Original source · versioned page text
SUPERSEDED - Amended Decision Notice - MCU22 0194 [As Published]
i. contact details for the on-site manager; and
ii. dispute resolution procedures.
9. It is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed to
construct the works and a final document will be required to be submitted at the Pre-Start
Meeting for the project.
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Road work, Stormwater, Drainage work,
Earthworks, Landscaping,
Development Permit for Building Works All building work.
10. SUBMISSIONS
Not applicable.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Nadine Gorton
Acting Coordinator Planning
Page 9 of 33
Document Set ID: 22544890
Version: 1, Version Date: 16/08/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.