Original source · versioned page text
FURTHER REPORT - Planning & Environment Committee 6 May 2025 MCU21/0110
PLANNING & ENVIRONMENT COMMITTEE MEETING 6 MAY 2025 7.2 FURTHER REPORT - MCU21/0110 - APPLICATION FOR MATERIAL CHANGE OF USE - RESORT COMPLEX AND ANICILLARY BAR, FOOD AND DRINK OUTLET, OUTDOOR SPORT AND RECREATION, AND CLUB (MINOR EXTENSION TO EXISTING CLUBHOUSE) AT 61 NOOSA SPRINGS DRIVE, NOOSA HEADS Author Development Assessment Manager, Patrick Murphy Development & Regulation Department Index ECM/Applications/MCU21/0110 Attachments 1. ATTACHMENT 1 - MCU21/0110 - PROPOSED CONDITIONS 2. ATTACHMENT 2 - MCU21/0110 - DEVELOPMENT ASSESSMENT MANAGER'S REPORT 3. ATTACHMENT 3 - MCU21/0110 - OFFICER'S REPORT 11 July 2023 4. ATTACHMENT 4 - MCU21/0110 - OFFICER REPORT 7 November 2023 5. ATTACHMENT 5 - MCU21/0110 - OFFICER REPORT 11 June 2024 6. ATTACHMENT 6 - MCU21/0110 - APPLICANT SUBMISSION 13 October 2023 7. ATTACHMENT 7 - MCU21/0110 - PROPOSAL PLANS 8. ATTACHMENT 8 - MCU21/0110 - POOL SIZE COMPARISON EXECUTIVE SUMMARY A report for this application was first presented to Council at the Planning and Environment Committee on 11 July 2023, at that time the application sought to develop a 106-room hotel on land within Noosa Springs. The report addressed a range of issues including the sites split zoning, the potential odour impacts of the nearby sewage treatment plant, bushfire risk, ecology, carparking and built form. The officer’s recommendation was to approve the application on the basis that the odour impacts had been satisfactorily addressed and matters relating to bushfire, ecology, carparking and built form had been suitably addressed. The matter was referred to the General Committee Meeting dated 17 July 2023 at which time a motion was put forward to refuse the application. The motion was successful, and the application was recommended for refusal. On 19 July 2023 the applicant stopped the decision-making period until 29 September 2023. As this was done prior to the Ordinary Meeting of 20 July 2023 Council was not able to finalise a decision on the application. The decision-making period recommenced on 29 September 2023. A Further Report was prepared for the Planning and Environment Committee meeting on 7 November 2023, due to the significance of the matter was referred to the General Meeting of 13 November 2023. At that time the applicant had not amended the layout of the proposed development however had provided several written submissions which included an analysis of the submissions made during the notification period, a letter from a solicitor reviewing the proposed grounds of refusal, and a further letter from the applicant’s planning consultant seeking to justify grounds to support the development. The grounds of refusal proposed at the General Committee on July 17, 2023, were reviewed by a planning solicitor. Accordingly, the updated grounds of refusal were included in the report.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of pages 2 to 80 (of 245)
Page 2
PLANNING & ENVIRONMENT COMMITTEE MEETING 6 MAY 2025
On 13 November 2023 the applicant made an Other Change to the application to include an
extension to the existing clubhouse. The change was an Other Change as it introduced a new land
use into the application. This meant that the application reverted to the Confirmation Notice stage
and no decision was able to be made on the application at the 13 November 2023 General
Committee Meeting.
The change application formalised the changes to the clubhouse that were referred to in the original
report, and included the following:
• Minor alterations to the internal configurations of the bar, kitchen, cold room and store
area (red dotted outline); and
• New liquor cool room, new dry store, new security & procurement office, new wet and
dry waste areas and new enclosed storage area (shown as yellow shading).
A report considering the proposal including the Other Change was prepared for consideration at the
Planning and Environment Committee dated 11 June 2024. At this meeting the matter was referred
to the General Committee Meeting of 17 June 2024. At the General Committee meeting it was agreed
to defer the matter to a future meeting round as the applicant requested to extend the decision-
making period so it could enter into meaningful discussions about changes that might be made to
the proposed Resort Hotel, that are reasonable, to address any valid planning concerns Councillors
might have about the development.
On 27 February 2025, the applicant made a minor change to the existing application reducing the
proposal from a 106 bedroom resort to a 69 bedroom resort. in a letter supporting the amended
application the applicant advises:
The request for a minor change stems from concerns raised by councillors about the scale of
the development, which unavoidably, extends into the Recreation and Open Space Zone and
partly into the Biodiversity, Waterways and Wetlands Overlay (Biodiversity Overlay) towards
the east of the site. This is despite the development not having a significant impact on any
environmental values as confirmed by Dr Watson and Council’s environmental officer. Other
concerns were raised about the scale and extent of the pools within the centre of the site and
the continued operation of the tennis courts, including during construction.
The changes being made to the development are detailed below:
• Pavilion 5 has been removed from the top of the site towards the east with the stair and
lift area reconfigured for Pavilion 4.
• Pavilion 1, Level 1 presidential suite changed to two (2) deluxe rooms with a reduction
in the terrace areas at ground level.
• The character and privacy of the central recreation zone has been strengthened by
increasing the planted landscape spaces, with the swimming pools reduced in size and
enhanced by being integrated into a natural landscape setting.
• A minor increase in the size of the amenities building will provide for wellness facilities
that complement the recreation zone.
• A change to the overall design of the open space areas, with pathways and small deck
areas added to make some passive use of the open space area towards the east where
Pavilion 5 was located while maintaining the existing vegetation.
• An increase in the size of the southeastern tennis court to a ITF (pro-tour size) tennis
court; and
• A reduction in the height of the structures above the decked carpark to the south with
the solar panels to be maintained.
The minor change plans form the basis of the current assessment. Noting earlier officer
recommendations regarding previous versions of the development and noting the reduced footprint
Page 3
PLANNING & ENVIRONMENT COMMITTEE MEETING 6 MAY 2025 associated with the current minor change the application is supported subject to reasonable and relevant conditions. RECOMMENDATION That Council note the Further Report by the Manager Development Assessment to the Planning and Environment Committee Meeting dated 6 May 2025 regarding Application No. MCU21/0110 for a Development Permit for a Material Change of Use – Resort Complex and ancillary Bar, Food and Drink Outlet, Outdoor Sport and Recreation and Club (minor extension to existing clubhouse) at 61 Noosa Springs Drive, Noosa Heads and: A. Approve the application subject to conditions in accordance with Attachment 1. REPORT Link to Corporate Plan Not applicable. Previous Council Consideration Finance Risk & Opportunities Human Rights . Consultation External Consultation - Community & Stakeholder Internal Consultation
Page 4
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
ATTACHMENT 1 – (MCU21/0110) – PROPOSED CONDITIONS
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the
use continues.
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA 1.00 19 Site Plan, prepared by Marchese Partners 06.02.2025
DA 1.01 15 Entry Link Level Plan, prepared by Marchese 06.02.2025
Partners
DA 1.02 18 Basement Plan, prepared by Marchese Partners 06.02.2025
DA 1.03 16 Lower Ground Floor Plan, prepared by Marchese 06.02.2025
Partners
DA 1.04 16 Ground Level Plan, prepared by Marchese 06.02.2025
Partners
DA 1.05 16 Level 1 Plan, prepared by Marchese Partners 06.02.2025
DA 1.06 16 Level 2 Plan, prepared by Marchese Partners 06.02.2025
DA 1.07 16 Level 3 Plan, prepared by Marchese Partners 06.02.2025
DA 1.08 16 Roof Plan, prepared by Marchese Partners 06.02.2025
DA 1.10 9 Existing Clubhouse Plan, prepared by Marchese 06.02.2025
Partners
DA 1.11 9 Proposed Clubhouse Plan, prepared by 06.02.2025
Marchese Partners
DA 1.12 5 Carpark Plans, prepared by Marchese Partners 06.02.2025
DA 2.01 16 South and West Elevation, prepared by 06.02.2025
Marchese Partners
DA 2.02 16 Noth and East Elevation, prepared by Marchese 06.02.2025
Partners
DA 2.03 6 Carpark Elevations and Section, prepared by 06.02.2025
Marchese Partners
DA 2.04 10 Tennis Courts, prepared by Marchese Partners 06.02.2025
Page 1 of 12
Page 5
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
DA 3.01 16 Building Sections, prepared by Marchese 06.02.2025
Partners
DA 3.02 14 Part 1 Sections, prepared by Marchese Partners 06.02.2025
DA 3.03 15 Part 2 Sections, prepared by Marchese Partners 06.02.2025
DA 4.01 12 Extrapolated 8m & 12m above NGL plane, 06.02.2025
prepared by Marchese Partners
DA 4.05 12 3D View – Building Entry, prepared by Marchese 06.02.2025
Partners
DA 4.06 11 3D View – Pool View 1, prepared by Marchese 06.02.2025
Partners
DA 4.07 11 3D View – Pool View 2, prepared by Marchese 06.02.2025
Partners
DA 4.08 11 3D View – Looking North from Resort Drive, 06.02.2025
prepared by Marchese Partners
LCP2 – M Landscape Concept Design Package prepared 21.02.2025
LCP18 by Place Design Group
N/A 1 Terrestrial Ecology Assessment prepared by
Gondwana Ecology dated 26.02.2020 and as
amended by letter from Gondwana Ecology
dated 9 February 2023
N/A 8 Bushfire Hazard Assessment and Mitigation Plan 25.02.2025
prepared by Rob Friend & Associates
Nature and Extent of Approved Use
3. The approved resort units must be used for short term visitors only. The approved units
must not be occupied by persons for the purpose of permanent accommodation,
excluding those persons in a manager's residence for the premises. The requirements
of this condition must be included in the Community Management Statement for any
body corporate for the subject site.
4. The approved uses and associated activities must not result in environmental
nuisances such as noise, visual or odour impacts that unreasonably diminish the
amenity of the area or surrounding uses.
5. Service vehicle movements associated with non-residential uses on the premises
(including loading and unloading) must not occur outside the hours of 7am to 6pm
Monday to Saturday and not at all on Sundays or public holidays. The requirements of
this condition must be included in the Community Management Statement for any body
corporate for the subject site.
6. Conferences and Functions must only occur within the existing Noosa Springs Golf
and Spa Resort.
Page 2 of 12
Page 6
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Currency Period
7. This development approval lapses if the use has not happened by 15 May 2031 unless
an application to extend the currency period is approved by Council.
Ventilation
8. All internal use areas of the accommodation use including hotel suites, common areas,
office, dining, bar and lobby areas shall be fully air-conditioned, allowing external
façade elements (doors and windows) to be closed if required. Fresh air makeup to the
air conditioning systems must be drawn from roof level locations located as far as
practical from the Noosa Wastewater Treatment Plant.
9. Activated carbon filtration must be installed on all fresh air makeup locations of the air
conditioning systems and must be regularly maintained to manufacturer specifications.
Outdoor Use Areas – swimming pools and tennis courts
10. Use by guests and visitors of the tennis courts, is limited to the following time periods:
i. 7am to 6pm: Four courts
ii. 6pm to 9pm: Two courts only
iii. 9pm to 6am: No usage of tennis courts
11. Use by guests and visitors of the swimming pools is limited to the time period 6am to
12am only.
Acoustic
12. An updated acoustic report must be submitted to Council prior to the issue of an
Operational Works approval. The amended acoustic report must include
recommendations to address the impact on residential amenity attributed to vacuum
truck operations on the site and provide acoustic mitigation measures to achieve
compliance with the noise criteria proposed in Section 6.2.4.1 of the Trinity Noise
Impact Assessment Report dated 20 February 2025. The recommendations of the
acoustic report must be implemented prior to the commencement of the approved
uses.
Noise Limits
13. Noise generated by the development must not exceed the following criteria at any off-
site noise sensitive receptor:
Period Background Noise Level Overall Noise Limits Design Component
L90 dBA Leq,adj,T dBA Noise Limits Leq,adj,T
dBA
Day 36 41 39
(7am to 6pm)
Evening 31 36 34
(6pm to 10pm)
Night 28 31 28
(10pm to 7am)
Page 3 of 12
Page 7
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Odour
14. The operator must prepare and maintain an Odour Complaint Management Plan, with
the plan including the internal management of any complaints from hotel guests. The
Odour Management Plan must be submitted to Council for approval prior to the issue
of an Operational Works approval.
Built Form and Development Appearance
15. The maximum height of the development must be in accordance with the approved
plans.
16. Certification must be submitted to Council from a Licensed Surveyor which certifies
that the buildings do not exceed the maximum height requirement of this Decision
Notice.
17. All air conditioning units or other mechanical equipment must be fully enclosed or
screened such that they are not visible from the street frontages nor adjoining
properties.
18. All deck and balcony areas above ground floor must not be enclosed by permanent
fixtures such as shutters, louvres, glass panelling or the like.
19. The development must incorporate the colour scheme and proposed mix of building
materials as outlined in the approved plans.
20. Any security screens on the premises consist of grille or translucent screens and not
solid shutters, screens or roller-doors.
21. All mechanical equipment and other service infrastructure located on the site must be:
a. located not less than 2 metres from a property boundary;
b. fully enclosed or screened such that they are not visible from the street frontages
nor adjoining properties. Where screened by landscaping, landscaping beds must
be at least 1.5 metres wide.
22. No part of the site may be used for outdoor storage of materials.
Performance Bond
23. Security in the form of a cash bond or trading bank guarantee to the sum of $200,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond
or guaranteed sum to effect compliance with conditions.
Tennis Court Fencing
24. Tennis court fencing must be comprised of black powder coated posts and rails with
black PVC coated chain wire mesh, or the like.
Tennis Court Light Spillage and Glare
25. Lighting must be directed onto the site and away from neighbouring properties.
26. The level of light emanating outside the property must not exceed an illumination level
of 12 lux nor an average of 10 lux when measured 3 metres outside the property
boundary.
27. The light fittings must be baffled to ensure that a light source is not directly visible from
the habitable room window of an adjoining property.
28. All light readings are to be taken in a horizontal plane at a height of 1000mm above
ground level.
Page 4 of 12
Page 8
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Tennis Court Operating Hours
29. Tennis courts must not be illuminated after 10.00p.m. nor before 7.30 a.m.
Structural Stability
30. All lighting support columns must be manufactured from galvanised steel.
31. The pole height shall not exceed 8 metres.
32. The pole and associated concrete footing design must be engineer certified to support
the light fitting and to withstand wind loads appropriate to the terrain classification.
Tennis Ball Machines
33. Machines which operate on the air compression principle must not be used after 7.00
p.m. nor before 8.00 a.m.
34. Silent running machines which operate at a noise level not exceeding 10 decibels
(when measured at the property boundary) must not be used after 10.00 p.m. nor
before 7.30 a.m.
Public Safety
35. During operating hours, all parking areas, pedestrian areas and entrances/exits to all
stairwells, lifts, foyers and public toilets must be well lit with vandal resistant lighting
and with intensities to satisfy the requirements of Australian Standard AS1158 “Public
Lighting Code”. Lighting must be designed to reduce the contrast between shadows
and well lit areas. In particular, appropriate security lighting must be provided in the
location of the bicycle/ scooter parking and bin storage area.
36. After hours access to loading docks, storage areas and the basement carpark
(including the vehicle ramp and all stairwells) must be restricted by a security gate,
lockable doors and/or other suitably appropriate means. The basement carpark must
be kept closed and locked at all times while the use is not operating.
Community Management Statement
37. Any proposed Community Management Statement required for the development
pursuant to the Body Corporate and Community Management Act 1997 must be
submitted to Council for endorsement at the same time as submission of the Building
Format Plan (or similar) to Council for compliance assessment.
38. All clauses and by-laws of the proposed Community Management Statement must
accord with the requirements of this Decision Notice.
Water & Sewer Connections
39. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
40. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to the development site.
ENGINEERING/TRAFFIC
Site Access and Driveways
41. A sealed access driveway must be provided from the internal service road to all parking
and manoeuvring areas of the development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawing RS-051 and
respective addendum; and
Page 5 of 12
Page 9
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
b. suitable safety measures, including warning signage, to improve driver awareness
of pedestrians and enhance pedestrian safety. Warning signage must be provided
near the exit ramp from the underground parking area to warn motorists of
pedestrian movement along the frontage street.
Car Parking
42. Car parking must be provided in accordance with the approved plans and as amended
by the conditions of this approval. The works must be undertaken in accordance with
an Operational Works approval.
43. The parking layout is to be in accordance with the requirements of AS/NZS 2890.1-
2004
44. Provision of vandal resistant public lighting with intensities to satisfy the requirements
of Australian Standard AS1158: Public Lighting Code.
45. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
46. Directional signage must be provided to direct visitors and customers to the car parking
spaces provided on site.
Security Access to Carpark
47. Where access to the carpark is proposed to be restricted by a security gate, provision
must be made for queuing of vehicles clear of the roadway while waiting for the security
gate to open.
48. Where a secure carpark services a commercial use on the site, the security gate must
remain open at all times while commercial uses on the site are open for business. The
requirements of this condition must be included in the Community Management
Statement for anybody corporate for the subject site.
Service Vehicles
49. Service vehicle parking, manoeuvring and standing spaces must be provided on the
site. The works must be undertaken in accordance with an Operational Works
approval.
Pedestrian and Bicycle Facilities
50. Pedestrian and bicycle facilities must be provided for the development. The works must
include in particular:
a. signage and lighting at strategic locations to direct people to building entries and
public toilet facilities;
b. a total of 53 bicycle parking spaces; and
c. end of trip facilities involving 27 lockers, 6 showers and change rooms within the
development.
Water quality and quantity
51. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and the Queensland Urban Drainage Manual.
52. A stormwater quality treatment system must be provided for the development. The
works must be undertaken in accordance with an Operational Works approval and the
Bioretention Technical Design Guidelines (Water by Design, 2012), and must include
in particular:
Page 6 of 12
Page 10
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
a. stormwater quality treatment devices of a size and location generally in accordance
with those shown in Drawing No. C6070/20/P07 prepared by Walsh Consulting
Engineers dated 26/10/2021, with the exception of the following:
i. Bioretention filter area is to be increased in size to the area stated for
bioretention surface area on the above referenced plan
b. bioretention devices which:
i. are designed generally in accordance with IPWEQA Standard Drawing No.s
DS-073, DS-075 and DS-076
ii. are provided with a free-draining outlet from the sub-soil drainage system
53. Permanent educational signage* must be erected to educate the residents of /
customers to the development about the function of the bioretention device(s). The
dimensions, standard, presentation and location of the educational signage must be in
accordance with an Operational Works approval.
54. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The
approved Operational Works drawings for the stormwater quality treatment system and
detailed life cycle costing of the system must be attached as an addendum to this
document. Records of all maintenance activities undertaken must be kept and made
available to Council upon request.
55. Operating roof water harvesting tanks must be provided for the development. The tanks
must be provided in accordance with an Operational Works approval and must include
in particular:
a. a total tank capacity of 135,000 litres
b. a catchment of not less than 2,800m2 of the building roof area
c. re-use of harvested stormwater for non-potable outdoor uses including irrigation of
landscaped areas and swimming pool top-up.
56. Certification must be submitted to Council from a qualified person which certifies that
the stormwater harvesting tanks and associated reticulation has been installed in
accordance with the requirements of this Decision Notice.
Acid Sulfate Soils
57. An Acid Sulfate Soil Management Plan must be prepared and submitted with the
Operational Works application for the site. The acid sulfate management plan must
include testing, monitoring and treatment requirements for the works.
Services
58. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
59. Certification must be submitted to Council from all relevant service providers (Energex,
NBN and Unitywater which certifies that the development has met the requirements of
this Decision Notice and all applicable legislation at the time of construction.
Easements
60. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
Page 7 of 12
Page 11
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
61. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard
easement terms. Draft easement documentation must be submitted to Council for
endorsement.
62. All works must be kept clear of any existing or proposed easements on the subject
land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
63. All excavation, fill, soil retaining structures and associated batters must be undertaken
in accordance with an Operational Works approval and contained entirely within the
subject site unless written permission from the respective landowner(s) is provided to
Council.
64. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All
retaining walls that are publicly accessible and exceed 1.0m in height must be fitted
with a commercial grade safety fence.
Damage to Services and Assets
65. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
LANDSCAPING
Landscaping Works
66. The development site must be landscaped in accordance with a Council endorsed
landscape package prepared by a qualified person*. The works must be undertaken in
accordance with an Operational Works approval and the Noosa Plan for that specific
area and must include in particular:
a. the works shown on the Approved Landscape Concept Design Package Plans, with
the inclusion of the requirements of the approved Bushfire Hazard Assessment and
Mitigation Plan version 8, prepared by Rob Friend and Associates dated
25.02.2025.
b. Plant Pallet including hard and soft plant percentages, plant numbers, planting
locations, pot sizes and whether Noosa Native, Australian Native or Exotic;
c. a Landscape Management Plan including (but not limited to):
i. landscape design principles for bushfire hazard areas in Part 5 of Bushfire
Resilient Building Guidance for Queensland Homes (QRA 2020);
ii. Certification from a qualified* person ensuring the Landscape Management
Plan complies with the design principles in the Part 5 of Bushfire Resilient
Building Guidance for Queensland Homes (QRA 2020) and the Bushfire
Management Plan.
iii. Management of branches overhanging building envelopes.
Page 8 of 12
Page 12
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
d. clear integration of the Bushfire requirements and recommendations identified
within the approved Bushfire Hazard Assessment Report & Mitigation Plan version
8 dated 25.02.2025, including landscaping treatments where maximum distances
are permitted including:
i. a band of vegetation up to 20m wide along Resort Drive is to contain 100%
less flammable plant species;
ii. the remaining area greater than 20m from Resort Drive can contain no less
than 50% less flammable plant species in the understory and groundcover;
and
iii. regular maintenance of groundcover and understorey to reduce flammability
within the landscaped area.
e. clear integration of the landscaping recommendations, for the purpose of odour
mitigation, identified in the Katestone report dated December 2020.
f. A vegetated buffer of a height that avoids line of sight contact with the Sewage
Treatment Plant from any place or structure on the development site to Council’s
satisfaction.
g. Both sides of Resort Drive Road Reserve between the intersections of Links Drive
and Lakeview Rise must be rehabilitated and revegetated in accordance with the
landscaping recommendations of the approved Bushfire Hazard Assessment and
Mitigation Plan version 8, prepared by Rob Friend and Associates dated
25.02.2025.
h. The works must be undertaken in accordance with an Operational Works approval.
i. Details of water quality treatment device plantings with a minimum of five plant
species and a plant density of 8 plants per square metre;
j. Details of all fencing and gates (including but not limited to height, construction
type, materials);
k. Details of tree protection methods provided by a qualified person* to be engaged
to protect trees identified within the conditions of this approval in particular
vegetation located within the mapped Koala Habitat Area to the north of the
development site.
l. Native trees of a minimum pot size of 100L to replace existing trees to be removed
from the site, at the rate of 1 replacement tree for every tree removed that has a
diameter greater than 200mm measured at 1.2 metres from ground surface level.
m. Vegetated screening of any electrical transformers, bin storage areas and the like
from the road frontage.
n. Vegetation offsets in accordance with the recommendations Gondwana Ecology
letter dated 9 February 2023.
67. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
68. Control of all weeds species listed in the following standards and legislation:
a. Declared plants under the Land Protection (Biodiversity Act 2014 and subordinate
Regulation 2016).
b. Noosa Local Government Area Pest Management Plan 2015-2019.
c. Undesirable Species as listed in Planning Scheme Policy 3 Landscaping Plants
and Guidelines.
Page 9 of 12
Page 13
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
69. All entry statements, fences, retaining walls and buffer/screen plantings must be
located entirely within private land and not within the public road reserve.
Treatment of Temporarily Vacant Land
70. Where some or all of the land remains vacant or undeveloped for more than 3 months,
or buildings are demolished and redevelopment is delayed for more than 3 months, the
following works must to be carried out:
a. the site must be cleared of all rubble, debris and demolition materials
b. the site must be graded to prevent ponding (to the same level as the adjoining
footpath wherever practicable), turfed and mown at a minimum 3 weekly intervals
c. the site must be landscaped with perimeter planting consisting of advanced
specimens of fast growing tree species
d. the site must be maintained to ensure no nuisance to adjacent premises, roads or
footpaths
e. where fencing is installed to secure boundaries:
i. the fencing must be durable and not capable of being pushed or blown over
ii. the fencing type must not detract from local amenity (barbed wire is not
acceptable)
iii. vandalism must be promptly repaired and any graffiti removed.
Retention of Existing Trees
71. Existing trees on the development site and in the road reserve must be retained in
accordance with an Arborist Report (or part thereof) prepared by a qualified person*
and endorsed through an Operational Works approval. The Arborist Report must
include:
a. Tree removal/retention plan that includes all native trees and identifies in particular
all native trees to be removed with a diameter greater than 100mm measured at
1.2m from ground surface level.
b. Vegetation identified as not approved for removal within ‘Attachment E - Tree
Removal Plan’ within the approved Terrestrial Ecological Assessment report, and
as amended by the letter, attached plans and tree survey prepared by Gondwana
Ecology dated 9 February 2023, must be protected.
c. Incorporate vegetation to be retained as a result of the removal of Pavilion 5 as per
the minor change to application submitted 27 February 2025.
72. The trees identified for retention in the conditions of this approval must be maintained
in good health for the life of the tree.
*(Refer to Advisory Note)
Vegetation Removal
73. Any removal of vegetation must be in accordance with the conditions of this approval.
Land Rehabilitation
74. The land area containing retained vegetation is required to be rehabilitated with local
native species suitable for the area and the species selection consistent with the
naturally occurring species in the area whilst maintaining compliance with bushfire
conditions within this approval. The works must be undertaken in accordance with an
Operational Works approval.
75. A Vegetation Management and Rehabilitation Plan is to be prepared by a qualified
person* and submitted for approval as part of the operational works application. This
plan must include (but not limited to):
Page 10 of 12
Page 14
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
a. Existing remnant vegetation protection;
b. Vegetation rehabilitation;
c. Weed management; and
d. Performance outcomes and how and when they are to be achieved.
76. A “no clearing zone” must be established and maintained over the area identified as ‘1
– Existing Remnant Vegetation to be retained with weed management implementation’
within the Landscape Concept Design Package plan LCP5 listed within this Decision
Notice. With the exception of the trees approved to be removed in the conditions of this
approval. The following activities must not be carried out within the no clearing zone:
a. clearing, cutting down, poisoning, lopping or pruning of native vegetation which is
indigenous to, or planted within, the zone
b. soil/spoil dumping and/or compacting
c. soil excavation, other than for planting indigenous native plants.
The following exceptions apply:
a. declared plants under the Land Protection (Pest and Stock Route Management)
Act 2002 and sub-ordinate Regulation 2003, and any Council Listed Environmental
Weeds, Exotic Grasses and other plants identified in writing by Council
b. indigenous native trees which pose a well-founded threat to persons or property as
approved in writing by Council
c. controlled bushfire burns to maintain ecological processes subject to submission of
a Bushfire Management Plan and agreed in writing by Council.
Fauna Management
77. Vegetation must only be removed or disturbed in accordance with a Fauna
Management Plan (or part thereof) prepared by a qualified person* and endorsed
through an Operational Works approval. *(Refer to Advisory Note)
78. Permanent artificial nesting boxes must be installed within the Koala Habitat (Core) to
provide compensatory habitat for arboreal mammals and hollow dependent avian
species. The works must be undertaken in accordance with an Operational Works
approval.
Bushfire Management
79. The development must be carried out in accordance with the approved Bushfire Hazard
Assessment and Mitigation Plan version 8, prepared by Rob Friend and Associates
dated 25.02.2025, with the exception of the following:
a. Establishment of an additional evacuation point offsite within the golf course that
is separated from buildings and is located outside of identified bushfire hazard
prone areas or potential impact buffer.
The report must be resubmitted to Council incorporating the above amendments prior
to the issue of any Development Permit for Operational Works. *
*(Refer to Advisory Note)
80. Certification must be submitted to Council from a qualified person* which certifies that
the development has been constructed in accordance with the bushfire management
conditions of this Decision Notice. *(Refer to Advisory Note)
81. Certification must be submitted to Council from a qualified Person which certifies that
the development is sufficiently serviced by reticulated water with hydrant standpipes,
in ground hydrants and water pressure to meet firefighting needs in an emergency.
Page 11 of 12
Page 15
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
82. A copy of the Bushfire Hazard Assessment Report & Mitigation Plan and evacuation
procedure listed within this Decision Notice must be provided to the nearest fire
authority. *(Refer to Advisory Note)
WASTE DISPOSAL
83. Prior to the issue of any Operational Works approvals for this development an
Operational Waste Management Plan must be submitted to Council. The Waste
Management Plan must be in accordance with the Waste management Code and
Planning Scheme Policy 9 - Waste Management.
84. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9 - Waste Management. The facilities must include an
impervious area, within the site, correctly sized for all refuse and recycling containers
and suitably screened from public places and neighbouring properties. A bin wash area
is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket
trap. The drain outlet must be designed to prevent storm water entry to the sewerage
system.
85. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
86. Storage, disposal and management of solid, liquid and vegetative waste is conducted
in a safe and ecologically sustainable manner without environmental nuisance. In this
regard, vegetated waste must be disposed of via a green waste bin or at a local transfer
station.
B. Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
Page 12 of 12
Page 16
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
ATTACHMENT 2 – (MCU21/0110) - DEVELOPMENT ASSESSMENT MANAGER’S
REPORT
REPORT
A report was presented to Council at the Planning and Environment Committee on 11 July 2023
for a development application which seeks to develop a 106-room hotel on land within Noosa
Springs.
The report addressed a range of issues including the sites split zoning, the potential odour impacts
of the nearby sewage treatment plant, bushfire risk, ecology, carparking and built form. The
officer’s recommendation was to approve the application on the basis that the odour impacts had
been satisfactorily addressed and matters relating to bushfire, ecology, carparking and built form
had also been suitably addressed.
Three deputations were made at this meeting, the deputations were made by residents of Noosa
Springs, Unitywater and the applicant. Notably, Unitywater advised they were opposed to the
proposed development based on insufficient separation being provided to the existing sewage
treatment plant.
The matter was referred to the General Committee Meeting dated 17 July 2023 at which time a
motion was put forward to refuse the application. The motion was successful, and the application
was recommended for refusal.
On 19 July the applicant stopped the decision-making period until 29 September 2023. As this was
done prior to the Ordinary Meeting of 20 July 2023 Council was not able to finalise a decision on
the application. The decision-making period recommenced on 29 September 2023.
A Further Report was prepared for the Planning and Environment Committee meeting on 7
November 2023, due to the significance of the matter was referred to the General Meeting of 13
November 2023.
At that time the applicant had not amended the layout of the proposed development however
provided several written submissions which included an analysis of the submissions made during
the notification period, a letter from a solicitor reviewing the proposed grounds of refusal, and a
further letter from the applicant’s planning consultant seeking to justify grounds to support the
development.
The officer recommendation remained in support of the application, it was recommended that
condition 13 of the original recommendation, which required guests to be advised of the potential
for odour from the sewage treatment plant, be deleted. At that time, the grounds of refusal proposed
at the General Committee on 17 July 2023, were reviewed by a planning solicitor. Accordingly,
updated grounds of refusal were included in the report.
On 13 November 2023 the applicant made an Other Change to the application to include an
extension to the existing clubhouse. The change was an Other Change as it introduced a new land
use into the application. This meant that the application reverted to the Confirmation Notice stage
and no decision was able to be made on the application at the 13 November 2023 General
Committee Meeting.
A report considering the proposal including the Other Change was prepared for consideration at
the Planning and Environment Committee dated 11 June 2024, at this meeting the matter was
referred to the General Committee Meeting of 17 June 2024. At the General Committee meeting it
was agreed to defer the matter to a future meeting round as the applicant requested to extend the
decision-making period so it could enter into meaningful discussions about changes that might be
made to the proposed Resort Hotel, that are reasonable, to address any valid planning concerns
Councillors might have about the development.
On 27 February 2025, the applicant made a minor change to the application. In a letter supporting
the amended application the applicant advises:
Page 1 of 13
Page 17
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
The request for a minor change stems from concerns raised by councillors about the scale
of the development, which unavoidably, extends into the Recreation and Open Space Zone
and partly into the Biodiversity, Waterways and Wetlands Overlay (Biodiversity Overlay)
towards the east of the site. This is despite the development not having a significant impact
on any environmental values as confirmed by Dr Watson and Council’s environmental officer.
Other concerns were raised about the scale and extent of the pools within the centre of the
site and the continued operation of the tennis courts, including during construction.
The changes being made to the development are detailed below:
• Pavilion 5 has been removed from the top of the site towards the east with the stair and
lift area reconfigured for Pavilion 4.
• Pavilion 1, Level 1 presidential suite changed to two (2) deluxe rooms with a reduction in
the terrace areas at ground level.
• The character and privacy of the central recreation zone has been strengthened by
increasing the planted landscape spaces, with the swimming pools reduced in size and
enhanced by being integrated into a natural landscape setting.
• A minor increase in the size of the amenities building will provide for wellness facilities
that complement the recreation zone.
• A change to the overall design of the open space areas, with pathways and small deck
areas added to make some passive use of the open space area towards the east where
Pavilion 5 was located while maintaining the existing vegetation.
• An increase in the size of the southeastern tennis court to a ITF (pro-tour size) tennis
court; and
• A reduction in the height of the structures above the decked carpark to the south with the
solar panels to be maintained.
The minor change plans form the basis of the current assessment, these have been supported by
the following additional information.
• Addendum to Odour Report
• Noise Impact Assessment
• Updated Bushfire Hazard Assessment and Mitigation Plan
• Updated Ecological Advice
• Operational Waste Management Advice
The minor change has reduced the number of hotel rooms from 106 to 69.
The following images detail the previously proposed and currently proposed site plan of the
development.
Page 2 of 13
Page 18
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Figure 1: Previous proposed site plan (with zones)
Figure 2: Current proposed site plan (with zones)
Page 3 of 13
Page 19
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Figure 3: Previous proposed site plan
Figure 4: Current proposed site plan
Page 4 of 13
Page 20
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Change to include clubhouse (Other Change submitted 13 November 2024):
The change formalises the changes to the clubhouse that were referred to in the original officer
report, and include the following:
• Minor alterations to the internal configurations of the bar, kitchen, cold room and store
area (red dotted outline); and
• New liquor cool room, new dry store, new security & procurement office, new wet and
dry waste areas and new enclosed storage area (shown as yellow shading).
The applicant has advised:
The application material states that the proposed 105m² floor area extension to the existing
clubhouse would be obtained by undertaking a change to the current development approval
17380DA, which provides for a material change of use for a Country Club including Golf
Clubhouse, Health Club and Tennis Centre. It was originally intended to change the current
development approval once the approval for the “Boutique Hotel” was obtained; however, it
has now been decided to include this component as part of the current application.
The existing clubhouse, to which the proposed extension applies, is located within the Tourist
Accommodation Zone, a Club is an inconsistent use within this zone. Notwithstanding, the existing
clubhouse was approved under approval 17380 DA in 1999 and has occupied the site for an
extended period.
The inclusion of the Club use within the current Material Change of Use application facilitates minor
changes to the layout of the building with minor extensions to the building footprint as detailed in
the following image:
Figure 5: Additional clubhouse floor area (yellow)
The proposed additional 105m2 of gross floor area within the existing clubhouse was identified in
the original report to Council. At that time the assessment of plot ratio acknowledged the potential
additional clubhouse gross floor area noting the proposed plot ratio of all buildings, including the
proposed change to the clubhouse, would be significantly below the maximum allowed within the
Tourist Accommodation Zone (15,240m2 permitted with 10,208m2 proposed).
Page 5 of 13
Page 21
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Whilst the modifications to the clubhouse result in an increase in the use area of the clubhouse
this is primarily related to additional storage area and as such does not generate a need for
additional parking, noting the traffic consultant has reviewed the proposed car parking and is
satisfied that it adequately meets the needs of the proposed resort.
The Other Change was not required to be publicly notified on the basis that the change would not
be likely to attract a submission objecting to the thing comprising the change if public notification
were to apply to the change (s 27.3 Development Assessment Rules), this was on the basis that
the use has long been established and the proposed building alterations are minor.
