2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                        Replacement Cost by Component Condition
   $1,800,000.00                                                                1    2   3    4     5


   $1,600,000.00

   $1,400,000.00

   $1,200,000.00

   $1,000,000.00

      $800,000.00

      $600,000.00

      $400,000.00

      $200,000.00

            $0.00
                         Sand Pumping Station (SPS)        Sea Water Supply Pump Station (SWSPS)



Figure 2: SRS Asset Condition by Replacement Costs

4.4        Operations
Operations for the SRS are those activities not specifically targeted towards upgrade, replacement,
maintenance or restoration. These day to day operational activities have no effect on the SRS facility
conditions but, are necessary to keep the assets appropriately utilised and operating.

Typical operational activities include:
•    utility costs, e.g. water, electric, gas and rates;
•    cleaning and consumables;
•    salaries, depreciation;
•    security surveillance and patrols;
•    asset management data collection and condition assessment.

Operations expenditure is not fully distinguished from maintenance expenditure in the Council
financial systems; however there are some entries on a line item basis that relate to operations costs
e.g. utility costs including electricity, gas, water, depreciation and income.

                    Actual             Actual         Actual      Budget         Forecast          Forecast
 Year               2014/15            2015/16        2016/17     2017/18        2018/19           2019/20
 Operating          $206,429           $287,132       $339,578    $577,472       $577,472          $577,472


Table 4: SRS Annual Operations Expenditures (actuals and proposed budget)

It is estimated that operational costs will rise in the future with increasing utility costs; particularly
electricity. Noosa Council will consider various sustainability and energy efficiency measures in
existing and upgraded facilities to minimise costs and environmental impact. This operational
strategy is considered in relation to Zero Emissions Noosa™ (ZEN) Organisational Strategy.



Asset Management Plan: Noosa Main Beach Sand Recycling System                                           Page 11
Log in to download the original file

2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan(PDF, 1MB).pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.