Bushfire Hazard Assessment & Management Plan v2 NCES REF: J001445
434 Lake Cooroibah Rd Lake Cooroibah, QLD
Table 2 – Table 8.2.3.3 Bushfire Hazard Areas – Part 8 Overlay Code Noosa Plan 2020
PERFORMANCE OUTCOMES ACCEPTABLE OUTCOMES PROPOSED SOLUTION
Safety of people and property
PO1 AO1.1 This Bushfire Hazard Assessment and Management Plan has been prepared to
Development maintains the safety of people and Development which will materially increase the number of people maintain the safety of people and property from the adverse impacts of bushfire.
property from the adverse impacts of bushfire. living or congregating on premises, including reconfiguring a lot, is not
AO1.1 – No increase in the number of people living or congregating on premises
located within a medium or high bushfire hazard area.
is proposed within a confirmed medium or high bushfire hazard area.
AO1.2
Development maximises setbacks from hazardous vegetation to AO1.2 –The extent of separation proposed in conjunction with the mitigating
achieve an acceptable risk. measures referenced within this report generates an acceptable risk.
Editor’s Note —PSP8 Natural Hazards provides guidance for
assessing bushfire hazard risk and preparing a bushfire hazard
management plan.
Impact on Ecologically Important Areas
PO2 No acceptable outcome provided No new clearing is deemed necessary to enact bushfire mitigation measures on
Bushfire mitigation measures do not adversely impact the site.
on:
a) biodiversity values, connectivity and ecosystem
functioning; and
b) the long term physical integrity of waterways, wetland
and areas of native vegetation.
Water Supply for Fire Fighting Purposes
PO3 AO3.1 AO3.1 – Lot 7 will not be connected to the reticulated water supply. The new
Development provides an adequate water supply for Premises are connected to the reticulated water supply. water supply to Lot 7 should therefore satisfy Assessment Benchmark 4 of the
firefighting purpose which is reliable, safely located and SPP Bushfire 2019, which references the QFES 2019 Bushfire Resilient
freely accessible. Editor's note—For reconfiguring a lot, water supply needs to provide Communities. Provision of 10,000 litres supply located within 10 metres of each
for a minimum flow and pressure of 10 litres a second at 200kPa at all residential building on the lot is required.
times for firefighting purposes.
OR
AO3.2
Where there is no available reticulated water supply, the premises
has:
a) an accessible dam, swimming pool or water tank available for
firefighting purposes with an onsite water volume of not less than
5,000 litres; and
b) a water supply outlet pipe 50 millimetres in diameter fitted with a
standard fire brigade fitting connected to the water supply (other than
where the water supply is in a swimming pool or dam).
Document Set ID:©24816699
2026 28
Version: 1, Version Date: 25/05/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - RAL26 0015 - Bushfire Hazard Assessment (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.