ORDINARY MEETING AGENDA 19 MAY 2022
3 3D HAZARD MAPPING TOOL – APPOINTMENT OF SIMTABLE™
That Council note the report by the Disaster Management Officer to the Services and
Organisation Committee Meeting dated 10 May 2022 and agree to enter into a medium sized*
contractual arrangement with Simtable™ for the provision of a 3D hazard simulation tool for a
trial period of two (2) years, in accordance with section 235 (a) of the Local Government
Regulation 2012. At the end of the 2 year trial, officers will assess the merits of the 3D Hazard
Mapping Tool in supporting disaster management activities and whether to continue using it
long term. Funding of ongoing costs will then be considered through future budget processes
to determine whether general revenue, grants or other funding is applied.
*medium sized contractual arrangements are valued between $15,000 and $200,000, exc. GST
4 NOOSA DRIVE PATHWAY PROJECT REFERENCE GROUP - APPOINTMENT OF
COUNCILLORS TO REFERENCE GROUP
That Council note the report by the Infrastructure Planning, Design and Delivery Manager to
the General Committee Meeting dated 16 May 2022 regarding the establishment of the Noosa
Drive Pathway Project Reference Group and appoint Councillor Wilkie as Chair and Councillor
Lorentson as a member of the Group.
5 2122Q125 – CONTRACT FOR PROJECT MANAGMENT SERVICES FOR 2022 FLOOD
RECOVERY AND RECONSTRUCTION
That Council note the report by the Disaster Reconstruction Coordinator to the General
Committee Meeting dated 16 May 2022 and award Contract number 2122Q125 to Erscon
Engineering Consultants (Erscon), under Section 234 – Exception for LGA arrangement, of
the Local Government Regulation 2012, to provide Project Management Services to lead the
Disaster Recovery Funding Arrangements (DRFA) activities as per the guidelines outlined by
the Queensland Reconstruction Authority (QRA), for a term of 27 Months to the (maximum)
value of $2,100,000.00 GST exclusive as follows:
A. $2,000,000 for Project Management services that will exist until the DRFA acquittal date
of September 30, 2024. These costs will be recoverable under the guidelines of the
DRFA so Council will not have to fund this cost; and
B. $100,000 for submission administration that will exist until the DRFA acquittal date of
September 30, 2024. These costs are not recoverable under the guidelines of the DRFA
and will need funding by Council. It is proposed that the Disaster Management Reserve
restricted cash be used to fund this activity.
6 MCU21/0151 – APPLICATION FOR MATERIAL CHANGE OF USE –
TELECOMMUNICATIONS FACILITY SITUATED AT 25 RAILWAY PDE, POMONA
In accordance with Chapter 5B of the Local Government Act 2009, Cr Finzel provided the following
declaration to the meeting of a declarable conflict of interest in this matter:
I, Cr Wegener, inform the meeting that I have a declarable conflict of interest in this matter as I have an
NBN tower located on my property and receive income from NBN via a lease arrangement. It could be
viewed that I have an interest in mobile phone networks and NBN towers however as the application is
by Telstra and it does not indicate NBN or Optus infrastructure I do not believe a reasonable person
could believe I have a perception of bias. Therefore, I will choose to remain in the meeting room.
However, I will respect the decision of the meeting on whether I can remain and participate in the
decision.
Page 11 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.