Minor Change submitted 27 February 2025, including the deletion of pavilion 5:
Ecology
The applicant has provided a revised development layout that has reduced the extent of
disturbance to areas of mapped biodiversity. The original design that included pavilion 5 caused
disturbance to an overall area of approximately 1,562m², while the amended design with pavilion
5 removed has reduced the total extent of disturbance by 380m² to 1,182m².
Notably, 455m² of the 1,182m² affected area is comprised of low-impact pathways and decking.
These sections have minimal ecological effects since this infrastructure can be built to avoid trees
and valuable features, while providing access for maintenance and pedestrian way finding to open
spaces. Consequently, the actual disturbance on the mapped areas is reduced to just 727m².
From an ecological standpoint, the proposed changes to the development represent a notable
improvement. The initially proposed environmental outcomes are still in place, ensuring a
satisfactory ecological result and creating a net positive impact.
Previously proposed positive ecological outcomes remain part of the application, these include:
• Retention of mapped Koala habitat.
• Weed management.
• Landscaping and rehabilitation utilising suitable native species.
• Planting of 120 koala habitat trees.
• Planting of a minimum 25 Glossy Black-cockatoo feed trees.
• Relocation of hollow logs and installation of nest boxes.
Bushfire
The applicant has provided a revised bushfire report which includes the addition of ‘note 1’ which
addresses the setback distance requirements for the revised development proposal.
The original design needed to meet a minimum setback requirement to achieve a radiant heat flux
of less than 29kW/m², or a separation of 15.7 meters from the hazardous vegetation to the north.
The design exceeded this requirement by providing a separation of 21.9 meters from the northeast
and 24.4 meters from the northwest, resulting in a radiant heat flux within the range of 19-29kW/m².
Page 6 of 13
Page 22
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Figure 6: Bushfire separation of original proposal
The revised design which removes pavilion 5, now provides a separation distance of 38.4 metres
from the closest hazardous vegetation to the north. This equates to a separation distance
equivalent to less than 10kW/m². This outcome significantly improves the bushfire separation and
assists in mitigating the risk to people and property by locating infrastructure further away from
hazardous vegetation.
Page 7 of 13
Page 23
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Figure 7: Bushfire separation of amended proposal
All previous bushfire recommendations are still applicable to the revised development layout.
Landscape
The applicant has provided a revised set of concept landscape plans that depict the revised layout.
The plans have included additional areas of remnant vegetation to be retained within the location
of the now removed pavilion 5, as well as incorporated bush pathways and timber decks that wind
through the trees and located existing trees for meditation/relaxation. The revised plans are
considered appropriate at this conceptual stage, with detailed design to be undertaken as part of
a landscape operational works application.
Site Cover and Plot Ratio
The subject site includes an area of 23,447m2 that is zoned Tourist Accommodation. The balance
of the site is zoned Recreation and Open Space Zone (14,608m2).
The Tourist Accommodation zone code requires a maximum site cover of 40% (9,378m2) and a
Plot ratio of 0.65:1 (15,240m2). The Recreation and Open Space Zone requires a maximum site
cover of 10% (1,460m2) whilst the relevant performance outcome prescribes that the gross floor
area of buildings of roofed structures does not exceed 100m2 excluding major sporting clubs,
clubhouse facilities which do not exceed 800m². 3,052m2 of gross floor area is proposed in the
Open Space and Recreation Zone.
Page 8 of 13
Page 24
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
The total site cover of all buildings on the site (including that zoned Recreation and Open Space)
is:
• Existing club house -1,839m2
• Existing day spa & gymnasium -1,308m2
• New Hotel – 2,721m2
• Tennis Courts – 2,558m2
• Elevated car park – 1,234m2
The total gross floor area of all buildings on the site (including that zoned Recreation and Open
Space) is:
• Proposed Hotel facilities – 5,392m2
• Existing day spa and gymnasium - 1,241m2
• Existing clubhouse - approximately 2,000m2 + 105m2 proposed as part of future change.
The following table details the proposal’s compliance with site cover and plot ratio.
Zone Proposed
Site Cover Tourist Accommodation Zone 5,868m2
9,378m2 permitted
Recreation and Open Space Zone
1,460m2 permitted
Total Permitted: 10,838m2 Total including car park and tennis
courts: 9,660m2
Plot Ratio Tourist Accommodation Zone 5,686 m2
15,240m2 permitted
Recreation and Open Space Zone 3,052m2
Buildings do not generally exceed
100m2 excluding major sporting clubs,
clubhouse facilities which do not exceed
800m².
Total: 8,738m2
Importantly, the area shown zoned for tourist accommodation is not on a cadastral base, nor was
the determination of the zone boundaries based on detailed odour assessment. The assessment
of the current application, including consideration of the supporting material, has enabled a ground
truthing to determine the most suitable footprint for the proposed tourist accommodation use to
occur.
It is acknowledged that the extent of site cover does not comply within the existing mapped
Recreation and Open Space zone when considered in isolation. However, the proposal complies
with the total amount of site cover and plot ratio permitted over the whole site noting that the
building and structures do not detrimentally reduce the useability of open space or dominate the
site. It is noted that the current proposal has reduced the extent of pool area from 1,157m2 to
457m2.
Page 9 of 13
Page 25
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Furthermore, the total extent of site cover and plot ratio proposed do not exceed the amount
permitted under the Tourist Accommodation Zone, on this basis it is considered that the site cover
and plot ratio are appropriate for the overall site.
Odour and Noise
The submitted acoustic report and addendum to the odour report have been reviewed by Council’s
external consultant who is supportive of the amended layout and advises:
With respect to odour, the amended design is considered acceptable. An odour complaints
management plan remains relevant.
With respect to noise, …..amended operating hours for the tennis courts to match the latest
Trinity Report.
For outdoor area usage – previous conditions referred to Plate 1 which limited use hours.
The intent previously was to allow use of outdoor dining areas immediately adjacent the hotel
but to limit the use of pool areas further north. This was both a noise and odour outcome.
I suggest a similar requirement be maintained for this amended development. Limit all pool
usage to 6am to 12MN.
…….include a new condition putting the noise limits from Section 6.1 of the Trinity report into
the conditions package.
Service and refuse collection hours maintained as 7am to 6pm.
Given that the Trinity report shows the vacuum truck operations (albeit infrequent) exceed
the noise limits nominated, I have included requirement for an amended noise report to
address this as the report says with further design and barriers etc, compliance can be
worked out later.
I am happy to accept their amended criteria for this infrequent event.
Unitywater
As noted in the original report and through deputations made by their representatives, Unitywater
has raised concerns with the proposed development. Speifically that the accommodation facilities
and recreation areas are located too close to the nearby Noosa Sewage Treatment Plant (STP)
and will likely result in odour complaints with subsequent compliance action potentially requiring
cost prohibitive upgrades.
As per the original assessment, a thorough analysis of odour impacts has been undertaken by
suitably qualified experts utilising methodologies that are accepted in Planning and Environment
Court proceedings.
As noted in the officer report to Council in July 2023, the original odour impact assessment report
was prepared based on site-specific odour monitoring conducted at the STP and use of
meteorological and dispersion modelling to assess resultant odour levels at the proposed
development site.
The odour assessment adopted the Queensland Odour Guideline odour criterion of 2.5 Odour
Units, 1 hour average, 99.5 percentile which is considered the appropriate basis for assessment,
and notably the benchmark considered in Planning and Environment Court appeals. The criterion
requires the prescribed odour concentration to be achieved 99.5% of the time, being measured at
one-hour intervals.
The current proposal maintains development outside of the 2.5 odour unit line, notably the current
proposal increases the distance from the Noosa STP to both the nearest accommodation building
and the swimming pool. Under the originally proposed layout the accommodation buildings were
located approximately 270 metres from the existing Noosa STP infrastructure, the current proposal
provides approximately 302 metres of separation.
Page 10 of 13
Page 26
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Importantly, whilst Unitywater have provided a response to the methodologies utilised by both the
applicant’s and Council’s consulting acoustic consultants they have not conducted their own
technical analysis.
A review of the applicant’s report and Council’s consulting odour expert was undertaken by
Unitwayter’s third-party consultant who notes their own work was……limited to a high-level
review of the proposed mitigation measures contained within the Provided Documents and
recommend further mitigation measures that could be considered by council and/or
Proponent, which would aid in further reducing the impact risk of the Proposed Development
encroachment upon the current and future operational and business continuity of Noosa STP under
normal and unintended or unavoidable odour release conditions [bold added].
As per the original report to Council, the further mitigation measure included the installation of
activated carbon filters to fresh air makeup locations. This has been included within the
recommended conditions to further protect indoor air quality.
Whilst Unitywater have expressed concerns regarding use of land that is reasonably separated
from the existing Noosa STP it is important to note that under the Noosa Plan 2020 numerous
consistent uses are identified within the Recreation and Open Space Zone, these include:
• Tourist Park
• Nature-based tourism
• Major sport, recreation and entertainment facility
• Outdoor Sport and Recreation
• Indoor Sport and Recreation
• Place of worship
• Emergency services
• Community use
• Club
• Market
Notably, a Park is Accepted development, this would permit occupation to the property boundary
which at its minimum is 220 metres from existing STP infrastructure.
Furthermore, the Noosa Plan 2020 does not include a requirement for a separation distance to be
provided from the Noosa STP.
Waste Management
In summary, the key elements of the waste management strategy are:
• Refuse collection methodology to remain unchanged when compared to current
methodology associated with the existing day spa and clubhouse – a waste collection
vehicle can enter and exit the site in a forward gear from the eastern side of the site via
Resort Drive.
• Transfer of new waste from the proposed Hotel to occur via an electric bin tug from ground
level.
• Waste to be stored in a waste storage room within the extended clubhouse, currently uses
the existing loading bay.
• Development will result in increased waste generation; no change to frequency of waste
collection proposed although more regular servicing can occur on site if needed.
The submitted Operational Waste Management Advice has been reviewed by Council’s Waste
Management team who are satisfied with report and recommended conditions.
CONSULTATION
Referral Agencies
The amendments to the application have been referred to SARA who have not raised any issues.
Page 11 of 13
Page 27
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
Internal Council Referrals
The application was forwarded to the following internal Council officers:
• Senior Environment Officer
• Coordinator Development Engineering
• Waste Management Department
Other Referrals
Through the assessment the application has been forwarded to the following external experts for
review and/or comment:
• Bushfire
• Hydraulic Engineer
• Traffic consultant
• Acoustic consultant
• Odour consultant
EQUITABLE ACCESS AND FACILITIES
In assessing this application, the plans for the proposed building work have not yet been evaluated
for compliance with the requirements of the National Construction Code - Building Code of
Australia (Volume 1) as they pertain to people with disabilities. The following codes may impact
the proposed building work and will be addressed as part of future building approvals required for
the site:
a. The Disability Discrimination Act 1992 (Commonwealth)
b. The Anti-Discrimination Act 1991 (Queensland); and
c. The Disability (Access to Premises – Buildings) Standards.
HUMAN RIGHTS COMPATIBILITY STATEMENT
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in
a manner that is compatible with huma rights. This report should be rea in conjunction with
Council’s Human Rights Policy.
CONCLUSION & REASONS FOR DECISION
This report has considered the Other Change made on 13 November 2023 to include an extension
to the existing clubhouse and the Minor Change received 27 February 2025 primarily involving the
deletion of Pavilion 5.
The introduction of the Club use and the associated amendments to the existing clubhouse raise
no concerns on the basis the clubhouse use was approved in 1999, the proposed changes do not
exceed the permissible plot ratio and adequate car parking is providing on site noting that the
increased use area primarily relates to additional storage.
The Minor Change has reduced the footprint of the development, increased the separation distance
from the Noosa STP and reduced the extent of tourist accommodation proposed within the Open
Space and Recreation Zone.
Page 12 of 13
Page 28
PLANNING AND ENVIRONMENT COMMITTEE MEETING REPORT 6 MAY 2025
The officer’s recommendation remains in support of the development and has required minor
amendments to previously recommended conditions to reflect updated plans and reports whilst the
condition requiring guests to be advised of the potential for odour from the sewage treatment plant
has been removed.
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors Director Director
Chief Executive Officer Community Development Financial Services
Executive Officers Sport & Active Lifestyles Fleet
Community Engagement Arts & Culture Revenue Services
People & Culture Community Connection ICT
Governance Customer Experience Procurement
Commercial Property
Strategy & Environment Development & Regulation Infrastructure Services
Director X Director Director
Strategic Land Use Planning X Development Assessment Infrastructure Planning, Design
and Delivery
Economic Development & Local Laws Civil and Asset operations
Destination Management
Environmental Services Environmental Health X Waste
Innovation & Digital Hub Building & Plumbing Building & Facilities
Property / Permits Disaster Management
Page 13 of 13
Page 29
ATTACHMENT 3 - MCU21/0110 - OFFICER REPORT 11 JULY 2023
PLANNING & ENVIRONMENT COMMITTEE MEETING 11 JULY 2023
5.1 MCU21/0110 - APPLICATION FOR MATERIAL CHANGE OF USE - BAR, FOOD, AND
DRINK OUTLET, OUTDOOR SPORT AND RECREATION, RESORT COMPLEX AT 61
NOOSA SPRINGS DRIVE, NOOSA HEADS
Author Development Assessment Manager, Patrick Murphy
Development & Regulation Department
Index Application / MCU21/0110
Attachments 1. ATTACHMENT 1 - MCU21 0110 - PROPOSED CONDITIONS
2. ATTACHMENT 2 - MCU21 0110 - MANAGER DEVELOPMENT
ASSESSMENT REPORT
3. ATTACHMENT 3 - MCU21 0110 - PROPOSAL PLANS
EXECUTIVE SUMMARY
The application seeks to develop a 106 room hotel on land within Noosa Springs, the hotel is to
operate as an integrated development utilising the existing facilities at Noosa Springs Golf and Spa
Resort.
The site is split zoned, with both the Tourist Accommodation Zone and the Recreation and Open
Space Zone applying to the site. The application of split zoning to the site was in response to the
need for an odour buffer between future development and the nearby sewage treatment plant
(STP). Supporting documentation has assessed the odour impacts of the STP to determine the
appropriate building footprint and associated outdoor recreation areas. This material has been
reviewed and supported by Council’s consulting odour expert with conditions recommended to
address use of outdoor areas and ventilation of the building at its interface with the accepted odour
limit. The built form has been sited within the determined footprint with some outdoor dining and
recreational facilities proposed to be located outside of this area.
The proposed built form is consistent with the prevailing built form within Noosa Springs and
compliments the golf clubhouse and spa facilities which are located nearby. The building exceeds
the height limit in limited areas due to the topography of the site and the large footprint which is
anticipated in buildings providing resort accommodation.
The built form extends over both zones with the extent of site cover not exceeding the combined
amount permitted within the Tourist Accommodation Zone and Recreation and Open Space Zone.
The extent of plot ratio over the whole site does not exceed the amount permitted under the Tourist
Accommodation Zone.
The application has also demonstrated compliance with the carparking, bushfire, and water
quality/quantity requirements of the Noosa Plan whilst variations to setbacks are supported.
The application is recommended for approval subject to conditions.
RECOMMENDATION
That Council note the report by the Acting Development Assessment Manager to the Planning &
Environment Committee Meeting dated 9 My 2023 regarding MCU21/0110 development permit for
material change of use for resort complex (106 rooms), food and drink outlet, bar and outdoor sport
and recreation at Links Drive, Noosa Heads and:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 30
PLANNING & ENVIRONMENT COMMITTEE MEETING 11 JULY 2023
A. Approve the application in accordance with the proposed conditions detailed in Attachment 1.
B. Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
C. Find the following relevant to the assessment and sufficient reason to approve the application:
1. The current mapped Recreation and Open Zone, was a consequence of it not being
adequately demonstrated, at the time it was created, that further encroachment would not
result in amenity impacts on guests of a resort. The current application has reviewed the
potential for odour impacts of the nearby sewage treatment plant and has identified an
accurate and appropriate area for the development footprint to be located.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 31
ATTACHMENT 1 – MCU21/0110 – PROPOSED CONDITIONS
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the
use continues.
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA 1.00 13 Site Plan, prepared by Marchese Partners 09.02.2023
DA 1.01 13 Entry Link Level Plan, prepared by Marchese 09.02.2023
Partners
DA 1.02 13 Basement Plan, prepared by Marchese 09.02.2023
Partners
DA 1.03 11 Lower Ground Floor Plan, prepared by 09.02.2023
Marchese Partners
DA 1.04 11 Ground Level Plan, prepared by Marchese 09.02.2023
Partners
DA 1.05 11 Level 1 Plan, prepared by Marchese Partners 09.02.2023
DA 1.06 11 Level 2 Plan, prepared by Marchese Partners 09.02.2023
DA 1.07 11 Level 3 Plan, prepared by Marchese Partners 09.02.2023
DA 1.08 11 Roof Plan, prepared by Marchese Partners 09.02.2023
DA 1.12 3 Carpark Plans, prepared by Marchese Partners 09.02.2023
DA 2.01 12 Noth and East Elevation, prepared by 09.02.2023
Marchese Partners
DA 2.02 12 South and West Elevation, prepared by 09.02.2023
Marchese Partners
DA 2.03 3 Carpark Elevations and Section, prepared by 09.02.2023
Marchese Partners
DA 2.04 6 Tennis Courts, prepared by Marchese Partners 09.02.2023
DA 3.01 12 Building Sections, prepared by Marchese 09.02.2023
Partners
DA 3.02 10 Part 1 Sections, prepared by Marchese 09.02.2023
Partners
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 32
DA 3.03 11 Part 2 Sections, prepared by Marchese 09.02.2023
Partners
DA 0.03 7 GFA Calculations, prepared by Marchese 09.02.2023
Partners
DA4.05 9 3D View – Building Entry, prepared by 09.02.2023
Marchese Partners
DA4.06 9 3D View – Pool View 1, prepared by Marchese 09.02.2023
Partners
DA4.07 9 3D View – Pool View 2, prepared by Marchese 09.02.2023
Partners
DA4.08 9 3D View – Looking North from Resort Drive, 09.02.2023
prepared by Marchese Partners
DA5.02 6 Accommodation Types, prepared by Marchese 09.02.2023
Partners
LCP2 – D Landscape Concept Design Package prepared 08.02.2023
LCP23 by Place Design Group
N/A 1 Terrestrial Ecology Assessment prepared by
Gondwana Ecology dated 26.02.2020 and as
amended by letter from Gondwana Ecology
dated 9 February 2023
N/A 4 Bushfire Hazard Assessment prepared by Rob
Friend & Associates dated 30.04.2022 and as
amended by the letter from Rob Friend and
Associates dated 10.02.2023
Plate 1 Outdoor Use Areas – Time of Use Restrictions
Nature and Extent of Approved Use
3. The approved resort units must be used for short term visitors only. The approved units
must not be occupied by persons for the purpose of permanent accommodation,
excluding those persons in a manager's residence for the premises. The requirements
of this condition must be included in the Community Management Statement for any
body corporate for the subject site.
