PR22001.IFurtherAdviceResponse.9Feb2023
has been retained mid way down the ramp to minimise the catchment that flows to the basement pump
(addressed as part of prior correspondence).
In support of the above changes DME Projects have revised the Engineering Package which forms
Attachment 2 to this response, with these amendments incorporated within the Architectural Plan
Package.
In accordance with discussions with Council’s engineer it is understood removing the mechanical solution
(flood barrier) to the basement’s immunity shall provide sufficient confidence to Council that the
basement is protected during a significant weather event.
I trust this information is sufficient for your purposes, however should you require any further details or
clarification, please do not hesitate to contact Ben Walsh by telephone on 0430 011 617.
Yours faithfully
Ben Walsh
Director | Principal Planner