Original source · versioned page text
FURTHER REPORT - Planning & Environment Committee 6 May 2025 MCU21/0110
Currency Period
7. This development approval lapses if the use has not happened by 20 July 2029 unless
an application to extend the currency period is approved by Council.
Ventilation
8. All internal use areas of the accommodation use including hotel suites, common areas,
office, dining, bar and lobby areas shall be fully air-conditioned, allowing external
façade elements (doors and windows) to be closed if required. Fresh air makeup to the
air conditioning systems must be drawn from roof level locations located as far as
practical from the Noosa Wastewater Treatment Plant.
9. Activated carbon filtration to be installed on all fresh air makeup locations of the
air conditioning systems and are regularly maintained to manufacturer specifications.
Outdoor Use Areas – swimming pools and tennis courts
10. Use by guests and visitors of the tennis courts, is limited to the time period 6am to
10pm only.
11. Use by guests and visitors of the swimming pools located to the north of the proposed
buildings as identified in Plate 1 (not including the outdoor area between the proposed
buildings) is limited to the time period 6am to 12am only.
Acoustic
12. An updated acoustic report must be submitted to Council prior to the issue of an
Operational Works approval. The amended acoustic report must include
recommendations to address the impact on the residential amenity attributed to use of
the loading docks, including the noise associated with vehicles and trucks accessing
and using the loading docks. The recommendations of the acoustic report must be
implemented prior to the commencement of the approved uses.
Odour
13. All guests must be advised of the potential for odour from the sewage treatment plant
to be noticeable.
14. The operator must maintain an Odour Complain Management Plan, with the plan
including the internal management of any complaints from hotel guests. The Odour
Management Plan must be submitted to Council prior to the issue of an Operational
Works approval.
Built Form and Development Appearance
15. The maximum height of the development must be in accordance with the approved
plans.
16. Certification must be submitted to Council from a Licensed Surveyor which certifies
that the buildings do not exceed the maximum height requirement of this Decision
Notice.
17. All air conditioning units or other mechanical equipment must be fully enclosed or
screened such that they are not visible from the street frontages nor adjoining
properties.
18. All deck and balcony areas above ground floor must not be enclosed by permanent
fixtures such as shutters, louvres, glass panelling or the like.
19. The development must incorporate the colour scheme and proposed mix of building
materials as outlined in the approved plans.
20. Any security screens on the premises consist of grille or translucent screens and not
solid shutters, screens or roller-doors.
21. All mechanical equipment and other service infrastructure located on the site must be:
Document Set ID: 22048375
Version: 34,
32, Version Date: 24/10/2023
05/07/2023
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.