001 ECM_21713731_v5_Negotiated Decision Notice OPW21 0134 · OPW21/0134.02

of 14

Text shows just the words. Original shows the document exactly as it was published.

                                                            Officer:            Laurie Schreck
                                                            Direct Telephone:   07 53296223
                                                            Our Reference:      OPW21/0134
                                                            Your Reference:     17623

               26 November 2021


               WAG INVESTMENTS
               C/- Tod Consulting Pty Ltd
               PO Box 61
               NOOSAVILLE QLD 4566
               [email protected]



               Dear Sir/Madam
                                              Negotiated Decision Notice
                                                      Planning Act 2016

               I refer to your application and the representations you made in respect to the decision notice. On
               2 December 2021, Council decided your representations. This negotiated decision notice replaces
               the decision notice of 27 October 2021.
               Details of the negotiated decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:           OPW21/0134

                   Street address:           135 Lake Weyba Dr Noosaville Qld 4566

                   Real property description: Lot 1 RP 36729

                   Planning Scheme:          Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council on 27 October 2021, decided to issue the following type of approval:
                      Development Permit for Operational Work - Road work, Drainage work, Landscaping,
                       Electrical Reticulation, Stormwater, Earthworks, Clearing Veg
               In relation to representations, Council on 2 December 2021 decided to:
               A. Amend condition 1
               B. Include additional 56
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.




                                             PO Box 141                  P. (07) 5329 6500       [email protected]
                                             TEWANTIN QLD 4565           F. (07) 5329 6501       www.noosa.qld.gov.au
                                                                                                              Page 1 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021
Full text of the other 13 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.              Rev.    Plan/Document Name                       Date

                         17623-C000            C       Locality Plan, Drawing Index and Notes 08 September
                                                       as prepared by Tod Consulting          2021

                         17623-C001            C       Plan of Development as prepared by Tod 08 September
                                                       Consulting                             2021

                         17623-C100            C       Earthworks, Erosion and Sediment 08 September
                                                       Control Plan as prepared by Tod 2021
                                                       Consulting as annotated by Council

                         17623-C200            C       Roadworks and Drainage        Plan   as 08 September
                                                       prepared by Tod Consulting              2021

                         17623-C201            C       Roadworks Details as prepared by Tod 08 September
                                                       Consulting                           2021

                         AC1212-S4400232 1 A           Electrical Reticulation as prepared by 27 July 2021
                         of 2                          Auspower Connect

                         AC1212-S4400232 1 A           Electrical Reticulation as prepared by 27 July 2021
                         of 2                          Auspower Connect

                         AC1212-         B             NBN Pit and Pipe Design Stage 1 4 New 21 July 2021
                         CAD_REF_AC1212T               Connections as prepared by Auspower
                                                       Connect

                         Report 19060          Final   Bushfire Management Plan as prepared 03 June 2021
                                                       by Land and Environment Consultants

                         LAK07                 B       Vegetation Management Plan as September
                                                       prepared by Urban Forest Concepts 2021

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 03 November 2023, unless an application to extend the currency
                      period is approved by Council.
               SITE SPECIFIC CONDITIONS
               3.     The Erosion and Sediment Control elements of Plan Number 17623-C100 have not been
                      approved. Erosion and Sediment Control Plans must be regularly revised and updated by a
                      suitably qualified person (CPESC or RPEQ with relevant experience) during development
                      works.
               4.     The existing crossover to the existing dwelling on proposed Lot 3 must be removed and the
                      verge area reinstated to match the existing verge treatments. Grassed verge areas to be
                      reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be
                      maintained by the developer until established.




