Plan No. Rev. Plan Name – Prepared By Date
Sheet 1/18 B Cover Sheet – Bush & Beach Pty Ltd 2 July 2009
Sheet 2/18 B Site Plan– Bush & Beach Pty Ltd 2 July 2009
Sheet 3/18 B Floor Plan – Bush & Beach Pty Ltd 2 July 2009
Sheet 4/18 B Elevations 1 – Bush & Beach Pty Ltd 2 July 2009
Sheet 5/18 B Elevations 2 – Bush & Beach Pty Ltd 2 July 2009
Sheet 6/18 B Section 1 – Bush & Beach Pty Ltd 2 July 2009
Relevant Period
2. The Development Permit for a material change of use lapses if the use has not happened by
17 August 2013, unless an application to extend the currency is approved by Council.
Security Bond
3. Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for building works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
Building Height
4. The building height shall not exceed 8.0 metres and 2 storeys above the natural ground level
and finished ground level.
Landscaping
5. A minimum of 20% of the site shall be retained as soft landscaping.
6. Screening vegetation of 200mm pot size consisting of native, endemic species with a mature
height of not less than 5 metres shall be planted at a minimum of 1.5 metre centres to
northern boundary for the full length of the dwelling in accordance with Council’s PSP 3
Landscaping Plants & Guidelines.
Water Storage
7. On site water storage for a minimum of 45,000 litres shall be provided on site to service the
detached house.
Earthworks
8. Earthworks required on site shall be carried out in accordance with Council’s Planning
Scheme Policy PSP5 Engineering Design Standards, so as not to cause the additional
ponding of water on any adjoining lands or concentrate or direct overland flow on to an
adjoining property.
9. Sediment and erosion control measures must be in place prior to the demolition of the shed
and building work. If such measures are not in place or are not satisfactory, ‘on the spot’
fines may be issued. Such fines can be issued if sediments from the site are found to enter
or have the potential to enter Council’s stormwater system or natural waterways.
General
10. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
Page 2 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2009.00000951.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.