2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
3. Future Demand
3.1      Demand Drivers
There is currently an adhoc approach of demand management applied to the management of the
SRS through, the serviceability of the SRS, the agreed levy contributions, the contract management
of the contractor and the compliance with the permit conditions. Targets initiated to assist in
monitoring activities of the SRS should act as an indicator to reviewing demand management. It is
Council policy that any change in the level of service due to demand is reported to Council in
accordance with current guidelines and practices.

The major driver of capital upgrade for the SRS will be changes in legislative/statutory requirements,
compliance with WH&S policies, changes in technologies or changes to the contracted operational
activities. The recent Condition Audit Report 2 for this facility highlighted the need to improve on
preventative maintenance activities to preserve the current life of the assets.


3.2      Demand Impacts on Assets
The most significant impact on assets from demand relate to periods of scheduled closures for asset
repairs/refurbishment or maintenance works. These scheduled activities should ideally be
undertaken outside of the regular storm season, November to May, where beach erosion is most
prevalent.




2 CH2M Noosa Sand Recycling System – Asset Condition Assessment 8th December 2017


Asset Management Plan: Noosa Main Beach Sand Recycling System                                  Page 8
Log in to download the original file

2018-04-10 S&O Agenda - Attachment 1 to Item 6 - Sand Recycling System Asset Management Plan(PDF, 1MB).pdf · 1.1 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.