                                                                                                  Page 2 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 3

               PRIOR TO COMMENCEMENT OF WORKS
                      Tree Clearing/Retention
               5.     The Tree Survey/Civil Works Overlay plan from Appendix 6 of the approved Vegetation
                      Management Plan must be amended and submitted to Council for approval prior to the
                      prestart meeting with the amendments to include:
                      a.      A colour coded legend included on the plan to be read in conjunction with the map; and
                      b.      Corresponding colour coding included on the Tree Schedule table in Appendix 4 of the
                              approved Vegetation Management Plan.
               6.     Tree/vegetation protection fencing must be installed under the supervision of the Project
                      Arborist in accordance with the Vegetation Management Plan as prepared by Urban Forest
                      Concepts.
                      Engineering
               7.     Prior to the pre-start meeting, all necessary approvals from external service providers (e.g.
                      Unitywater, Energex, NBN) and external parties on which the development works are
                      proposed have been obtained and a copy supplied to Council.
               8.     A condition report including photographs of the frontage of the site and the section of Lake
                      Weyba Dr where the reconstruction works will tie into must be completed and submitted to
                      Council prior to the prestart meeting.
               9.     The principal contractor must have all the appropriate insurance and public liability
                      documentation to carry out the works. The principal contractor is also responsible to ensure
                      that any subcontractors also have the appropriate insurance and public liability
                      documentation. Certificates demonstrating currency of public liability insurance and works
                      insurance covering the works must be submitted to Council prior to the prestart meeting.
               10.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Tree protection/clearing works;
                      c.      Electrical reticulation works;
                      d.      Erosion and sediment control works; and
                      e.      Other relevant parties.
               11.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;
                              ii.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased;
                              iii.     Any proposed fencing to the site during the construction phase of the
                                       development;
                              iv.      No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off.
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures;



                                                                                                          Page 3 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 4

                      c.      Works programme identifying key components of the works and their respective
                              durations;
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues;
                      e.      Include a post out to the local residents advising of the proposed development, the
                              expected time frames and the site contact details;
                      f.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details; and
                      g.      For haulage operations involving significant volumes of fill material or excavated
                              material being transported onto or off the site: details on the location of external fill
                              sites/sources, the haulage route, type of vehicle to be utilised during filling operations
                              and frequency of usage. NB any damage to the existing road system as a result of
                              haulage operations shall be fully repaired at the applicant’s expense.
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
                      Bonds
               14.    A site control and/or compliance bond of $50,000 is to be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               DURING CONSTRUCTION
                      Engineering
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Final Order No. 61 of 2018 for a
                              Reconfiguration of Lot viz. RAL21/0504 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Roadworks (External Roadworks & Road Widening Works)
               17.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.




                                                                                                         Page 4 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 5

               18.    All street surfacing must consist of a minimum depth of 30mm of an approved hot mixed
                      asphaltic concrete, unless other pavement types are approved as feature areas in
                      intersection thresholds, speed control devices, turning areas, indented parking etc.
               19.    The installation and/or modification of any traffic signs, street signs, line marking and Raised
                      Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
                      Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
                      installation system. All new signage must be Class 1 retroreflective material in accordance
                      with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
                      1: Retroreflective sheeting.
               20.    The developer must notify Council’s Traffic Engineer for any works involving the removal or
                      modification of existing Council traffic signs prior to such works commencing.
                      Pavement Design and Construction
               21.    The pavement design for the reconstruction of Lake Weyba Dr is not approved. To attain
                      approval for the pavement design, the following details must be submitted and certified by
                      an RPEQ with the proposed pavement design:
                      a.      The design CBR must be based on the four day soaked CBR value for the subgrade
                              material;
                      b.      The design subgrade CBR must be representative of each homogenous insitu section
                              of finished subgrade. With respect to each section:
                              i.       For four or less test results, the design CBR must be taken as the least estimated
                                       insitu CBR result.
                              ii.      For five or more test results, the design CBR must be taken as the 10th percentile
                                       of all estimated insitu CBR results.
                      c.      The samples must be taken generally in the position of the outer wheel path on both
                              sides of the proposed road. A sketch plan showing the location of all tests must be
                              submitted with the test results for pavement design approval; and
                      d.      Where imported material has been (or is proposed to be) used for subgrade
                              replacement, and the depth of the imported material is less than 300mm, the pavement
                              design CBR must be based on the testing results of the insitu material and not the
                              imported material.
               22.    At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
                      under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
                      until this requirement has been achieved.
               23.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               24.    Safe pedestrian access on all streets in the vicinity of the development must be maintained
                      at all times. Should footpath/road closures be necessary to carry out construction works,
                      Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               25.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               26.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.




