‘C4 Construction Hydraulic m

Building Service Engineers

 

Calculation of Stormwater Runoff and Detention Requirements for: PO Box 1176 Buddina 4575
Project: 5 BLUEFIN COURT

Ref: 1874 Date: 11/04/08

Calculate increase in peak flow due to extra impervious area

Predevelopment Case

 

Maximum event = Q100

time of Concentration = 5 mins
Intensity (1) = 326 mm/hr
Existing site area (A) = 606 sq.m

Calc coeff of runoff
From QUDM Table 5.04.2
for Q10 intensity

200.00 mm/hr

With fraction impervious = 0.00
Interpolating C10 = 0.70
From table §.04.3
frequency factor Q100 = 1.20
Therefore Coefficient of runoff for grassed site Q100 = 0.84
Peak runoff for predeveloped catchm = Coeff of R * Intensity * Area / 3600 L/sec
= 46 Us
Post Development Case
a) New Impervious Catchment Area = 340 sq.m
Coeff of Runoff = 4
Intensity as before = 326 mm/hr
Therefore peak Runoff = Coeff of R * Intensity * Area / 3600
= 31 Lis
b) New Pervious area = Total site Area - new impervious area
= 266 sq.m
Coeff of runoff as before 0.84

326.00 mm/hr
Coeff of R * Intensity * Area / 3600
20 L/s

Intensity as before
Therefore peak Runoff

Total Peak runoff post development case runoff pervious + runoff impervious

51 Lis

Difference in peak flow Runoff due to development

Peak runoff post dev - Peak runoff pre dev.
= 5 Lis
Therefore Required reduction in peak flow for Maximum event
difference in peak flow between developed and undeveloped areas : 5 Us

Used in these records

About this file

File size
2.7 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

08_0744 - Operational Works - Landscaping, Stormwater, Carparking, Access, Frontage Works, Stormwater Disposal, Sediment & Erosion Control [As Published].pdf · 2.7 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.