4. The approved uses and associated activities must not result in environmental
nuisances such as noise, visual or odour impacts that unreasonably diminish the
amenity of the area or surrounding uses.
5. Service vehicle movements associated with non-residential uses on the premises
(including loading and unloading) must not occur outside the hours of 7am to 6pm
Monday to Saturday and not at all on Sundays or public holidays. The requirements of
this condition must be included in the Community Management Statement for any body
corporate for the subject site.
6. Conferences and Functions must only occur within the existing Noosa Springs Golf
and Spa Resort.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 33
Currency Period
7. This development approval lapses if the use has not happened by 20 July 2029 unless
an application to extend the currency period is approved by Council.
Ventilation
8. All internal use areas of the accommodation use including hotel suites, common areas,
office, dining, bar and lobby areas shall be fully air-conditioned, allowing external
façade elements (doors and windows) to be closed if required. Fresh air makeup to the
air conditioning systems must be drawn from roof level locations located as far as
practical from the Noosa Wastewater Treatment Plant.
9. Activated carbon filtration to be installed on all fresh air makeup locations of the
air conditioning systems and are regularly maintained to manufacturer specifications.
Outdoor Use Areas – swimming pools and tennis courts
10. Use by guests and visitors of the tennis courts, is limited to the time period 6am to
10pm only.
11. Use by guests and visitors of the swimming pools located to the north of the proposed
buildings as identified in Plate 1 (not including the outdoor area between the proposed
buildings) is limited to the time period 6am to 12am only.
Acoustic
12. An updated acoustic report must be submitted to Council prior to the issue of an
Operational Works approval. The amended acoustic report must include
recommendations to address the impact on the residential amenity attributed to use of
the loading docks, including the noise associated with vehicles and trucks accessing
and using the loading docks. The recommendations of the acoustic report must be
implemented prior to the commencement of the approved uses.
Odour
13. All guests must be advised of the potential for odour from the sewage treatment plant
to be noticeable.
14. The operator must maintain an Odour Complain Management Plan, with the plan
including the internal management of any complaints from hotel guests. The Odour
Management Plan must be submitted to Council prior to the issue of an Operational
Works approval.
Built Form and Development Appearance
15. The maximum height of the development must be in accordance with the approved
plans.
16. Certification must be submitted to Council from a Licensed Surveyor which certifies
that the buildings do not exceed the maximum height requirement of this Decision
Notice.
17. All air conditioning units or other mechanical equipment must be fully enclosed or
screened such that they are not visible from the street frontages nor adjoining
properties.
18. All deck and balcony areas above ground floor must not be enclosed by permanent
fixtures such as shutters, louvres, glass panelling or the like.
19. The development must incorporate the colour scheme and proposed mix of building
materials as outlined in the approved plans.
20. Any security screens on the premises consist of grille or translucent screens and not
solid shutters, screens or roller-doors.
21. All mechanical equipment and other service infrastructure located on the site must be:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 34
a. located not less than 2 metres from a property boundary;
b. fully enclosed or screened such that they are not visible from the street frontages
nor adjoining properties. Where screened by landscaping, landscaping beds
must be at least 1.5 metres wide.
22. No part of the site may be used for outdoor storage of materials.
Performance Bond
23. Security in the form of a cash bond or trading bank guarantee to the sum of $200,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond
or guaranteed sum to effect compliance with conditions.
Tennis Court Fencing
24. Tennis court fencing must be comprised of black powder coated posts and rails with
black PVC coated chain wire mesh, or the like.
Tennis Court Light Spillage and Glare
25. Lighting must be directed onto the site and away from neighbouring properties.
26. The level of light emanating outside the property must not exceed an illumination level
of 12 lux nor an average of 10 lux when measured 3 metres outside the property
boundary.
27. The light fittings must be baffled to ensure that a light source is not directly visible from
the habitable room window of an adjoining property.
28. All light readings are to be taken in a horizontal plane at a height of 1000mm above
ground level.
Tennis Court Operating Hours
29. Tennis courts must not be illuminated after 10.00p.m. nor before 7.30 a.m.
Structural Stability
30. All lighting support columns must be manufactured from galvanised steel.
31. The pole height shall not exceed 8 metres.
32. The pole and associated concrete footing design must be engineer certified to support
the light fitting and to withstand wind loads appropriate to the terrain classification.
Tennis Ball Machines
33. Machines which operate on the air compression principle must not be used after 7.00
p.m. nor before 8.00 a.m.
34. Silent running machines which operate at a noise level not exceeding 10 decibels
(when measured at the property boundary) must not be used after 10.00 p.m. nor
before 7.30 a.m.
Public Safety
35. During operating hours, all parking areas, pedestrian areas and entrances/exits to all
stairwells, lifts, foyers and public toilets must be well lit with vandal resistant lighting
and with intensities to satisfy the requirements of Australian Standard AS1158 “Public
Lighting Code”. Lighting must be designed to reduce the contrast between shadows
and well lit areas. In particular, appropriate security lighting must be provided in the
location of the bicycle/ scooter parking and bin storage area.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 35
36. After hours access to loading docks, storage areas and the basement carpark
(including the vehicle ramp and all stairwells) must be restricted by a security gate,
lockable doors and/or other suitably appropriate means. The basement carpark must
be kept closed and locked at all times while the use is not operating.
Community Management Statement
37. Any proposed Community Management Statement required for the development
pursuant to the Body Corporate and Community Management Act 1997 must be
submitted to Council for endorsement at the same time as submission of the Building
Format Plan (or similar) to Council for compliance assessment.
38. All clauses and by-laws of the proposed Community Management Statement must
accord with the requirements of this Decision Notice.
Water & Sewer Connections
39. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
40. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to the development site.
ENGINEERING/TRAFFIC
Site Access and Driveways
41. A sealed access driveway must be provided from the internal service road to all parking
and manoeuvring areas of the development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawing RS-051 and
respective addendum; and
b. suitable safety measures, including warning signage, to improve driver
awareness of pedestrians and enhance pedestrian safety. Warning signage must
be provided near the exit ramp from the underground parking area to warn
motorists of pedestrian movement along the frontage street.
Car Parking
42. Car parking must be provided in accordance with the approved plans and as amended
by the conditions of this approval. The works must be undertaken in accordance with
an Operational Works approval.
43. The parking layout is to be in accordance with the requirements of AS/NZS 2890.1-
2004
44. Provision of vandal resistant public lighting with intensities to satisfy the requirements
of Australian Standard AS1158: Public Lighting Code;
45. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
46. Directional signage must be provided to direct visitors and customers to the car parking
spaces provided on site.
Security Access to Carpark
47. Where access to the carpark is proposed to be restricted by a security gate, provision
must be made for queuing of vehicles clear of the roadway while waiting for the security
gate to open.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 36
48. Where a secure carpark services a commercial use on the site, the security gate must
remain open at all times while commercial uses on the site are open for business. The
requirements of this condition must be included in the Community Management
Statement for anybody corporate for the subject site.
Service Vehicles
49. Service vehicle parking, manoeuvring and standing spaces must be provided on the
site. The works must be undertaken in accordance with an Operational Works
approval.
Pedestrian and Bicycle Facilities
50. Pedestrian and bicycle facilities must be provided for the development. The works must
include in particular:
a. signage and lighting at strategic locations to direct people to building entries and
public toilet facilities;
b. a total of 53 bicycle parking spaces; and
c. end of trip facilities involving 27 lockers, 6 showers and change rooms within the
development.
Water quality and quantity
51. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and the Queensland Urban Drainage Manual
52. A stormwater quality treatment system must be provided for the development. The
works must be undertaken in accordance with an Operational Works approval and the
Bioretention Technical Design Guidelines (Water by Design, 2012), and must include
in particular:
a. stormwater quality treatment devices of a size and location generally in
accordance with those shown in Drawing No. C6070/20/P07 prepared by Walsh
Consulting Engineers dated 26/10/2021, with the exception of the following:
i. Bioretention filter area is to be increased in size to the area stated for
bioretention surface area on the above referenced plan
b. bioretention devices which:
i. are designed generally in accordance with IPWEQA Standard Drawing
No.s DS-073, DS-075 and DS-076
ii. are provided with a free-draining outlet from the sub-soil drainage system
53. Permanent educational signage* must be erected to educate the residents of /
customers to the development about the function of the bioretention device(s). The
dimensions, standard, presentation and location of the educational signage must be in
accordance with an Operational Works approval.
54. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The
approved Operational Works drawings for the stormwater quality treatment system and
detailed life cycle costing of the system must be attached as an addendum to this
document. Records of all maintenance activities undertaken must be kept and made
available to Council upon request.
55. Operating roof water harvesting tanks must be provided for the development. The tanks
must be provided in accordance with an Operational Works approval and must include
in particular:
a. a total tank capacity of 135,000 litres
b. a catchment of not less than 2,800m2 of the building roof area
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 37
c. re-use of harvested stormwater for non-potable outdoor uses including irrigation
of landscaped areas and swimming pool top-up
56. Certification must be submitted to Council from a qualified person which certifies that
the stormwater harvesting tanks and associated reticulation has been installed in
accordance with the requirements of this Decision Notice.
Acid Sulfate Soils
57. An Acid Sulfate Soil Management Plan must be prepared and submitted with the
Operational Works application for the site. The acid sulfate management plan must
include testing, monitoring and treatment requirements for the works.
Services
58. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
59. Certification must be submitted to Council from all relevant service providers (Energex,
NBN and Unitywater which certifies that the development has met the requirements of
this Decision Notice and all applicable legislation at the time of construction.
Easements
60. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
61. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard
easement terms. Draft easement documentation must be submitted to Council for
endorsement.
62. All works must be kept clear of any existing or proposed easements on the subject
land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
63. All excavation, fill, soil retaining structures and associated batters must be undertaken
in accordance with an Operational Works approval and contained entirely within the
subject site unless written permission from the respective landowner(s) is provided to
Council.
64. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All
retaining walls that are publicly accessible and exceed 1.0m in height must be fitted
with a commercial grade safety fence.
Damage to Services and Assets
65. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 38
LANDSCAPING
Landscaping Works
66. The development site must be landscaped in accordance with a Council endorsed
landscape package prepared by a qualified person*. The works must be undertaken
in accordance with an Operational Works approval and the Noosa Plan for that specific
area and must include in particular:
a. the works shown on the Approved Landscape Concept Design Package Plans,
with the exception of:
i. extending ‘31. Turf - no plantings with 5 metres of building’ as annotated
by Council;
b. a Landscaping Plan and Plant Pallet including hard and soft plant percentages,
plant numbers, planting locations, pot sizes and whether Noosa Native,
Australian Native or Exotic;
c. a Landscape Management Plan including (but not limited to):
i. landscape design principles for bushfire hazard areas in Part 5 of Bushfire
Resilient Building Guidance for Queensland Homes (QRA 2020);
ii. Certification from a qualified* person ensuring the Landscape Management
Plan complies with the design principles in the Part 5 of Bushfire Resilient
Building Guidance for Queensland Homes (QRA 2020) and the Bushfire
Management Plan.
iii. Management of branches overhanging building envelopes.
d. clear integration of the Bushfire requirements and recommendations identified
within the approved Bushfire Hazard Assessment Report & Mitigation Plan
version 4 dated 30 April 2022, and as amended by the Further Advice letter from
Rob Friend and Associates Pty Ltd dates 10 February 2023, including
landscaping treatments where maximum distances are permitted including:
i. a band of vegetation up to 20m wide along Resort Drive is to contain 100%
less flammable plant species;
ii. the remaining area greater than 20m from Resort Drive can contain no less
than 50% less flammable plant species in the understory and groundcover;
and
iii. regular maintenance of groundcover and understorey to reduce
flammability within the landscaped area.
e. clear integration of the landscaping recommendations, for the purpose of odour
mitigation, identified in the Katestone report dated December 2020.
f. A vegetated buffer of a height that avoids line of sight contact with the Sewage
Treatment Plant from any place or structure on the development site to Council’s
satisfaction.
g. Both sides of Resort Drive Road Reserve between the intersections of Links
Drive and Lakeview Rise must be rehabilitated and revegetated in accordance
with the landscaping recommendations of the approved Bushfire Hazard
Assessment and Mitigation. The works must be undertaken in accordance with
an Operational Works approval.
h. Details of water quality treatment device plantings with a minimum of five plant
species and a plant density of 8 plants per square meter;
i. Details of all fencing and gates (including but not limited to height, construction
type, materials);
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 39
j. Details of tree protection methods provided by a qualified person* to be engaged
to protect trees identified within the conditions of this approval in particular
vegetation located within the mapped Koala Habitat Area to the north of the
development site.
k. Native trees of a minimum pot size of 100L to replace existing trees to be
removed from the site, at the rate of 1 replacement tree for every tree removed
that has a diameter greater than 200mm measured at 1.2 metres from ground
surface level.
l. Vegetated screening of any electrical transformers, bin storage areas and the
like from the road frontage.
m. Vegetation offsets in accordance with the recommendations Gondwana Ecology
letter dated 9 February 2023.
67. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
68. Control of all weeds species listed in the following standards and legislation:
a. Declared plants under the Land Protection (Biodiversity Act 2014 and sub-
ordinate Regulation 2016).
b. Noosa Local Government Area Pest Management Plan 2015-2019.
c. Undesirable Species as listed in Planning Scheme Policy 3 Landscaping Plants
and Guidelines.
69. All entry statements, fences, retaining walls and buffer/screen plantings must be
located entirely within private land and not within the public road reserve.
Treatment of Temporarily Vacant Land
70. Where some or all of the land remains vacant or undeveloped for more than 3 months,
or buildings are demolished and redevelopment is delayed for more than 3 months, the
following works must to be carried out:
a. the site must be cleared of all rubble, debris and demolition materials
b. the site must be graded to prevent ponding (to the same level as the adjoining
footpath wherever practicable), turfed and mown at a minimum 3 weekly intervals
c. the site must be landscaped with perimeter planting consisting of advanced
specimens of fast growing tree species
d. the site must be maintained to ensure no nuisance to adjacent premises, roads
or footpaths
e. where fencing is installed to secure boundaries:
i. the fencing must be durable and not capable of being pushed or blown over
ii. the fencing type must not detract from local amenity (barbed wire is not
acceptable)
iii. vandalism must be promptly repaired and any graffiti removed.
Retention of Existing Trees
71. Existing trees on the development site and in the road reserve must be retained in
accordance with an Arborist Report (or part thereof) prepared by a qualified person*
and endorsed through an Operational Works approval. The Arborist Report must
include:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 40
a. Tree removal/retention plan that includes all native trees and identifies in
particular all native trees to be removed with a diameter greater than 200mm
measured at 1.2m from ground surface level.
*(Refer to Advisory Note)
72. Vegetation identified as not approved for removal within ‘Attachment E - Tree Removal
Plan’ within the approved Terrestrial Ecological Assessment report, and as amended
by the letter, attached plans and tree survey prepared by Gondwana Ecology dated 9
February 2023, must be protected.
73. The trees identified for retention in the conditions of this approval must be maintained
in good health for the life of the tree.
Vegetation Removal
74. ‘Attachment E - Tree Removal Plan’ within the approved Terrestrial Ecological
Assessment report and as amended by the letter, attached plans and tree survey
prepared by Gondwana Ecology dated 9 February 2023 identifies the vegetation
approved for removal.
75. Any removal of vegetation must be in accordance with the conditions of this approval.
Land Rehabilitation
76. The land area containing retained vegetation is required to be rehabilitated with local
native species suitable for the area and the species selection consistent with the
naturally occurring species in the area whilst maintaining compliance with bushfire
conditions within this approval. The works must be undertaken in accordance with an
Operational Works approval.
77. A Vegetation Management and Rehabilitation Plan is to be prepared by a qualified
person* and submitted for approval as part of the operational works application. This
plan must include (but not limited to):
a. Existing remnant vegetation protection;
b. Vegetation rehabilitation;
c. Weed management; and
d. Performance outcomes and how and when they are to be achieved.
78. A “no clearing zone” must be established and maintained over the area identified as ‘1
– Existing Remnant Vegetation to be retained with weed management implementation’
within the Landscape Concept Design Package plan LCP5 listed within this Decision
Notice. With the exception of the trees approved to be removed in the conditions of this
approval. The following activities must not be carried out within the no clearing zone:
a. clearing, cutting down, poisoning, lopping or pruning of native vegetation which
is indigenous to, or planted within, the zone
b. soil/spoil dumping and/or compacting
c. soil excavation, other than for planting indigenous native plants.
The following exceptions apply:
a. declared plants under the Land Protection (Pest and Stock Route Management)
Act 2002 and sub-ordinate Regulation 2003, and any Council Listed
Environmental Weeds, Exotic Grasses and other plants identified in writing by
Council
b. indigenous native trees which pose a well-founded threat to persons or property
as approved in writing by Council
c. controlled bushfire burns to maintain ecological processes subject to submission
of a Bushfire Management Plan and agreed in writing by Council.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 41
Fauna Management
79. Vegetation must only be removed or disturbed in accordance with a Fauna
Management Plan (or part thereof) prepared by a qualified person* and endorsed
through an Operational Works approval.
*(Refer to Advisory Note)
80. Permanent artificial nesting boxes must be installed within the Koala Habitat (Core) to
provide compensatory habitat for arboreal mammals and hollow dependent avian
species. The works must be undertaken in accordance with an Operational Works
approval.
Bushfire Management
81. The development must be carried out in accordance with the approved Bushfire Hazard
Assessment Report & Mitigation Plan version 4 dated 30 April 2022, and as amended
by the Further Advice letter from Rob Friend and Associates Pty Ltd dated 10 February
2023, listed within this Decision Notice, with the exception of the following:
a. Establishment of an additional evacuation point offsite within the golf course that
is separated from buildings and is located outside of identified bushfire hazard
prone areas or potential impact buffer.