                                                                                                           Page 5 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 6

                      Site Access and Driveways
               27.    The communal driveway crossover must be constructed in accordance with Council’s
                      Standard Drawing RS-056 & RS-056.1.
               28.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete;
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      c.      Underground service conduits for water supply, electricity and any other services must
                              be provided as part of the access driveway;
                      d.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               29.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
                      the Plan of Survey.
               30.    Fall protection must be provided to retaining walls that are over 1m high.
               31.    Any retaining walls within the bushfire protection zone shown in Figure 6.1 of the approved
                      Bushfire Management Plan, must be constructed with non-combustible or fire resisting
                      materials in accordance with the Bushfire Management Plan.
               32.    Slope and batters are a maximum grade of:
                      a.      1 in 4 for grassed areas;
                      b.      1 in 3 for planted areas; and
                      c.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               33.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               34.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g. by blocking or interfering with natural overland flows).
               35.    The fill works undertaken must not result in any ponding of stormwater within the proposed
                      lot or on adjacent lots. Any reshaping works required to prevent ponding must be effectively
                      stabilised with turf or equivalent stabilisation method.
               36.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               37.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.




                                                                                                        Page 6 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 7

               38.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;
                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               39.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the Supervising Engineer’s instructions and the current best practice
                      standards * (Refer to Advisory Note).
               40.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               41.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
               42.    Prior to the completion of the development and commencement of use, all site surfaces must
                      be effectively stabilised using methods which have achieved effective short-term stabilisation
                      and which will continue to achieve effective stabilisation in the medium to long-term. For the
                      purpose of this condition, an effectively stabilised surface is defined as one that does not, or
                      is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
                      lead to sedimentation, or lead to water contamination.
               43.    A log book for the Erosion and Sediment Control measures and inspections must be
                      maintained by the site manager and made readily available to Council when requested. The
                      Supervising Engineer must verify and endorsed the E&SC measures upon their installation,
                      and periodically check these measures and the log book during construction and the
                      stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
                      fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
                      whether the device should be replaced or repaired. Documentation is to include how the
                      damage was caused and what measures can be implemented to reduce the possibility of
                      repeat occurrences. Any damage to either permanent or temporary water quality control
                      structures or devices is to be immediately rectified at the contractor’s expense.
                      The effectiveness of the erosion and sediment control devices must be monitored. All ESC
                      measures are to be inspected:
                      a.      At least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      Within 24 hours of expected rain; or




                                                                                                         Page 7 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 8

                      c.      Within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
               Damage to Services and Assets
               44.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      Where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      Where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               Vegetation Clearing/Retention
               45.    A qualified person* must be engaged for the duration of the works to:
                      a.      Ensure works are carried out in accordance with the requirements of the approved
                              Vegetation Management Plan.
                      *(Refer to Advisory Note)
               46.    A QPWS recognised spotter-catcher must be engaged to manage fauna prior and during
                      clearing works in accordance with the requirements in the approved Vegetation Management
                      Plan and must:
                      a.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows;
                      b.      Ensure clearing works avoids nesting times of animals and birds;
                      c.      Co-ordinate staging and sequence of clearing with fauna protection;
                      d.      Protect and recover fauna during clearing operations (not previously removed); and
                      e.      Manage the translocation of animals and recovery procedures in accordance with
                              relevant legislation.
               Street Trees
               47.    Inclusion of 1 Callistemon viminalis (or similar species approved by Council) public amenity
                      tree* within the road reserve for every 8 metres of road frontage to Lake Weyba Drive. These
                      street trees are not to be included in replacement plantings as required by the Vegetation
                      Management Plan.
               48.    Public amenity trees* must:
                      a.      Meet Specifying Trees – a guide to assessment of tree quality (NATSPEC).
                      b.      Minimum 45L pot size.
                      c.      Meet landscaping requirements detailed within Noosa Plan 2020 – PSP2 Landscaping.
                      d.      Be located in accordance with engineering requirements for safe vehicle and
                              pedestrian sight lines.
                      e.      Be located on the roadside side of the power lines.
                      f.      Be located from services and infrastructure a minimum of:
                                       a. 6m from electricity poles and pillars.
                                       b. 4m from street lighting.
                                       c. 2m from stormwater catchment pits.
                                       d. 2m from any adjoining driveway.




