Minor Change Existing Approval 51992 213 03 (As Published)

of 5

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                Officer:            Andrew Gaffney
                                                                                Direct Telephone:   07 53296284
                                                                                Our Reference:      51992.213.03
                                                                                Your Reference:     Noosa Scouts

               27 November 2025


               Scouts Queensland
               C/- Across Town Planning
               11 Bareki St
               WURTULLA QLD 4575
               [email protected]



               Dear Sir/Madam,
                                            Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 23 October 2025, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              51992.213.03

                   Street address:              11 Eumundi Noosa Rd Noosaville Qld 4566

                   Real property description:   Lot 7 RP 224431

                   Planning Scheme:             Noosa Plan 2020 (26 September 2025)

               2.      DECISION DETAILS

               The following type of approval was issued on 12 July 1996
               •       Development Permit for Material Change of Use of Premises - Special Uses – Scouts
                       (dormitory, kitchen and dining room)
               In relation to the request to make a minor change to the existing approval, Council on 20 November
               2025, decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Amend conditions 20, 21, 22, 23 & 24.
               C.      Include additional conditions 25 and 26.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is 2 years starting from the day of this approval
               (51992.213.02).
               below.


               ABN 97.969.214.121                                                              PO Box 141
               noosa.qld.gov.au                                                         Tewantin QLD 4565
               [email protected]                                                         07 5329 6500
                                                                                                         Page 1 of 5
Document Set ID: 24343810
Version: 5, Version Date: 01/12/2025
Log in to download the original file

Minor Change Existing Approval 51992 213 03 (As Published).pdf · 150 KB (small file)

Full text of the other 4 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               To be read in conjunction with approval 3B-259/03536 TP, copy attached.
               PLANNING – Additional Conditions 13 October 2015
                      When Conditions must be Complied With
               15     Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
                      the use commencing, and then compliance maintained at all times while the use continues.
                      Approved Plans
               16     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                            Plan No.            Rev.   Plan/Document Name                             Date

                                                A      Site Plan, prepared by Noosa Sea Scouts        15/09/2018

                            Page 1 of 1                Plan Sheet, prepared by Shed Boss 11 Aug 2015
                                                       Sunshine Coast

               17     The shed must be setback a minimum of 4 metres from the northern boundary.
               18     The vegetation along the northern boundary adjacent to the shed must be retained. The
                      vegetation may be side trimmed. In this regard the vegetation to be retained must be
                      protected from construction activities by:
                      a.       clearly marking the vegetation with flagging tape
                      b.       installing protective fencing around the drip line of the vegetation
                      c.       fill or excavation must not impact on the health of the vegetation
                      d.       using low impact construction techniques around vegetation.
               19     No windows or doors are permitted on the left elevation.
                      Approved Plans – 20 November 2025
               20     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.       Rev.    Plan/Document Name                                     Date

                        -              -       Site Plan, prepared by Noosa Sea Scouts                9/10/2018
                                               Annotated by Council

                        -              -       Proposed Shade Shelter – Dimensions, Elevations 9/10/2018
                                               and 3-D Plans, Noosa Sea Scouts

                        A02            E2      Site Plan, prepared by Salt Air Modular                26/08/2025
                                               Annotated by Council

                        A03            E3      Floor Plan, prepared by Salt Air Modular               28/08/2025

                        A05            E2      Elevations (1), prepared by Salt Air Modular           26/08/2025

                        A06            E2      Elevations (2), prepared by Salt Air Modular           26/08/2025




                                                                                                         Page 2 of 5
Document Set ID: 24343810
Version: 5, Version Date: 01/12/2025

Page 3

                        A13            E2    Roof plan                                                   26/08/2025

               21     The shade shelter must be setback a minimum of 10 metres from the southern boundary and
                      45 metres from the eastern boundary of the site.
               22     The maximum height of the shade shelter and ablution block must not exceed 4.5 metres
                      above the finished ground level and the natural ground level.
               23     With regard to the construction of the shade shelter and ablution block, existing trees on the
                      site must be retained. Trees must be protected from construction activities by using low
                      impact construction techniques around vegetation.
               24     The ablution block must be connected to the onsite sewer connection in accordance with the
                      standards and requirements of Northern SEQ Distributer-Retailer Authority (Unitywater).
               Additional conditions - 20 November 2025
                      Flood Immunity
               25.    The approved ablution block building must be constructed to provide flood immunity against
                      the Defined Flood Event (1% AEP event).
                      Building Appearance
               26. External colours and finishes must be of muted environmental tones, with broad
                   expanses of a single colour not permitted. Walls must be broken up by varying tones
                   or design elements.


               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               1.     This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in
                      accordance with Council’s “Charges Resolution” made pursuant to the Sustainable Planning
                      Act 2009 and in conjunction with the State Planning Regulatory Provision (adopted charges).
                      Equitable Access and Facilities
               2.     The plans for the proposed building work have NOT been assessed for compliance with the
                      requirements of the National Construction Code - Building Code of Australia (Volume 1) as
                      they relate to people with disabilities. Your attention is also directed to the fact that in addition
                      to the requirements of the National Construction Code as they relate to people with
                      disabilities, one or more of the following may impact on the proposed building work:
                      a.      the Disability Discrimination Act 1992 (Commonwealth);
                      b.      the Anti-Discrimination Act 1991 (Queensland); and
                      c.      the Disability (Access to Premises – Buildings) Standards.
                      Infrastructure Charges
               3.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges




                                                                                                             Page 3 of 5
Document Set ID: 24343810
Version: 5, Version Date: 01/12/2025

Page 4

               7.        PROPERTY NOTES

               Not applicable.
               8.        VARIATION APPROVAL DETAILS

               Not applicable.
               9.        FURTHER DEVELOPMENT PERMITS REQUIRED

               •         Development Permit for Building Works
               10.       SUBMISSIONS

               Not applicable.
               11.       RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               12.       OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.




               Yours faithfully,

               Andrew Gaffney
               Senior Development Planner | Development Assessment
               Development & Regulation



               Enc:      Appeal Rights
                         Approved Plans/Documents



               DECISION NOTICE HISTORY
               •     Original Decision Notice – 12 July 1996.
               •     Decision Notice - Minor Change 51992.213.01 – 13 October 2015 – additional conditions 15, 16, 17, 18 and 19;
               •     Decision Notice – Minor Change 51992.213.02 – 23 October 2018, amend condition 16 and additional conditions 20, 21,22, 23 &
                     24.

               •     Decision Notice - Minor Change 51992.213.03 – 20 November 2025, with an amendment to conditions 20, 21, 22, 23 & 24 and
                     additional condition 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35 & 36.




                                                                                                                                    Page 4 of 5
Document Set ID: 24343810
Version: 5, Version Date: 01/12/2025

Page 5

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                    Page 5 of 5
Document Set ID: 24343810
Version: 5, Version Date: 01/12/2025

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.