The report must be resubmitted to Council incorporating the above amendments prior
to the issue of any Development Permit for Operational Works.*
*(Refer to Advisory Note)
82. Certification must be submitted to Council from a qualified person* which certifies that
the development has been constructed in accordance with the bushfire management
conditions of this Decision Notice. *(Refer to Advisory Note)
83. Certification must be submitted to Council from a qualified Person which certifies that
the development is sufficiently serviced by reticulated water with hydrant standpipes,
in ground hydrants and water pressure to meet firefighting needs in an emergency.
84. A copy of the Bushfire Hazard Assessment Report & Mitigation Plan and evacuation
procedure listed within this Decision Notice must be provided to the nearest fire
authority.
*(Refer to Advisory Note)
WASTE DISPOSAL
85. Prior to the issue of any Operational Works approvals for this development an
Operational Waste Management Plan must be submitted to Council. The Waste
Management Plan must be in accordance with the Waste management Code and
Planning Scheme Policy 9 - Waste Management.
86. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9 - Waste Management. The facilities must include an
impervious area, within the site, correctly sized for all refuse and recycling containers
and suitably screened from public places and neighbouring properties. A bin wash area
is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket
trap. The drain outlet must be designed to prevent storm water entry to the sewerage
system.
87. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
88. Storage, disposal and management of solid, liquid and vegetative waste is conducted
in a safe and ecologically sustainable manner without environmental nuisance. In this
regard, vegetated waste must be disposed of via a green waste bin or at a local transfer
station.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 42
ATTACHMENT 2 – MCU21/0110 - MANAGER DEVELOPMET ASSESMENT REPORT
APPLICATION DETAILS
Applicant Noosa Springs Real Estate Pty Ltd
Proposal Material Change of Use - Bar, Food and Drink Outlet, Outdoor
sport and recreation, Resort complex
Properly Made Date 22 June 2021
Information Request Date 23 July 2021
Information Response Date 24 November 2021
Decision Due Date 10 June 2022
Number of Submissions 442 objections and 1 support - 395 properly made
PROPERTY DETAILS
Property Address 61 Noosa Springs Drive Noosa Heads Qld 4567
RP Description Lot 4 SP 178340
Land Area 38,055m²
Existing Use of Land Noosa Springs golf club house, tennis courts and day spa
STATUTORY DETAILS
SEQRP Designation Urban Footprint
Zone Tourist Accommodation Zone
Recreation and Open Space
Precinct Not applicable
Local Plan Area Noosa Heads Local Plan Area
Overlays Land Subject to Acid Sulfate Soils
- Above 5 metres AHD to 20m metres AHD
Biodiversity, Waterways and Wetlands Overlay
- Area subject to Biodiversity Overlay
Bushfire Hazard Overlay
- High Potential Bushfire Intensity
- Potential Impact Buffer
Landslide Hazard Overlay
- High Hazard Area
- Moderate Hazard Area
Assessment Type Impact
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 43
REPORT
1. PROPOSAL
It is proposed to develop a hotel that has been designed to be integrated with the Noosa Springs
clubhouse and spa complex, creating a destination with extensive recreation and leisure facilities
The hotel comprises of 106 room 5-star boutique hotel which is to be constructed over 6 levels and
will include (as advised by the applicant):
• A variety of accommodation types:
o 98 standard rooms
o 6 premium suites
o 2 presidential suites
The rooms have generous balconies or terraces and have various orientations and
outlooks. Some rooms have direct access to a resort swimming pool from terraces. The
rooms do not have kitchens or other facilities that would make them self-contained.
• Basement car parking
• Café and bar - An island bar and lounges will provide guests with a place to meet and
socialise. It is located to provide expansive views over the swimming pool and recreation
areas
• Outdoor pool area - The hotel swimming pools and recreation area has been designed to
provide guests with an appealing alternative to the beach. The split level, free form pool is
a central feature of the hotel.
The existing four (4) tennis courts will need to be demolished to locate the hotel buildings. It was
originally proposed to construct new tennis courts near the northern boundary of the site.
However, due to concerns being raised regarding the ecological attributes of this area, the
applicant has relocated the tennis courts above a car parking area. A small amenity building is
proposed near the tennis courts to provide a toilet and other services. The applicant has advised
that the tennis courts and facilities will continue to be used by members upon completion of the
development and the tennis professional will continue to provide tuition to school children and
others.
It is proposed to expand and upgrade the back of house facilities of the Noosa Springs clubhouse
in conjunction with the hotel development. The clubhouse kitchen will operate as the production
kitchen for both the hotel and the clubhouse restaurant and function rooms. The Noosa Springs
restaurant and bar is intended to be upgraded so it can provide high quality, efficient food and
beverage services. The clubhouse restaurant will provide the main dining facilities and services for
hotel guests. A separate development approval already exists for the clubhouse, a future minor
change application will be made to this approval to enable the works.
Access to the site will be via Links Drive with some car parking provided to the north of the proposed
porte cochere and additional car parking provided within a basement and a two-level car park
adjacent to the golf course. Overflow areas are available to the south and north of pavilions 3 and
5 respectively. A loading dock is proposed to be accessed via Resort Drive.
The development generally does not exceed 3 storeys however a minor portion of the building is
4 storeys.
The site is subject to split zoning, approximately 23,447m2 is zoned Tourist Accommodation Zone
whilst the remining 14,608m2 is zoned Recreation and Open Space Zone. The development is
situated across both zones with the built form situated within both zones.
The following images provide a Locality Plan and plans of the proposed development, the proposal
plans are included as Attachment 3.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 44
Figure 1 – Locality
Figure 2 – Site Plan
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 45
Figure 3 – Elevations
Figure 4 – Elevations
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 46
Figure 5 – Development footprint with zones overlaid
2. SITE DETAILS
2.1. Background
Noosa Springs is master planned as a high-quality residential and resort destination that
comprises:
• 299 residential dwellings
• 42 apartments of The Fairways
• 18-hole championship golf course
• Clubhouse complex including restaurant, bars, function rooms, pro shop/retail outlet, day spa,
fitness centre with heated lap pool
• Synthetic grass tennis courts
Parkridge Noosa is located adjacent to Noosa Springs with the majority of the dwelling units able
to be used as either permanent residential living or short-stay accommodation, dwelling units in
the south-eastern corner of the development may only be used for short term accommodation. The
apartments have been strata-titled and separately owned and appear to be mostly occupied on a
permanent basis. There has long been strategic intent for visitor accommodation to be provided at
Noosa Springs. With the development of Parkridge being occupied predominately on a permanent
basis, this site was identified as suitable for visitor accommodation.
2.2. Site Description
The site address is Links Drive, Noosa Heads. The land has a broad frontage to Resort Drive,
Noosa Heads and the development site is part of Lot 4 on SP 178340 comprising 3.804 hectare.
The Noosa Plan zoning map designates part of the land within the Recreation and Open Space
zone (14,608m2) and the balance in the Tourist Accommodation zone (23,447m2).
The proposed hotel site is located on the western slopes of a high sand dune that extends along
the eastern side of the Noosa Springs property. The slope of the ridgeline varies across the site.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 47
2.3. Surrounding Land Uses
Existing related uses are located near the proposed hotel site and include: Noosa Springs Boutique
Hotel. The main clubhouse complex, day spa and the fitness centre (with 25 metre heated lap
swimming pool) are located on lower levels of the ridge. A carpark comprising 3 tiers is located
adjacent to the clubhouse/spa complex. Heavily vegetated vacant land is situated to the north and
east of Resort Drive owned by the Noosa Council. The land on the southern side of Resort Drive
has been developed as Parkridge Noosa.
A sewage treatment plant is located approximately 220 metres from the norther boundary of the
subject site.
3. ASSESSMENT
3.1. Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following
statutory planning instruments to the extent they are relevant to the development:
• State Planning Policy;
• South East Queensland Regional Plan;
• Planning Regulation 2017;
• Noosa Plan 2020.
3.2. State and Other Statutory Instruments
State Planning Policy
Noosa Plan 2020 is generally consistent with the State Planning Policy July 2017 (SPP) and the
SPP raises no further issues relevant to the proposed development.
It is noted that the State interest - emissions and hazardous activities seeks to protect sewage
treatment plants from encroachment by development that would compromise the ability of the
sewage treatment plant to function safely and effectively. As noted in the Odour section of this
report the applicant has demonstrated that the siting of the use is appropriate in context of potential
odour emissions from the sewage treatment plant.
South East Queensland (SEQ) Regional Plan
The site is located within the Urban Footprint of the SEQ Regional Plan. The proposal is consistent
with the regional policies of the SEQ Regional Plan.
Planning Regulation 2017
The following assessment benchmarks from the Planning Regulation 2017 apply to the application:
• Koala Habitat Area
The proposal is for urban activity within the Urban Footprint and is consistent with the assessment
benchmarks contained in the Planning Regulation 2017 for the SEQ Region.
3.3. Statutory Instruments – Planning Scheme
The application must be assessed against the whole of Noosa Plan 2020 to the extent the
provisions are relevant to the development.
Locality Provisions
The subject site is located in the Noosa Heads Local Plan Area and is subject to 2 zones being the
Tourist Accommodation Zone and Recreation and Open Space Zone. The proposed use is
identified as a consistent use within the Tourist Accommodation Zone and an inconsistent use
within the Recreation and Open Space Zone and is required to follow an impact assessable
application process.
The applications compliance and pertinent issues arising out of the assessment are discussed
below:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 48
Use
Under the superseded planning scheme, the full extent of the site was zoned Open Space
Recreation. The Noosa Plan 2020 amended the sites zoning such that it in part preserved the
recreation and open space intent for the site and introduced the Tourist Accommodation Zone to
a significant portion of the site.
The proposed use is a consistent use within the Tourist Accommodation Zone however it is an
inconsistent use within the Recreation and Open Space Zone. The application of split zoning to
the site was to enable to development of tourism accommodation in this area and the boundary
was in response to the need for an odour buffer between future development and the nearby
sewage treatment plant (STP). The purpose of the odour buffer is to ensure that future
development is not adversely impacted by the odour from the STP and that any future development
does not result in complaints to the relevant authority. The existing buffer, which is a result of the
existing split zoning, was a consequence of it not being adequately demonstrated, at that time, that
further encroachment would not result in amenity impacts on guests of a resort. The current
application has included an odour report which has been reviewed by Council’s expert external
consultant, this report and subsequent review has identified suitable areas for development with
regards to potential amenity impacts from the STP. The extent of area demonstrated to be outside
of the buffer area is approximately 28,000m2 which is larger than the existing 23,447m2 of Tourist
Accommodation Zone.
It is noted that the land included in the Recreation and Open Space Zone is outside of the Urban
Boundary. Consequently, part of the proposed hotel is located outside the Urban Boundary. The
entire site was within the Noosa Plan 2006 urban boundary however this boundary was amended
to align with the extent of the Tourist Accommodation Zone when the site became split zoned under
the Noosa Plan 2020. As discussed above, the Tourist Accommodation Zone was established at
the time based on initial information about the potential odour impacts and for the purpose of
creating separation from the STP.
The Urban Boundary, which forms part of the Noosa Plan 2020, is different from the Urban
Footprint, which forms part of the of SEQ Regional Plan mapping. The following image details both
the Urban Boundary and the Urban Footprint.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 49
Figure 6 – Urban Boundary (Noosa Plan 2020) and Urban Footprint (SEQ Regional Plan)
Detailed odour assessment was not done at the time. Notwithstanding, the proposed resort is
consistent with the higher order planning outcomes sought under the Noosa Plan’s Strategic
Framework, the Noosa Plan 2020 specifically sought the development of tourist accommodation
in this part of Noosa Springs by introducing the Tourist Accommodation Zone. At that time the need
for visitor accommodation within Noosa Springs was recognised, primarily on the basis of how the
broader site was being developed with limited visitor accommodation having been provided.
Accordingly, the draft scheme was amended to include the new Tourist Accommodation Zone
and for that area to be within the Urban Boundary. The extent of gross floor area, inclusive of the
proposed resort and the existing buildings on site, is less than what is permitted within the
existing mapped Tourist Accommodation Zone area. A total gross floor area of 10,208m2 is
proposed, the Noosa Plan 2020 permits up to 15,240m2 of gross floor area in the Tourist
Accommodation Zone. In this regard, the scale of development is consistent with the extent of
development anticipated to be developed within the existing Urban Boundary. It is anticipated
that both the zoning and the extent of the Urban Boundary would be amended in the future
should the application be approved.
The proposed Food and Drink Outlet is ancillary to the Resort Complex and will primarily be used
by guests of the hotel. The Noosa Plan’s definition of a Resort Complex includes integrated leisure
activities (….bars, meeting and function facilities, restaurants, sporting and fitness facilities). The
inclusion of these land uses within the Resort Complex is consistent with the anticipated uses
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 50
within a resort complex and establishes a logical connection with the existing resort facilities on
the site.
Odour
An odour report was submitted with the application, the purpose of the report was to determine
the potential for odour impacts on the proposed hotel due to the Noosa Wastewater Treatment
Plant. The development site is located within approximately 220 metres of the STP. The
accommodation buildings are located approximately 270 metres from the existing Noosa STP
infrastructure.
The odour impact assessment report was prepared on the basis of site-specific odour monitoring
conducted at the STP and use of meteorological and dispersion modelling to assess resultant
odour levels at the proposed development site.
The odour assessment adopted the Queensland Odour Guideline odour criterion of 2.5 Odour
Units, 1 hour average, 99.5%ile which is considered the appropriate basis for assessment, and
notably the benchmark considered in Planning and Environment Court appeals. The criterion
requires the prescribed odour concentration to be achieved 99.5% of the time, being measured at
one-hour intervals.
Council’s consulting odour expert reviewed the development application odour report and the
response to information request and considers that the reporting provides adequate assessment
for the purpose of understanding the potential odour impact of the STP upon the proposed
development. The application material has demonstrated the proposed buildings and pool and
communal area between the buildings comply with the odour criterion at all hours of the day. The
swimming pools and tennis courts comply between 6am to 12am and 6am to 10pm respectively.
Conditions establishing times which these areas can be used were proposed by Council’s external
consultant, the times are reflective of the hours which the areas comply with the odour criterion.
The conditions are included within the recommendation of this report.
Comments by Council’s consulting odour expert include:
This further peer review of the odour impact assessments, modelling and information
responses identifies that odour from the Noosa STP does impact upon the proposed
development and that exceedance of the 2.5 OU 1 hour 99.5%ile criterion will occur in
outdoor areas to the North of the proposed accommodation buildings and compliance is just
achieved at the facades of the proposed buildings nearest the STP.
The development is proposed to be located in relatively close proximity to the STP and, on
this basis, appropriate care and consideration is necessary to ensure that future
development does NOT:
(i) Experience excessive odour impact leading to potential complaints; and
(ii) Does not result in an unacceptable reverse amenity constraint upon the existing and
future operation of the WWTP (on the basis of potential odour complaints).
Given that the odour assessment identifies compliance in some outdoor areas (pool,
gardens and tennis court) is not achieved at all times, and that compliance is only achieved
on the basis of limited hours of use of these outdoor areas it is considered appropriate to
limit, by way of conditions, the hours of use (access) of certain outdoor areas to prevent
potential adverse odour experiences and complaints by guests.
Further, as the odour impact assessment identifies that 2.5 Odour Unit, 1 hour 99.5%ile is
predicted just external the façade of the nearest accommodation buildings, it is considered
appropriate to include conditions requiring accommodation use areas be fully air-
conditioned and that outdoor fresh makeup air to the rooms be drawn from locations as
distant from the STP as practical.
The requirement for disclosure of the potential for odour to guests should also be
considered to minimise the potential for complaints about perceived odour.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 51
It is thus our finding that odour impacts upon the development can be acceptable but only
on the basis of limiting hours of use of outdoor areas nearest the STP and provision of
suitable airconditioning to building internal areas with fresh air makeup drawn from
locations as far as practical from the STP. Further, the approval of the development does
increase the reverse amenity constraint upon the lawful operation of the STP due to
introducing additional sensitive receptors in closer proximity to the STP than existing
receptors and it is for this reason that specific conditions relevant to odour are necessary
as part of any development approval.
The suggested conditions are provided below:
Building Design - Ventilation
All internal use areas of the accommodation use including hotel suites, common areas,
office, dining, bar and lobby areas shall be fully airconditioned, allowing external façade
elements (doors and windows) to be closed if required. Fresh air makeup to the
airconditioning systems must be drawn from roof level locations located as far as practical
from the Noosa Wastewater Treatment Plant.
Outdoor Use Areas – swimming pools and tennis courts
Use by guests and visitors of the tennis courts, is limited to the time period 6am to 10pm
only.
Use by guests and visitors of the swimming pools located to the north of the proposed
buildings as identified in Plate 1 (not including the outdoor area between the proposed
buildings) is limited to the time period 6am to 12am only.
On the basis of the reporting provided by the applicant and the recommendations of the review by
the consulting odour expert the potential impacts of odour from the STP have been adequately
addressed in the design of the development. Conditions have been provided which address when
it is appropriate to use external areas, how ventilation is to be provided in those parts of the building
which abut the identified odour line and the implementation of vegetated buffers.
During the assessment of the application advice was sought from Unitywater, noting that
Unitywater are not a referral agency for the application. Unitywater raised the following concerns
with the application:
a. Existing use and surroundings
The existing format of the Noosa Golf and Spa Resort is consistent with the nearby pre-
existing Noosa Sewage Treatment Plant (STP) because it is currently just far enough away
from the facility not to be adversely impacted by the odour of the STP.
Unitywater complies with its licence obligations in respect of the odour management at the
STP. Odour nuisance has not been a concern at this STP with the current configuration of
the Noosa Golf and Spa Resort.
b. Proposed change to use
The proposed material change of use includes a significant increase in the scale of the
Noosa Golf and Spa Resort including outdoor amenities and open-air sporting facilities as
well as restaurants and bars.
The proposed footprint of these proposed new amenity would be within the radium from the
STP where it will be impacted by odour.
The mitigation factors proposed by the Developer do not include any scientifically proven
barrier to odour. Whilst they may improve the visual amenity, they will have no impact on
the odour management.
Further the Katestone modelling performed in 2016 do not take into account the change in
population and development of this areas in the intervening 6 years.