                                                                                                         Page 8 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 9

                      g.      Ensure mulch is placed around each tree, comprising of leaf and limb material of
                              varying sizes, free of foreign matter including anthropogenic waste, rock, soil/sediment
                              contamination and is applied to all planting areas to ensure a minimum 100mm depth
                              once settled.
                      *(Refer to Advisory Note)
               Weed Management
               49.    Weed control and management works must be undertaken in accordance with the approved
                      Vegetation Management Plan including the ongoing management of Singapore Daisy.
               Bushfire Management
               50.    All works must be undertaken in accordance with the relevant requirements of the approved
                      Bushfire Management Plan.
               FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Certification
               51.    Upon completion of the work and prior to signing the plan of survey, the following
                      certifications must be provided to Council:
                      a.      A certificate issued by an RPEQ certifying that the works have been constructed in
                              accordance with the Operational Works permit and the requirements of the Bushfire
                              Management Plan.
                      b.      A certificate issued by the Project Arborist certifying that the works have been
                              undertaken in accordance with this approval and the requirements of the approved
                              Vegetation Management Plan.
                      As Constructed Plans and ADAC XML Files (Council)
               52.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.       Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                       conformance with applicable standards and specifications, along with the
                                       relevant descriptions of assets, services and structures and;
                              ii.      Licensed Surveyor in regard to the cadastral and locational information, levels
                                       and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.




                                                                                                        Page 9 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 10

                      e.      Landscaping, including all assets and improvements within parks, open space and road
                              reserves areas are to be shown on an accompanying separate landscape plan
                              (prepared in .dwg file format with accompanying hardcopy PDFs) and include a
                              complaint ADAC XML file. Details of the landscaping and all associated assets and
                              improvements may be included in the ADAC XML digital file prepared for associated
                              civil infrastructure, or alternatively, be provided as a separate ADAC XML digital file
                              containing landscape and asset information only.
                      f.      The building envelope data must be submitted in both hardcopy and digital format
                              (ADAC XML Digital File). ADAC - Asset Design As Constructed, is to be prepared in
                              accordance with industry standards and recorded in “MGA - UTM56 / GDA94”
                              projection.
                      On Maintenance
               53.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
                      Maintenance’, the supervising RPEQ must submit to Council:
                      a.      Certification that all works have been undertaken and completed in accordance with
                              the requirements of this Permit;
                      b.      As Constructed details in accordance with Council’s Planning Scheme Policy; and
                      c.      Maintenance and operational manuals for all proprietary or site specific devices.
                      Off Maintenance
               54.    Prior to requesting an Off Maintenance inspection the developer must provide a written
                      request for the Off Maintenance inspection.
               55.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      A Council inspection reveals works do not comply with approval requirements;
                      b.      Submitted certification falsely states works comply with approval requirements.
                      ADDITIONAL CONDITION – 2 December 2021
               56.    Prior to the prestart meeting, provide a written agreement between the Developer and the
                      property owner(s) of No. 133 Lake Weyba Dr in regard to the potential impacts to their
                      frontage and crossover resulting from the construction of the necessary electrical
                      infrastructure. The agreement must address the extent of the reinstatement works and a copy
                      of the co-signed agreement must be submitted to Council.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     As this driveway is a private structure, the owner bears full responsibly for the standard of its
                      construction, maintenance and any liabilities associated with its construction.
               2.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.




