INFRASTRUCTURE CHARGE CALCULATION DETAILS:
The infrastructure charge is calculated in accordance with Council’s Infrastructure Charges Resolution
incorporating the charge apportionment (break-up) agreement with Unitywater in compliance with the
Sustainable Planning Act 2009 and Statutory Regulatory Provision (adopted charges) applying at the
time of issuing the notice.

Council’s infrastructure charge levied is based on the following:

    Development              Unit of                               % Charge
                                               Charge Rate                             % Council                            $ Amount
       Class                Measure                               (Clause 13 (c)
                                                                                                             Qty
                                                (Table 13.1
                                                                   & Table 10.3
                                                                                     Apportionment                        (at 1 July 2014
      (Table 13.1          (Table 13.1                                                                                         Index)
                                               Columns 4 & 5)                           (Table 10.1)
       Column 2)          Columns 3 & 5)                            Note: (1))

 Approved Development Defined Use & Quantity: Industrial Business - Type 1 - Warehouse (Self Storage) = 3,770m2 gfa
                                   2
 Industry                   m gfa                   $50               100%                 60%              3,770             $130,065.00
                           2
 Non-Residential         m impervious
                                                    $10               100%                100%              3,601              $36,010.00
 Stormwater                  area
                                                                                   Gross Infrastructure Charge =              $166,075.00

 Discount (Credit) for Lawful Existing Defined Use & Quantity (Clause 8.4): Industry - 1 x Vacant Lot (REC12/0106)

 Industry                  Industry Lot            -$50           100%             69%             1                          -$19,320.00
                                                  Existing Lawful Use or Contribution Discount (Credit) =
                                                                                                                              -$19,320.00
                                          (Clause 8.4 - Limited to and not exceeding the Gross Infrastructure Charge)
                                                                   * NET INFRASTRUCTURE CHARGE =                          * $146,755.00

The infrastructure charge payable will be allocated to Council “Trunk” infrastructure networks in
accordance with Council’s Resolution as follows:
                                                                                                                    * Net Infrastructure
   Council “Trunk” Infrastructure Network                 Net Infrastructure                                          Charge Amount
                    (Table 10.2)                                Charge
                                                                                     Offset/Rebate/Other
                                                                                                                          Payable
                                                                                                                    (at 1 July 2014 Index)

 Transport                                                          $94,133.00                         -$0.00                  $94,133.00

 Public Parks & Land for Community Facilities                       $16,612.00                         -$0.00                  $16,612.00

 Stormwater                                                         $36,010.00                         -$0.00                  $36,010.00

   * Net Infrastructure Charge Payable =                        * $146,755.00                          -$0.00              * $146,755.00
* Subject to Automatic Increase Provision until date of payment.

Basis of Negotiated Infrastructure Charges Notice:

Representation dated 16 December 2014 considered the impervious area used to calculate the
infrastructure charge to be incorrect. Council review of the calculation agrees with the representation that
the impervious area is 3,601 m2 in accordance with the approved plan and not 4,140 m2 as originally
calculated and applied. Representation approved by Council on 17 December 2014.




                                       PO Box 141                     P. (07) 5329 6500       [email protected]
                                       TEWANTIN QLD 4565              F. (07) 5329 6501       www.noosa.qld.gov.au            ICN - Page 3

Used in these records

About this file

File size
312 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated ICN.N1040 (Rev1) - MCU14_0067 with Info Notice.pdf · 312 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.