To support this position, we attach:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 52
ii. Memorandum of Unitywater engineer.
iii. Report by Paul King of MWA Environment dated 7 January 2022.
c. Impact on the community
Should the proposed material change of use be approved, the likely impact is that it will
result in an environmental nuisance at a sensitive place under the Environmental
Protection Act 1994 which could result in a prosecution of Unitywater. This will force
environmental studies by Unitywater, and likely very expensive modifications to be made
the Noosa STP which will ultimately be a cost borne by the rate payers of the Noosa
Council through their water bills.
These concerns were provided to both the applicant and the consulting odour expert who
advised:
It is my opinion that the concerns of Unitywater are validly held and that approval of the
development has the potential to result in odour complaints and these may have the
potential to result in constraint upon the operations of the STP. However, this must be
considered in regard of the odour predictions which do show compliance of the built form of
the development with acceptable odour levels (albeit right on the 2.5OU criterion limit). On
the basis that the Katestone predictions are accurate, there would be no basis for a valid
odour complaint from the accommodation building use to affect the lawful operation of the
STP. The Unitywater concerns reinforce my opinion that should Council choose to approve
this development that there need to be very specific conditions in respect to odour
outcomes.
Conditions were provided by Council’s consulting odour expert after this advice was provided to
Council officers.
Subsequent discussions with Unitywater and Council’s consulting odour expert resulted in
Unitywater obtaining a third-party review of the application. The report notes that…the scope of
work is limited to a high-level review of the proposed mitigation measures contained within the
Provided Documents and recommend further mitigation measures that could be considered by
council and/or Proponent, which would aid in further reducing the impact risk of the Proposed
Development encroachment upon the current and future operational and business continuity of
Noosa STP under normal and unintended or unavoidable odour release conditions.
The report states that the most effective further mitigation measure, in terms of risk reduction and
operational and future capital costs to Unitywater and to the community, would be to preserve the
existing exclusion zone (i.e., separation distance). The report also maintains Unitywater’s position
that the odour dispersion modelling is not suitable for the prediction of unintended or unavoidable
odour release events, for example, sewerage network asset breakdown, significant rainfall,
heatwaves, process upsets, biosolids truck loading events, etc.
It is also noted that the report identifies that in the scenario that the proposed development is
approved, the author of the report supports in principle the odour mitigation measures proposed in
the suggested conditions of Council’s consulting odour expert.
In addition, Unitywater’s consultant recommends further mitigation measures in the form of:
• To the extent that is reasonable, an encumbrance or similar that transfers all responsibility of
STP-related odour complaints from Unitywater to the Proponent and is sanctioned by Council
and DES. Professional advice from a town planning or environmental law expert should be
consulted on this matter. Based on the sentiment in the letter by GH Australia, the Proponent
could be willing to enter such an arrangement;
• Activated carbon filtration to be installed on all fresh air makeup locations of the air
conditioning systems and are regularly maintained to manufacturer specifications; and
• To the extent that is reasonable, that the layout of structures is designed to avoid entrapment
of odour plumes. TOU are concerned that the northward facing concave layout of
accommodation structures is conducive to entrapment of STP odour plumes from the north.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 53
In review of report prepared by Unitywater’s consultant Council’s consulting odour expert advises
the operation of the sewage treatment plan is regulated by an Environmental Authority, issued by
Department of Environment and Science, which requires that the onus is on the operation to not
cause nuisance/harm from odour emissions. This applies at all times whether it be normal
operating conditions or the upset conditions, being the unintended and unavoidable odour relates
events which Unitywater’s consultant refers to. Furthermore, Council’s consulting expert notes that
existing residential uses at Noosa Springs, situated west of the STP are within proximity of the
2.5OU line whilst the existing outdoor recreation areas of the resort, including the existing tennis
courts, would experience odour concentrations above 2.5 OU. Thus, existing approved and
developed areas are already a constraint on the STP operation. It is also noted that Unity Water
have advised that they have no record of odour complaints from these current uses.
In terms of the comments by Unitywater’s consultant regarding the suitability of methodology used
by the applicant’s odour expert Council’s consulting expert states:
The use of modelling of odour from STP is an accepted practice for both development
assessment at the Local Government level and in the Planning and Environment Court.
Typically, the assessment is based upon normal worst case emissions not Upset conditions
(unintended or unavoidable odour emission conditions).
Whilst there are uncertainties in any form of assessment and modelling, it is a tool for
assessment purposes which informs the assessment manager of potential impacts.
In respect to independent ground truth verification – I assume the author is identifying the
use of field odour surveys which are manned inspections by persons with a laboratory verified
sense of smell that are used to characterize odour ie in terms of intensity and offensiveness.
The use of field odour surveys can inform and provide validation points for modelling.
In this instance there are existing residential uses and the Noosa Springs facility and outdoor
uses which are currently occupied and used and there does not appear to be a complaint
history in respect to odour which supports the modelling outcomes. Even if field odour testing
was conducted it does not guarantee any improved odour prediction/assessment outcome
in my opinion.
I have been involved in matters where modelling of upset conditions has been undertaken in
respect of STP operation. However, the reliance upon odour from upset conditions in
informing development assessment against the 2.5 OU 99.5%ile 1 hour criterion is in my
opinion very limited. This is because the 99.5%ile allows for periods of higher odour to occur
ie it is not absolute and the Environmental Authority requirement to not cause odour
nuisance/harm is in play at all times.
I understand the STP operator desire to maintain buffer separations, but this must be
considered on the basis of existing land uses and proximity of existing sensitive uses to the
STP which, as per above, already exist.
Further, it is my opinion that a short stay resort development has far less reverse amenity
constraint potential than standard residential uses.
In terms of the proposed additional mitigation measures proposed by Unitywater’s consultant:
• Legal advice has been obtained and it has been determined that an encumbrance or
similar that transfers all responsibility of STP-related odour complaints from Unitywater to
the proponent is too uncertain and potentially against public policy resulting in a deed of
agreement that is void, unenforceable and ineffective.
• Agreed that activated carbon filters to fresh air makeup locations can be required to further
protect indoor air quality.
• A major redesign of the development is not warranted.
The applicant’s odour expert also reviewed the Unitywater’s consultant’s comments and forms a
similar view to Council’s consulting expert, however, opposes the recommendation that activated
carbon filters be installed. The opposition to the carbon filters is on the basis that the applicant’s
proposal for fresh air makeup to the air conditioning systems must be drawn from roof level
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 54
locations located as far as practical from the STP” is sufficient to avoid odorous air being drawn
into the buildings. The applicant’s expert suggests that an additional measure to address concerns
regarding odour could be the imposition of a condition requiring an Odour Complaint Management
Plan, with the applicant’s stated intention to manage any odour complaints from hotel guests within
the business being central to the plan.
Based on the advice provided by Council’s consulting odour expert the applicant has adequately
demonstrated that the proposed development is suitable when considering the potential odour risk.
The consultants suggested conditions and the inclusion of carbon filters as suggested by
Unitywater’s odour expert are supported and form part of the recommendation. It is also
recommended that an Odour Complaint Management Plan be conditioned.
Traffic/car parking
The applicant provided traffic reports which reviewed the traffic and car parking demand associated
with the proposed 106 bedroom resort These reports, and subsequent responses to requests for
further information, were reviewed by Council’s consulting traffic engineer.
Much of the discussion in the review of the car parking analysis related to the methodology
determining car parking demand. Council’s traffic consultant undertook an assessment based on:
i. Adopt a design parking demand for the existing development of 160 cars based on the 2017
surveys.
ii. The RFI response indicates the hotel will have 44 EFT staff. Assuming 2/3rds of those travel
by their own car to/from work, this would generate 30 cars.
iii. Assuming half of the 112 resort rooms have a car on-site at midday would generate a
demand for 56 cars.
iv. Based on the above, the design parking demand would be 246 cars, which would be
accommodated by the proposed 255 parking spaces.
As per the comments above Council’s consulting traffic engineer is supportive of the proposed 255
formalised car parking spaces. In addition to the proposed formalised 255 car parking spaces the
applicant has also identified an additional 38 grassed overflow spaces.
The 255 formalised spaces include a 2-storey deck carpark situated adjacent to the western
boundary of the subject site whereby an additional storey of car parking is to be provided above
part of the existing at grade car park. The location of this deck car park is detailed in the following
images with the built form considerations discussed within the setback section of the report.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 55
Figure 7: Location of deck car park on plan
Figure 8: Location of deck car park on aerial
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 56
It is also noted that conditions of the SARA referral response also require the provision of a bus
setdown facility as part of the porte cochere.
Bushfire
The site is identified by the Noosa Plan 2020 Bushfire Hazard Overlay Map as ‘High Potential
Bushfire Intensity’ over the vegetation within the north and east of the site, and ‘Potential Impact
buffer over the balance of the site (Figure 9). This is mirrored by the State Planning Policy (SPP)
‘Bushfire Hazard Aea’ mapping (Figure 10).
Figure 9: Bushfire Hazard Overlay mapping (Noosa Plan 2020)
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 57
Figure 10: Bushfire Hazard Area mapping (State Planning Policy)
The applicant’s consulting fire expert has inspected the site to identify the status of the vegetation
within and around the development site and determine the likelihood of bushfire risk to the
development. This inspection confirmed the area of vegetation within the northern portion and
along the north-eastern boundary of the subject site is an area of ‘High Potential Bushfire Intensity’
as determined by both the Noosa Plan and SPP – Natural hazards risk and resilience bushfire
hazard area mapping.
The inspection also concluded that the area of vegetation in and surrounding Girraween Nature
Refuge is confirmed to be an area of ‘High Potential Bushfire Intensity’ and that the development
would fall within the 100 metre wide potential impact buffer. As a result, the development is required
to address the Noosa Planning Scheme Bushire Overlay code through the preparation of a bushfire
hazard assessment and mitigation plan.
The application material has included a Bushfire Hazard Assessment and mitigation plan (BHA), a
revised BHA was also submitted. These documents have been prepared in accordance with PSP8
Natural Hazards (SC6.9.4 Bushfire hazard assessment report and management plan) and the
Bushfire Resilient Communities (Technical reference guide for the state planning policy state
interest ‘natural hazards, risk and resilience – Bushfire’).
The vegetation associated with the ‘High Potential Bushfire Intensity’ was confirmed as Category
A or B, Regional Ecosystem 12.2.5, with significant disturbance to the mid and understory layers,
being invaded and colonised by a range of environmental weed species.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 58
Adjacent to the existing car parking area and tennis courts is a line of disturbed vegetation
containing a range of native canopy species with a low coverage of ground covers with areas
containing a range of exotic and native amenity shrubs.
The bushfire assessment found that the risk associated with bushfire was from outside the
proposed development area i.e. Girraween Nature Reserve to the north and east. Resort Drive
forms a natural firebreak that would be sufficient to buffer most ground fires, however a significant
bushfire involving Girraween Nature Reserve on a high fire danger day with an easterly wind has
the potential to cross Resort Drive and involve the vegetation within the subject site.
The report determined that a fire within the site, particularly involving the vegetation associated
with the northern and eastern boundary would be of low intensity and burn up the dominant slope
away from any of the existing infrastructure.
In response to the bushfire risk, the proposal has included a range of mitigation measures along
the northern and eastern boundary to reduce risk to people and property. This includes separation
distance from mapped hazardous vegetation that achieves a radiant heat flux of less than
29kW/m2. To achieve this outcome the development footprint along the northern and north-eastern
boundary must meet a minimum separation of 15.7 metres.
The below image, which is taken from the applicant’s BHA, indicates that Pavilion 5 achieves
24.465 metres and 21.965 metres at the ends of the building closest to the hazardous vegetation
which will achieve a radiant heat flux with 19-29kW/m2.
Figure 11: Proximity of pavilion 5 to hazardous vegetation
The building is separated from the northern hazardous vegetation via the proposed overflow
carpark which is approximately 35 metres in length. 35 metres will achieve a radiant heat flux of
12.5kW/m2.
The BHA has provided a range of comments and recommendations to reduce risk on the
infrastructure and users within the site. These include:
• Hazardous vegetation retained in proximity to the development is separated by Resort
Drive, tennis courts and auxiliary parking to provide a buffer between hazardous vegetation
and the proposed structures.
• A minimum setback between future habitable structures and the edge of potential
hazardous vegetation is 15.7 metres which achieves a radiant heat flux of less than
29kW/m2 and as such an acceptable level of risk achieved as defined under the State
Planning Policy, Natural Hazards, Risk and resilience.
• Landscaping within the site to utilise species considered to be less flammable where
rehabilitation is required to match the existing 12.2.5 Regional Ecosystem.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 59
• Landscape cannot contain flammable plant species to the north of the hotel abutting Resort
Drive (except for Non juvenile koala habitat trees).
• Non juvenile koala habitat trees to the north of the development can remain in situ with a
maintained understory required to reduce the bushfire risk.
• No less than 5 metres adjacent the eastern side of the hotel units identified on the
landscape concept plans must be turf only. This is to be extended to include all building
with an eastern aspect as detailed in the below image.
Figure 12: Area of 5 metres of turf only
• The use of less flammable plant species should comprise of a minimum 70% of all ground
covers and understory within the landscape area.
• Improvements to the resort drive verge including removal of vegetation from along the road
edges to improve sight lines and impacts of vegetation with emergency response vehicles.
(See General comments)
• The development be connected to reticulated water, with sign off from a hydraulic
engineering consultant that there is capacity to meet potential needs should a structural /
vegetation fire threaten the site.
• Sufficient hydrants standpipes or inground hydrants located within and around the facility to
ensure compliance with the relevant guidelines and standards.
• An emergency response plan including evacuation plan to provide a set of responses
should a vegetation fire involve adjacent vegetation and visitors, or staff need to be
relocated to ensure they are safe until the fire is brought under control by authorities. This
could involve:
o Evacuation on the golf course
o Evacuation behind buildings with fire safety standards
o Within the hotel reception area for further instruction
Water Supply
The development is serviced by reticulated water, with sufficient hydrant standpipes or in ground
hydrants located within and around the development site safely located and freely accessible.
Further sign off from a hydraulic engineer to ensure appropriate capacity to meet potential needs
in an emergency can form reasonable conditions where an approval is granted. See below current
hydrant locations within the site and within the Resort Drive Road Reserve.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 60
Figure 13: Location of fire hydrants (blue dots)
Evacuation
The Bushfire Resilient Communities (Technical reference guide for the state planning policy state
interest ‘natural hazards, risk and resilience – Bushfire’) provides advice regarding assembly and
evacuation. Where a planning scheme contains an assessment benchmark for the provision of a
safe assembly or evacuation area, a development condition may articulate how this could be
achieved.
A safe assembly or evacuation area may be a suitable alternative to an evacuation route, where
the site is in an isolated location, and any evacuation route would be long or pass through the
bushfire prone area. A safe assembly or evacuation area would involve:
• Establishing the safe assembly or evacuation area within the development site and outside
the identified bushfire prone area.
• Direct route/s to the designated area designed to ensure:
o Roads have sufficient capacity for the evacuating population.
o Occupants are directed away from, rather than towards or through areas with a greater
potential bushfire intensity.
o Minimising the length of route through bushfire prone areas
o Compliance with AS 3745-2010 Planning for emergencies in facilities where it is
deemed appropriate for isolated developments.
According to the BHA, an emergency response plan and evacuation plan is to be made available
to help guide a series of actions in the event of a vegetation fire involving nearby vegetation,
visitors, or staff, and the need to locate them to ensure their safety until the fire brought under
control by the appropriate authorities. An evacuation plan has been provided; the plan involves
evacuation to the existing country club.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 61
Figure 14: Proposed evacuation route
The applicant’s BHA has been reviewed by a consulting bushfire expert and Council’s Senior
Environment Officer. Review of the BHA identifies that a suitable methodology has been utilised
and that the proposed recommendations are supported. A condition requiring the establishment of
an additional safe evacuation point on the golf course, off site, away from buildings and outside
the identified bushfire prone area is recommended.
The review also identified that the Emergency Response Plan does not include any evidence of
involving the Queensland Fire and Emergency Services (QFES) in the preparation or that they
support the proposed solution. However, it is not common practise for QFES to be involved in the
preparation or review of a BHA or Emergency Response Plan.
Further communication with the consultant who provided the review stated via email ‘I do not think
that no involvement of the QFES in the preparation and endorsement of the emergency response
plan is problematic. The plan includes relevant elements recommended by the New South Wales
Rural Fire Service in Development Planning - A guide to developing a Bushfire Emergency
Management and Evacuation Plan (2014) and I accept the proposed measures within the plan’.
Standard bushfire conditions of approval will require that the bushfire hazard assessment /
mitigation plan as well as evacuation plan for the development must be provided to the nearest fire
authority.
Biodiversity, Waterways and Wetlands Overlay
The purpose and outcomes of the Biodiversity, Waterways and Wetlands overlay code is to protect,
rehabilitate and enhance ecologically important areas and improve connectivity. The development
site is mapped under the Noosa Plan 2020 as having environmental values including, ‘Area of
Biodiversity Significance’ located in the north and along the eastern boundary.
The very northern patch of vegetation is mapped as ‘MSES Environmental Values’ and ‘State
Koala Habitat Area (KHA)/Remnant Vegetation. States Regulated Vegetation Management Map
identified remnant regional ecosystem RE12.2.5 located in the small patch on the north section
(Corymbia intermedia +/- Lophostemon confertus +/- Banksia spp. +/- Callitris columellaris open
forest on beach ridges usually in southern half of bioregion) and also RE12.2.5 as essential habitat
for three frogs (acid frogs), the glossy black-cockatoo, the koala and a wattle species (Acacia
attenuate).
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 62
Figure 15: Extent of biodiversity overlay
The submitted Terrestrial Ecology Assessment (TEA) identified that the state mapped REs are
consistent with what is actually located within the area. The TEA further detailed that both indirect
and direct impacts are likely to occur as a result of the development. Indirect being edge effects
such as weed invasion and fragmentation and direct being the loss of trees and fauna habitat. It
is identified that vegetation and individual trees generally along the northern and eastern
boundary will be retained.
The site is not mapped as a Koala Priority Area but a small area in the north is mapped as Koala
Habitat (Core) extending from the bushland north of the road. The previous version of plans
submitted for assessment resulted in the removal of 19 Non-Juvenile Koala Habitat Trees (NJKHT)
in an ‘isolated pocket’ to the north and close to Resort Drive. The plans were subsequently
amended to re-locate the tennis courts which has allowed for the retention of these trees.