                                                                                                       Page 10 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 11

               3.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               4.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               5.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               6.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
               7.     A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                      until such time as the works are performing in accordance with the approved design unless
                      noted otherwise
                      Environmental Advisory Notes
               8.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               9.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control
               10.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               11.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                                      Appropriate for slopes and slope lengths; and
                                      Are consistent with best practice environmental management practices such as
                                       in the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability (i.e. until house construction has occurred on all lots),
                              Council Officers may take the following matters into consideration in determining
                              whether the site is capable of achieving medium to long-term stability:
                                      Evidence that the site has been effectively stabilised in the short term;
                                      Evidence that soil has been adequately ameliorated;
                                      Evidence that seed of annual and perennial grass species has been applied at
                                       an adequate rate; and




                                                                                                           Page 11 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 12

                                      That grass seed has germinated at a density that is likely to achieve an effective
                                       grass cover.
                      Vegetation Clearing/Retention
               12.    Qualified Person, for the purpose of:
                      a.      Undertaking, supervising tree works and preparing arboriculture certification, is
                              considered to be a person with a minimum three years current experience in tree
                              protection, hazard identification/mitigation and Specifying Trees – a guide to
                              assessment of tree quality (NATSPEC) assessment and either:
                              i.       International Society of Arboriculture (ISA) certification; or
                              ii.      A Diploma of Arboriculture.
                      b.      Managing Fauna protection is considered to be a certified Fauna Spotter Catcher
               13.    Public amenity trees are defined as any tree located within public streets, parks or areas that
                      will become publicly owned as a result of this development.
               7.     PROPERTY NOTES

               The following property notes will be placed against the subject properties as specified in Council’s
               property record system:
               Flood Emergency Management Plan
               “Lots 1, 2, 3 and 4 are all subject to a flooding hazard with a Flood Emergency Management Plan
               (FEMP), as prepared by Water Technology 27 February 2020, in place for the lots. All owners and
               occupiers of Lots 1-4, including successive landowners, are to be provided with a copy of the FEMP
               which is to be implemented by the Body Corporate and landowners/occupiers.”
               Bushfire Management Plan
               “There is a Bushfire Management Plan (BMP), as prepared by Land and Environmental
               Consultants 03 June 2021, in place that effects Lots 1, 2, 3 and 4. Prospective purchasers, property
               owners and occupiers are to be provided with a copy of the BMP and are to ensure the Bushfire
               Mitigation Plan detailed in the BMP is adhered to.”
               Vegetation Management Plan
               “For proposed lot 1, there is a requirement in the Vegetation Management Plan, that any boundary
               fencing to the premises must allow the passage of native fauna.”
               8.     VARIATION APPROVAL DETAILS

               Not applicable.
               9.     FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               10.    SUBMISSIONS

               Not applicable.
               11.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.




                                                                                                          Page 12 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 13

               12.      OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.


               Yours faithfully,




               Laurie Schreck
               Development Engineer

               Enc:     Appeal Rights
                        Approved Plans/Documents


               DECISION NOTICE HISTORY
                    Original Decision Notice – 27 November 2021.
                    Negotiated Decision Notice - 2 December 2021, with an
                     amendment to condition 1; include additional condition 56




                                                                                                     Page 13 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Page 14

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                                                                                              (2)       However, the P&E Court may hear and decide an appeal even
                   (b) succinctly states the grounds of the appeal.
                                                                                              if the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 14 of 14
Document Set ID: 21713731
Version: 5, Version Date: 06/12/2021

Used in these records

About this file

File size
220 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

001 ECM_21713731_v5_Negotiated Decision Notice OPW21 0134.pdf · 220 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.