.

PRIOR TO COMMENCEMENT OF WORKS

10.

Engineering

All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.

A condition report including photographs of the frontages of the site to Landrail Street and
Oriole Avenue must be completed and submitted to Council at the prestart meeting / prior to
any works commencing.

Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.

Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:

a. Civil engineering works;
b. Erosion and sediment control works;
c. Other relevant parties

A Construction Management Plan must be submitted to Council at least 5 working days prior
to any works commencing. The Construction Management Plan must address the following:

a. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD)

Used in these records

About this file

File size
4.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Operational Works Delegated Report OPW25 0054.pdf · 4.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.