The following image details the location of the NJKHT which were proposed to be removed.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 63
Figure 16: Tree removal within mapped koala habitat area
Re-locating the tennis courts above the existing car park results in the preservation of the 19
NJKHT, these trees are in the area identified as containing MSES values. Whilst some
vegetation within the Biodiversity Overlay will be removed, in areas adjacent the eastern
elevation of Pavilions 5 and 4 there will also be some vegetation retained in this area with the
vegetation in the roadside reserve retained and enhanced.
The retention of the non-juvenile Koala Habitat Trees, where a managed understory is maintained,
does not result in an unacceptable bushfire risk. It is proposed that this area be used as an
environmental, passive leisure and recreational walking area. The following additional
recommendations from the BHA are included within the landscaping conditions:
• Landscape planting should reflect the adjacent regional ecosystem and coastal vegetation
without increasing bushfire hazards.
• Mature trees are to remain in situ, with the understory to be maintained as a low bushfire
hazard are with lower flammability species only
• All weed species to be removed throughout the hotel grounds, with the exception of
landscape amenity specimens around existing structures
• Highly flammable native species such as bracken fern and blady grass to be managed so
that they are not dominant in this area
• A list of lower flammability species, specific to this site, is to be utilised to enhance the
environmental amenity through the low hazard areas.
• Regular maintenance around residential structures is to be maintained within the vegetation
to the north to the current standard and frequency of other areas around the resort and
residential areas.
Landscaping
The application material included an assessment of adherence to the Landscaping Codes
performance outcomes and a Landscaping Concept Design Package. The application generally
meets all performance outcomes as it will sit within the natural landscape and retains a significant
amount of native vegetation whilst enhancing the environment with rehabilitation, landscape
planting and weed management. The planting pallet chosen includes native and endemic species.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 64
The landscaping has been designed to meet bushfire requirements including specific low
flammability planting within higher risk areas.
As identified above within the bushfire section the landscape concept plan is required to be
amended to include an additional section that includes the 5m turfed area to ensure bushfire safety.
The proposed landscaping is supported subject to relevant conditions.
Voluntary Offset
The applicant has proposed to offset the loss of vegetation with the offset planting to occur in 2
locations on the golf course Offset Areas A and B). It is proposed to plant 120 koala habitat tree
(eg. E.tereticornis or similar) and 25 she-oaks (glossy black cockatoo feed trees).
The proposed offset areas are detailed in the following image.
Figure 17 – Proposed offset areas.
Offset area A will not significantly increase the bushfire hazards within the area and as such will
not increase the bushfire risk to the adjacent people and properties within ‘The Fairways’ residential
estate. This is due to maintained areas of the community tile scheme that will buffer the offset area
and be continuously maintained. Further to this the bushfire consultant has provided additional
recommendations to be undertaken within Offset area A:
• No additional plantings be undertaken within 30 metres of an existing structure within the
Fairways CTS
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 65
• A fire management line and access track are located between the bunker on the eastern side
of the fairway 1 near the fairway 1 green and the southern most residential structure within
the fairways CTS area
• The existing informal access track is to be maintained in its current location with a width of 6-
8 metres.
• The augmentation of the current vegetation be undertaken to the north of the access track.
The proposed offset area B will not present a bushfire risk to any infrastructure within and around
the existing Noosa Springs Development, due to the existence of highly maintained grassland
along fairway 3 and the driving range as well as a dam or water feature separating residential
dwellings to the west of the golf course fairway 3.
Water quality/quantity
Due to the topography of the site, it is possible to drain the development areas entirely through the
Golf course and to Weyba Creek without impacting any other properties or public infrastructure.
Bioretention devices are proposed for each of the new car parks and roof areas. The surface
areas for the bioretention devices are approximately 1% of the contributing catchment areas,
which is in-line with expectations. The bioretention areas treating roofwater are lower due to the
influence of the roofwater tanks which capture roofwater for reuse. The applicant has provided
135kL of rainwater tanks.
The application material has been reviewed by Council’s consulting hydraulic engineer who is
satisfied with the proposed outcomes. Conditions are provided.
Built form
The building design, including external materials and colours, is consistent with the Noosa Springs
architectural style and is designed to complement the adjacent clubhouse and spa buildings. The
buildings appear generally as only two-storey structures from Resort Drive.
The built form is considered to comply with the Noosa Plan for the following reasons:
• The proposed development incorporates soft landscaping between and around the
building, near the road frontages and around the central lagoon pool and open space area
and around the tennis courts and new carpark areas
• The proposed development respects the scale of surrounding vegetation being below the
tree line and provides for the retention of some vegetation where possible, generally
around the perimeter of the site
• The proposed development takes the form of five smaller separate building forms rather
than a large single bulky building. Further, steps down the slope and will not visually
dominate the nearby properties (see figures 18 and 19 below for photo montage of the
proposed development from adjoining golf course)
• The proposed development, through its design and siting, reinforces the correlation
between the natural and built character of the area by being responsive to the topography
• The proposed development is of a high design quality, incorporating landscape design that
emphasises the casual, outdoor lifestyle.
• The proposed buildings have a strong relationship with the outdoors through the
incorporation of natural materials, verandahs and glazing and orientation of openings
towards public spaces where practicable.
• The proposed buildings and structures have articulated roof forms which are visible from
the street. They incorporate a mix of lightweight and textured external building materials,
provide for variation through articulation, texture, and detailing. They incorporate verandah
and open balconies and shaded areas for outdoor living, with open, transparent, or semi-
open balustrades. The design makes use of understated colour schemes and low reflective
roofing and building materials that integrate with the existing Noosa Springs built form and
character and is consistent with the existing Noosa Springs Golf and Spa Resort facilities.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 66
• The applicant has provided a series of montages which address the views of the
development from the residential properties in Noosa Springs to the west of the subject
site. The photomontages demonstrate that the development sits within the existing tree line
and will be less prominent than the Parkridge development. The following images are some
of the montages that have been provided by the applicant.
Figure 18 – Photo montage of proposed development from golf course.
Figure 19 – Photo montage of proposed development from golf course, buildings above the tree line are
Parkridge.
Tennis Courts
Four tennis courts are currently located on the site, it was originally proposed to relocate the tennis
courts within an area that is subject to the Biodiversity, Waterways and Wetlands Overlay. Due to
concerns with the proposed loss of non-juvenile koala habitat trees the tennis courts have been
re-located so that they are situated above the existing north-western car park. The location of the
tennis courts is detailed in the following image:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 67
Figure 20 – Location of tennis courts
Figure 21 – Tennis court plans
Like the existing courts the proposed courts are located on two different levels, with 2 lower
courts and 2 upper courts. The bases of the existing tennis courts are at RL 25.5 and 27,
reflective of the split level on which they are also located. The top of the existing fencing and light
poles are significantly higher. The top of the fence of the proposed upper-level courts is at RL
26.2.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 68
The courts are setback at least 15.6 metres from Resort Drive and will be partially screen by the
existing vegetation within the road reserve and on the site. The visibility of the courts will be at its
greatest on the southern side of the roundabout at the intersection of Resort Drive and Links
Drive, essentially being within the resort site. Notwithstanding the bulk attributed to the tennis
courts will be limited noting tennis court fencing is a mesh style fence that is transparent, it is
recommended that a condition be included to detail the type of fencing and for the colour to be
black.
Whilst the tennis courts are elevated, they remain below the Recreation and Open Space zone 8
metre height limit with the exception the light poles, noting that 2 of the courts are located within
the Tourist Accommodation Zone which has a height limit of 12 metres. The plans include 9
metre light poles which range in height from 9.25 metres up to 12.67 metres above the existing
ground level The applicant has agreed to reduce the height poles by at least one metre which is
reflected in a condition within the recommendation.
The light poles will have a narrow form and will not be visually obtrusive and are infrastructure
that is expected to be associated with the tennis courts. The existing courts also include lighting,
the proposed lights will sit significantly lower than the existing lights. Conditions are also
recommended in relation to the tennis court lighting to limit the hours of operation and ensure
that the lights are baffled so that they do not result in amenity impacts.
Acoustic
A loading dock and a 5000 litre in ground grease trap are located within 25 metres of a residential
building within the Parkridge development. The size of the adjacent vehicle turnaround area
suggests that trucks are meant to access this area, specifically pump out trucks for the
interceptor. Whilst the applicant proposes to limit access to this area to the hours of 7am to 6pm
this does not necessarily prevent adverse noise impacts to the dwelling units to the southeast. A
second loading dock is located to the rear of the existing resort facilities building, this is situated
approximately 60 metres from the nearest residential building. It is anticipated that additional
measures may be required to ensure the protection of the amenity to the nearby dwellings.
Accordingly, a condition has been included requiring an updated acoustic report to assess the
potential noise impacts of these loading with recommendations to be implemented within the
development.
Site Cover and Plot Ratio
The subject site includes an area of 23,447m2 that is zoned Tourist Accommodation. The balance
of the site is zoned Recreation and Open Space Zone (14,608m2).
The Tourist Accommodation zone code requires a maximum site cover of 40% (9,378m2) and a
Plot ratio of 0.65:1(15,240m2). The Recreation and Open Space Zone requires a maximum site
cover of 10% (1,460m2) whilst there is no numerical requirement for Plot ratio.
The total site cover of all buildings on the site (including that zoned Recreation and Open Space)
is:
• Existing club house -1,839m2
• Existing day spa & gymnasium -1,308m2
• New Hotel – 3,670m2
• Tennis Courts – 2,505m2
• Carparking – 1,234m2
The total gross floor area of all buildings on the site (including that zoned Recreation and Open
Space) is:
• Proposed Hotel facilities - 6,862m2
• Existing day spa - 1,241m2
• Existing clubhouse - approximately 2,000m2 + 105m2 proposed as part of future change.
The following table details the proposal’s compliance with site cover and plot ratio.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 69
Tourist Accommodation Zone Proposed Complies
Site cover Tourist Accommodation Zone 6,817m2 Yes
9,378m2 permitted
Including car park and
Recreation and Open Space Zone tennis courts: 10,556m2
1,460m2 permitted
Total permitted: 10,838m2
Plot ratio Tourist Accommodation Zone 10,208m2 Yes
15,240m2 permitted
The proposal complies with the scheme requirements for both site cover and plot ratio as the
buildings are below the prescribed requirements when considering the site as a whole. It is
acknowledged that the extent of site cover does not comply within the existing mapped Recreation
and Open Space zone when considered in isolation however, the building and structures do not
detrimentally reduce the useability of open space or dominate the site. It is noted that the existing
land zoning was not based on detail odour assessment at the time, with the current application
ground truthing the appropriate area for the tourist accommodation use to occur. It is noted that
the extent of plot ratio does not exceed the amount permitted under the Tourist Accommodation
Zone. On this basis it is considered that the site cover and plot ratio are appropriate for the overall
site.
Building Height
The Tourist Accommodation zone has a maximum building height of three storeys. The proposed
development ranges in 2 storeys and 3 storeys with basement levels across the site, a small
section is 4 storeys where the basement car park is not backfilled. The maximum height
requirement of 12m is exceeded at the lower part of the site where the central part of the roof and
lift shaft range from 12.19 to 12.95m from natural ground level, the part of the building where the
basement is not backfilled is 14m above finished ground level.
The Recreation and Open Space Zone has a maximum height requirement of 8 metres. Most of
the built form within the Recreation and Open Space Zone does not exceed 8 metres. The
maximum height of the building within the Recreation and Open Space Zone ranges from 11.1m
to 12m above natural ground level.
The following image details those part which exceed 8 metres and 12 metres respectively, the
yellow area is the Recreation and Open Space Zone with the red area being the Tourist
Accommodation Zone, the building is identified in light blue in the areas which it exceeds the
relative height limits of these zones.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 70
Figure 22 - Extrapolated 8m (yellow) and 12m (red) above Natural Ground Plane
Despite this part of the building not complying with the 8m and 12m height requirements the
development is considered to comply with the corresponding Performance Outcomes as:
• The site is characterised by slope which rises approximately 15 metres from the western to
the eastern boundary of the site. The large footprint of the buildings, which is attributed to
their intended use, results in the development exceeding the height limit where the buildings
extend down the slope.
• The buildings are consistent with the expected height and scale for the purpose which they
are intended to be used.
• The development takes the form of 5 separate ‘pavilions’ which has allowed the development
to progressively step down the site, accordingly reasonable efforts have been made in the
design of the development to minimise the height impacts.
• The maximum exceedance of the height requirements generally relates to the ridgeline of
different buildings with the extent of exceedance less in other parts of the building where the
roof line pitches towards to the ground level.
• The exceedance in height is generally limited to the roof plane.
• The height of the development is generally consistent with the Parkridge Noosa development
which was also permitted height variations in recognition of the scale of the built form and the
similar topography.
• The areas of exceedance are located centrally on the site and will not visually dominate the
street or surrounding areas generally presenting generally as two storeys to Resort Drive;
o will preserve the amenity of surrounding premises including privacy, views, and access
to sunlight; Noosa Springs Boutique Hotel
o will respect the scale of any nearby vegetation by maintaining a vegetated skyline.
Earthworks
The Tourist Accommodation Zone includes an acceptable outcome which seeks to limit cut and fill
to a maximum of 1.5 metres. The site contains existing retaining walls and terraced platforms
supporting tennis courts and ancillary structures, with the remainder of the site containing a slope
which runs from Resort Dive to the golf course. The application material notes that additional
earthworks cut, fill and retaining will be required to construct proposed building pads, pools and
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 71
car parking areas. The extent of earthworks will exceed the 1.5 metre acceptable outcome, the
extent of works is a consequence of the existing benching and slope of the site, the large footprint
of the building and the depths required to facilitate basement levels. The earthworks are to be
generally located in the proposed building footprint and will not impact on landscape amenity
outcomes that are to be achieved through future landscaping. Furthermore, the natural landform
of the site has already been significantly disturbed through benching for the existing car parks,
access roads and tennis courts The earthworks will be further regulated through an Operational
Works application which will ensure that there is no erosion or sediment runoff from the site.
Setbacks
The proposed development complies with the acceptable solutions for setback requirements
except for the eastern elevation of the proposed resort, the two-level carpark and one of the tennis
courts.
The eastern elevation of the proposed resort is setback between 7.5 metres and 17 metres in lieu
of the 20 metre requirement within the Recreation and Open Space Zone. Whilst the buildings are
located within the Recreation and Open Space Zone it is acknowledged that the suitable
developable area would be determined through a ground-truthing exercise relating to the required
odour buffer setback. In this regard, the proposed setbacks comply with the setback requirements
for the Tourist Accommodation Zone. Furthermore, the road reserve is well vegetated with a
recommended condition requiring vegetation in the road reserve to be enhanced. Some of the
existing screening vegetation within this part of the site will also be retained with the areas outside
of the 5 metre turfed bushfire setback to be enhanced with further planting. The existing and future
landscaped vegetation will assist in filtering views of the built form. The proposed setbacks will not
be inconsistent with the predominant character of the surrounding area, noting the close proximity
of the Parkridge development to this part of the site.
The two-level car park includes an open sided shade structure which is approximately 7.8m high
and is setback 0m in lieu of 2.5m from the boundary (see figure 23 below)
Figure 23 – elevated carparking located on the western side boundary.
The 0m setback is consistent with the existing carparking area that is currently located adjacent
to the boundary. The adjoining land to the west (golf course) is heavily vegetated and will buffer
the built form of the car park when viewed from the golf course. The car park will only be seen by
persons utilising the resort and the associated facilities. Furthermore, the setback variation
relates to an internal boundary for 2 lots which are unable to be sold separately due to an
existing covenant restriction on the titles.
With regards to the tennis courts, the Recreation and Open Space Zone requires a 20 metre
setback to the front boundary (Resort Drive) and 4.5 metres from an internal road (Links Drive).
The tennis courts within this zone are setback between 15.6 metres and 28.5 metres, with the
majority of the tennis courts being in excess of 20 metres. One of the courts is located adjacent to
the Links Drive boundary above the existing car park, which is built to the boundary.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 72
Like the two-level car park the siting of one of the tennis courts adjacent to the Links Drive setback
will generally only be perceptible to those persons utilising the resort facilities, noting the significant
setbacks to Resort Drive. As per the below image the area within the adjoining road reserve
contains vegetation which will filter views of the tennis court whilst noting that the area currently
contains a car park.
Figure 24 – view from Links Drive towards elevated tennis courts.
Taking this into consideration the boundary setbacks can be supported on the following grounds:
• The location of the areas for which the reduced setbacks are sought internal to the Noosa
Springs site do not impact on the public realm, residential character or amenity or the
streetscape.
• The reduced setbacks will not obstruct views or cause overlooking of private open space or
habitable areas of adjoining premises.
• The reduced setbacks will provide a high level of amenity to users of the subject site.
• The tennis courts are located above existing car parks.
• Re-siting the tennis courts has enabled the retention of vegetation containing MSES values
and maintains the provision of 4 x tennis courts.
4. CONSULTATION
4.1. Referral Agencies
The application was referred to the following Referral Agencies:
• Department of State Development, Infrastructure, Local Government and Planning (SARA)
The Department is a referral agency for:
• Schedule 10, Part 10, Division 3, Subdivision 3, Table 1, Item 1— Koala habitat area in
SEQ region
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 73
• Schedule 10, Part 9, Division 4, Subdivision 1, Table 1, Item 1— Development impacting
on State transport infrastructure
The Department has responded advising that it does not object to the application subject to
conditions, including conditions relating to:
• Retention of native vegetation within the Koala Habitat Area
• Pedestrian connectivity from the porte cochere to the hotel reception
• Provision of a bus setdown facility as part of the porte cochere
4.2. Internal Council Referrals
The application was forwarded to the following internal Council officers:
• Senior Environment Officer
• Coordinator Development Engineering
4.3. Other Referrals
The application was forwarded to the following external experts for review and/or comment
• Bushfire
• Hydraulic Engineer
• Traffic consultant
4.4. Public Notification
The application was publicly notified for fifteen (15) business days in accordance with the Planning
Act 2016. 395 properly made submissions were received, all objecting to the application. The
following table provides a summary and assessment of the issues raised by submitters.
Matters Raised Comments
Traffic flow/carparking A traffic report was provided by the applicant
which has been amended in response to review
Existing car park is not adequate
by Council’s consulting traffic engineer. The
Resort Drive too narrow application has been amended since the
Impact of delivery and refuse vehicles application was notified with additional car parking
being provided. Council’s consulting traffic
Build an access road off the entry engineer supports the proposed car parking and
roundabout to Noosa Springs directly access arrangements for all vehicles.
onto Eenie Creek Road to enable safe &
quick exit. That would be expensive but The application was also referred to SARA with
should be an expense imposed on the the referral related to the impact of the
developer. development on state transport infrastructure.
SARA has provided conditions which include the
requirement for a setdown facility for a bus of
14.5m in length.
Where will construction vehicles be Future operational works approvals will include
located the requirement for a construction management
plan which will address the parking of construction
vehicles.
Noise – pool The pool is located approximately 100 metres
from the nearest dwelling with the hotel pavilions
being situated between the pool and this dwelling.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 74
It is over height The proposed development is permitted to have a
maximum height of 12 metres, where located in
Extent of height exceedance is excessive
the Tourist Accommodation Zone and 8 metres
and will impact of views of Parkridge
where located within the Recreation and Open
development’
Space Zone. Whilst the development does exceed
12 metre height will overpower existing the permitted height limits this is largely due to the
buildings sloping topography of the land and the scale of
Building height of 12 metres, will adversely buildings required to provide the intended use.
impact the scenic amenity of the area, The height variations are generally located
particularly when viewed from the north. internal to the subject site with the subject site
itself being within a golf resort, as such the height
The visual impact at the SW corner will be variations will not impact on streetscape or
astonishing. The building presents a five- adjoining properties.
storey development in the south west
corner
The development sits awkwardly with an
enormous scale imbalance between itself
and the existing resort buildings.
Reduced availability of tennis courts Since the application was notified the number of
tennis courts has been increased by 3 to 4 to
Reduction in number of tennis courts (4 to
maintain the status quo.
3)
It is acknowledged that there will be increased
demand for the tennis courts noting that the courts
are a private and not a public facility.
Weak on environmental and energy The application material included a terrestrial
efficiency aspects ecology assessment which was reviewed by
Council’s Senior Environment Officer with the
application also being referred to SARA to assess
the removal of koala habitat.
A sustainable building design report was also
provided which includes a range of ecological
design strategies.
Too far from beaches and river Noosa Shire includes a range of accommodation
types which are located within varying distances
Unsuitable site for development
of the beach and river.
Inappropriate commercial development
Under the Noosa Plan 2006 the site was zoned
impacting on the quality of residents'
Open Space Recreation. The site is zoned
lifestyle who purchased in the area
Tourist Accommodation under the Noosa Plan
believing no further development was
2020 with the change being communicated
possible.
through the public consultation process on
Any unanticipated development requires Noosa Plan.
demonstration of a high level of
The Noosa Plan 2020 requires that the site be
community need.
protected for the purpose of a resort
An overriding need in the public interest for complex or short-term accommodation to the
the development which would justify its general exclusion of permanent residents.
inconsistent use, planning conflicts,
destruction of habitat, loss of scenic
amenity and additional external pressure
on the Noosa region, particularly during
peak tourism periods. Eg. Increased
Vehicle Traffic.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 75
The developers are potentially "double-
dipping" as the land originally earmarked
for a hotel was used to build Parkridge.
The application is contrary to the stated
strategic and general principles of the
Noosa Shire Planning Scheme
Koala habitat The applicant has amended the application so that
the koala trees within the state mapped core koala
Inappropriate setbacks result in tree
habitat area.
removal
Council’s glossy black-cockatoo sighting mapping
Glossy black cockatoos are known to use
identifies that the subject land lies within an area
the site
that is not considered to be of importance for
glossy black-cockatoo. Areas to the north and
east are of value for this species. The terrestrial
ecology assessment located 1 glossy black within
2 km’s of the site. Offset planting will include the
planting of glossy black feed trees within the
landscaping.
The proposal complies with setback requirements
with the exception of the two level car park which
is to be constructed over the existing carpark
hardstand.
Overdevelopment The proposal is consistent with the site cover and
plot ratio requirements for the zones.
Fire – escape routes, emergency vehicles The application material has included a Bushfire
ability to enter the site Hazard Assessment and a Bushfire Management
Plan. Both documents have been reviewed by
Council’s consulting bushfire expert who is
satisfied that the development and associated
reports adequately address bushfire risk.
Setbacks 0m to rear boundary The proposal does include a two level carpark
which is situated adjacent to the western
Large carpark is not suitably screened
boundary, being the common boundary with the
golf course. A vegetated buffer is situated within
the golf course. There are considered to be no
amenity impacts on adjoining owners resulting
from the setback.
Inconsistent use within the Recreation and The extent of the mapped Recreation and Open
Open Space Zone Space Zone was intended to provide separation
between future development and odour impacts
Two thirds of the development is to be built
from the nearby sewage treatment plant. The
on land zoned "recreational and open
current application has ‘ground truthed’ the area
space"
appropriate for development via the provision and
subsequent review of odour impact reports.
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 76
Analysis should include impacts on all
Not a relevant planning consideration noting that
Noosa Springs Resort existing facilities –
the applicant is the owner of the land on which the
golf course, recreational and social
golf course and associated facilities are located.
facilities
No function centre is proposed within the hotel,
functions and conferences will continue to occur
within the Noosa Springs Golf and Spa Resort,
which is reflected in a condition within the
recommendation.
5. CONCLUSION & REASONS FOR DECISION
The application seeks to develop a of 106 room 5-star hotel on land within the existing Noosa
Springs development. The site is split zoned, with both the Tourist Accommodation Zone and the
Recreation and Open Space Zone affecting the site. The split zoning at the time sought to
recognise the need for a buffer distance (to mitigate potential odour impacts) associated with the
nearby sewage treatment plant (STP). Supporting documentation has assessed the odour impacts
of the STP to determine the appropriate building footprint and associated outdoor recreation areas.
This material has been reviewed and supported by Council’s consulting odour expert with
conditions recommended to address use of outdoor areas and ventilation of the building at its
interface with the accepted odour limit.
The proposed built form is consistent with the prevailing built form within Noosa Springs and
compliments the golf clubhouse and spa facilities which are located nearby. The building does
exceed the height limit due to the topography of the site and the large footprint anticipated in
buildings providing resort accommodation. Site cover does not exceed the combined amounts
permitted for both the Tourist Accommodation Zone and the Recreation and Open Space Zone
whilst the plot ratio complies with the requirements of the Tourist Accommodation Zone. The
application has also demonstrated compliance with the carparking, bushfire, and water
quality/quantity requirements of the Noosa Plan whilst variations to setbacks associated with the
two-level car park and elevated tennis courts are supported.
The application is recommended for approval subject to conditions.
Departments/Sections Consulted:
Mayor Community Services Corporate Services
Councillors Director Director
Community Development Financial Services
Chief Executive Officer Community Facilities Fleet
Executive Support Libraries & Galleries ICT
Local Laws Procurement
Waste & Environment Health Property
Revenue Services
Executive Services Development & Regulation Infrastructure Services
Director X Director Director
Community Engagement Building & Plumbing Services Asset Management
Customer Service X Development Assessment Buildings & Facilities
Governance Economic Development Civil Operations
People & Culture Environmental Services Disaster Management
X Strategic Land Use Planning Infrastructure Planning,
Design & Delivery
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Page 77
ATTACHMENT 3 - MCU21/0110 - PROPOSAL PLANS
IMPORTANT NOTES: REVISION DATE DESCRIPTION BY CLIENT DRAWING TITLE
1 04/09/20 FOR INFORMATION ST
Do not scale from drawings. All dimensions to be checked
on site before commencement of work. All discrepancies to 2
3
22/09/20
25/09/20
FOR INFORMATION
DA APPROVAL
ST
ST
NOOSA SPRINGS REAL ESTATE PTY COVER SHEET
be brought to the attention of the Architect. Larger scale
drawings and written dimensions take preference. This 4
drawing is copyright and the property of the author, and must 5
09/10/20
14/10/20
DA APPROVAL REVISED
DA APPROVAL REVISED
ST
ST
LTD
not be retained, copied or used without the express authority 6 04/11/20 COUNCIL PRESENTATION ST
Marchese Partners International Pty Ltd
of MARCHESE PARTNERS INTERNATIONAL PTY. LTD. 7 01/12/20 DA APPROVAL REVISED ST Level 14, 46 Edward Street. Brisbane, QLD 4000. Australia
8 21/04/22 UPDATED DA DRAW INGS BY P +61 7 3211 2600 F +61 7 3211 0297 E [email protected] PROJECT SCALE DATE DRAWN CHECKED
9 04/05/22 UPDATED RENDERS BY
www.marchesepartners.com
10 10/05/22 UPDATED DA DRAW INGS BY
NOOSA SPRINGS BOUTIQUE HOTEL 09/02/23 BY ST
FOR APPROVAL 11 09/02/23 UPDATED DA DRAW INGS LC Sydney · Brisbane· Melbourne · Adelaide
Kuala Lumpur · Auckland · Christchurch · London · Madrid JOB DRAWING REVISION
ABN 33 590 578 323
NOT FOR CONSTRUCTION 20079 DA0.01 11
Document Set ID: 22048375
22309820
Version: 34,
32,
1, Version
VersionDate:
Date:15/02/2023
05/07/2023
24/10/2023
Page 78
IMPORTANT NOTES: REVISION DATE DESCRIPTION BY CLIENT DRAWING TITLE
1 04/09/20 FOR INFORMATION ST
Do not scale from drawings. All dimensions to be checked
on site before commencement of work. All discrepancies to 2
3
22/09/20
25/09/20
FOR INFORMATION
DA APPROVAL
ST
ST
NOOSA SPRINGS REAL ESTATE PTY SITE IMAGE
be brought to the attention of the Architect. Larger scale
drawings and written dimensions take preference. This 4
drawing is copyright and the property of the author, and must 5
09/10/20
14/10/20
DA APPROVAL REVISED
DA APPROVAL REVISED
ST
ST
LTD
not be retained, copied or used without the express authority 6 04/11/20 COUNCIL PRESENTATION ST
Marchese Partners International Pty Ltd
of MARCHESE PARTNERS INTERNATIONAL PTY. LTD. 7 01/12/20 DA APPROVAL REVISED ST Level 14, 46 Edward Street. Brisbane, QLD 4000. Australia
8 09/02/23 UPDATED DA DRAW INGS LC P +61 7 3211 2600 F +61 7 3211 0297 E [email protected] PROJECT SCALE DATE DRAWN CHECKED
www.marchesepartners.com
NOOSA SPRINGS BOUTIQUE HOTEL 09/02/23 BY ST
FOR APPROVAL Sydney · Brisbane· Melbourne · Adelaide
Kuala Lumpur · Auckland · Christchurch · London · Madrid JOB DRAWING REVISION
ABN 33 590 578 323
NOT FOR CONSTRUCTION 20079 DA0.06 8
Document Set ID: 22048375
22309820
Version: 34,
1, Version
32, VersionDate:
Date:15/02/2023
05/07/2023
24/10/2023
Page 79
LEGEND
OPEN SPACE RECREATION ZONE
TOURIST ACCOMMODATION ZONE
2.5 OU CONTOUR
IMPORTANT NOTES: REVISION DATE DESCRIPTION BY CLIENT DRAWING TITLE
1 14/10/20 DA APPROVAL REVISED ST
Do not scale from drawings. All dimensions to be checked
on site before commencement of work. All discrepancies to 2
3
01/12/20
09/02/23
DA APPROVAL REVISED
UPDATED DA DRAW INGS
ST
LC
NOOSA SPRINGS REAL ESTATE PTY COUNCIL ZONING MAP OVERLAY
be brought to the attention of the Architect. Larger scale
drawings and written dimensions take preference. This
drawing is copyright and the property of the author, and must
LTD
not be retained, copied or used without the express authority
Marchese Partners International Pty Ltd
of MARCHESE PARTNERS INTERNATIONAL PTY. LTD. Level 14, 46 Edward Street. Brisbane, QLD 4000. Australia
P +61 7 3211 2600 F +61 7 3211 0297 E [email protected] PROJECT SCALE DATE DRAWN CHECKED
www.marchesepartners.com 1 : 500 @A1
NOOSA SPRINGS BOUTIQUE HOTEL 09/02/23 BY ST
FOR APPROVAL Sydney · Brisbane· Melbourne · Adelaide
Kuala Lumpur · Auckland · Christchurch · London · Madrid JOB DRAWING REVISION
ABN 33 590 578 323 0 5 10 20
NOT FOR CONSTRUCTION 20079 DA0.07 3
Document Set ID: 22048375
22309820
Version: 34,
1, Version
32, VersionDate:
Date:15/02/2023
05/07/2023
24/10/2023
Page 80
LEGEND
1 NEW HOTEL
2 POOL
3 NEW HOTEL ENTRY ROOF
4 TENNIS COURT WITH EXISTING ON-GRADE CAR PARK
BELOW
5 TENNIS PAVILION
6 AMENITIES
7 LINKS DRIVE
8 RESORT DRIVE
9 EXISTING COUNTRY CLUB
10 EXISTING DAY SPA & GYMNASIUM
11 EXISTING POOL
12 FIRE PIT
13 NEW 2 LEVEL CARPARK WITH EXISTING LOWER CAR
PARK BELOW
14 EXISTING MID CAR PARK
15 EXISTING UPPER CAR PARK
16 EXISTING PORTE-COCHERE
1
17 EXISTING PORTE-COCHERE ROOF
DA3.03 18 PEDESTRIAN ACCESS TO PORTE COCHERE
HATCH ZONE INDICATES MSES
FROM MID CAR PARK
1 ENVIRONMENTAL VALUES
19 NEW PORTE COCHERE ROOF
DA3.01 GREEN DASH INDICATES 20 EXISTING PORTE COCHERE ROOF EXTENSION
DA4.03
AREA OF BIODIVERSITY 21 SERVICE ACCESS TO POOL PLANT + WATER TANKS
SIGNIFICANCE 22 PLATEAU
23 SERVICE ROAD WAY EXTENSION
1 24 EXISTING SERVICE LANEWAY
2 25 EXISTING LOADING BAY
33 DA3.03 26 EXISTING SITE ACCESS
27 EXISTING MANHOLE AT PORTE-COCHERE LEVEL
8 28 EXISTING BUGGY PARKING
8305
29 EXISTING BUS PARKING
0
753
30 EXISTING BRIDGE CONNECTION
31 POOL PLANT BELOW
DA4.02 2 32 TENNIS COURT SHADE STRUCTURE
19 X CARPARKS
34 WITH SEATING BELOW
33 CONTROLLED GATE TO OVERFLOW CARPARKING
2.5 OU CONTOUR
34 REINFORCED TURF OVERFLOW CARPARKING / MULTI-
40
PURPOSE SPACE.
40
35 PEDESTRIAL ACCESS TO CLUBHOUSE
36 JACUZZI
37 68,000 LITRE WATER TANK BELOW
1 38 SOLAR PANEL CARPORT ROOFS
37
40 2.5 OU CONTOUR
1 SITE BOUNDARY
1 EXISTING EASEMENT
2 DA3.03
2 EXISTING SEWER LINE
6 23 MSES ENVIRONMENTAL VALUES
2 AREA OF BIODIVERSITY SIGNIFICANCE
1 1 DA3.03
2 1 1
DA3.02 DA3.02
SERVICE ROAD TO BE A
22 34 MINIMUM 3.5m WIDE
DA4.03 2 1
2 19 x CARPARKS
36 (INCLUDES 4xPWD) 33
2
0
12
350
2
DA3.02 1
3 2 37
DA2.04 DA2.04
156
35 31
21 11
SERVICE ROAD TO BE A
32 MINIMUM 3.5m WIDE
DA2.03 6
DA4.02 1 10
4 4 1 28
24
15
5
3
20
30
6 35
3 4
19 27
4 4 2
14
32 DA4.02 DA4.02 DA3.02
18
26
3 2
25
DA2.04 DA2.04
17
26
7 DA2.03 16 9
1
1
29 DA3.01
3 DA2.03
DA2.03 4 38
13
38
2
PORTE COCHERE TO BE RENOVATED TO
ENSURE 4.3M HEIGHT CLEARANCE FOR
DA2.03 VEHICLE ACCESS
IMPORTANT NOTES: REVISION DATE DESCRIPTION BY CLIENT DRAWING TITLE
1 04/09/20 FOR INFORMATION ST
Do not scale from drawings. All dimensions to be checked
on site before commencement of work. All discrepancies to 2
3
22/09/20
25/09/20
FOR INFORMATION
DA APPROVAL
ST
ST
NOOSA SPRINGS REAL ESTATE PTY SITE PLAN
be brought to the attention of the Architect. Larger scale
drawings and written dimensions take preference. This 4
drawing is copyright and the property of the author, and must 5
09/10/20
14/10/20
DA APPROVAL REVISED
DA APPROVAL REVISED
ST
ST
LTD
not be retained, copied or used without the express authority 6 04/11/20 COUNCIL PRESENTATION ST
Marchese Partners International Pty Ltd
of MARCHESE PARTNERS INTERNATIONAL PTY. LTD. 7 01/12/20 DA APPROVAL REVISED ST Level 14, 46 Edward Street. Brisbane, QLD 4000. Australia
8 19/10/21 CARPARK DESIGN ST P +61 7 3211 2600 F +61 7 3211 0297 E [email protected] PROJECT SCALE DATE DRAWN CHECKED
9 12/11/21 RFI ST
www.marchesepartners.com 1 : 500 @A1
10 04/03/22 DA REVISED DESIGN ST
NOOSA SPRINGS BOUTIQUE HOTEL 09/02/23 AB BY
FOR APPROVAL 11
12
13
13/04/22
21/04/22
09/02/23
REVISED DESIGN
UPDATED DA DRAW INGS
UPDATED DA DRAW INGS
BY
BY
LC
Sydney · Brisbane· Melbourne · Adelaide
Kuala Lumpur · Auckland · Christchurch · London · Madrid JOB DRAWING REVISION
ABN 33 590 578 323 0 5 10 20
NOT FOR CONSTRUCTION 20079 DA1.00 13
Document Set ID: 22048375
22309820
Version: 34,
1, Version
32, VersionDate:
Date:15/02/2023
05/07/2023
24/10/2023
The text continues on page 81.